Q
Which is the following are correct in relation to DSDM?
- It is the proven framework for Agile project management and delivery
- Its helps deliver results quickly and effectively
- It can be applied to small projects
- It has always maintained a strong focus on the corporate project- based environment A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (1.1) - - - correct answer ✅C Q Which is the following are correct in relation to DSDM?
- It is the proven framework for Agile project management and delivery
- Its helps deliver results quickly and effectively
And Answers
- It can be applied to small projects and full-scale business change
- It has always maintained a strong focus on the corporate project- based environment A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (1.1) - - - correct answer ✅D Q Which is the following is correct in relation to DSDM?
- It was created in 1994 by practitioners from several companies
- It was designed to build quality into the existing RAD process
- The contributing companies formed the DSDM Corporation
- DSDM is now universally available, free to view and use A. 1 & 2 only B. 2 & 3 only
And Answers
C. 1, 2 & 4 only D. All of the above (1.1) - - - correct answer ✅D Q Which is the following is correct in relation to DSDM?
- It was created in 1994 by practitioners from RAD
- It was designed to build quality into the existing RAD process
- The contributing companies formed the DSDM Corporation
- DSDM is now universally available for a small fee A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (1.1) - - - correct answer ✅B Q
And Answers
Which is the following is correct in relation to AgilePF?
- It is an evolution of DSDM Atern®
- It provides essential information to DSDM role holders information to enable any role as created in 1994 by practitioners
- It retains DSDM's project principles, roles and responsibilities The contributing companies formed the DSDM Corporation
- It embraces the DSDM practices to establish and demonstrate control A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (1.2) - - - correct answer ✅D Q Which is the following is correct in relation to AgilePF?
- It is an evolution of DSDM Atern®
- It provides essential information to DSDM role holders
And Answers
information to enable any role as created in 1994 by practitioners
- It removes DSDM's project principles, roles and responsibilities The contributing companies formed the DSDM Corporation
- It adapts the DSDM practices to establish and demonstrate control A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (1.2) - - - correct answer ✅A Q Which is the following is correct in relation to AgilePF?
- At the delivery level, the DSDM process has been simplified
- It reflects current trends in evolutionary solution development
- The most significant change is in the area of the processes
- Its streamlined products now aligns with the Agile philosophy
And Answers
A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (1.2) - - - correct answer ✅C Q Which is the following is correct in relation to AgilePF?
- At the delivery level, the DSDM process has been simplified
- It reflects current trends in evolutionary solution development
- The most significant change is in the area of the products
- Its streamlined products now aligns with the Agile philosophy A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (1.2) - - - correct answer ✅D
And Answers
Q
Which is the following is correct in relation to AgilePF?
- At the delivery level, the DSDM process has been simplified
- It reflects current trends in evolutionary solution development
- The most significant change is in the area of the processes
- Its streamlined processes now aligns with the Agile philosophy A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (1.2) - - - correct answer ✅A Q What are the benefits of using DSDM?
- It protects the quality of what is being delivered
- The risk of building the wrong solution is greatly reduced
- It involves the business stakeholders in the early stages
And Answers
- Prioritisation enables a project to be delivered on budget A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (2.6) - - - correct answer ✅A Q What are the benefits of using DSDM?
- It protects the quality of what is being delivered
- The risk of building the wrong solution is greatly reduced
- It involves the business stakeholders throughout the project
- Prioritisation enables a project to be delivered on time A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above.
And Answers
(2.6) - - - correct answer ✅D Q What are the benefits of using DSDM?
- It protects the integrity of what is being delivered
- The risk of building the wrong solution is greatly reduced
- The ultimate solution is more likely to meet the real business need
- Development is more likely to go smoothly A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (2.6) - - - correct answer ✅B Q What are the benefits of using DSDM?
And Answers
- It protects the quality of what is being delivered
- The risk of building the wrong solution is greatly reduced
- The ultimate solution is more likely to meet the real business need
- Deployment is more likely to go smoothly A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above. (2.6) - - - correct answer ✅D Q Which of the following are the elements on which an effective Solution Development Team (SDT) are built? A. Employability, Stability, Skills, Sense B. Empowerment, Scalability, Skills, Size C. Empowerment, Stability, Skills, Size D. Employability, Scalability, Skills, Sense
And Answers
(5.3) - - - correct answer ✅C Q Which of the following are correct in relation to the Solution Development Team (SDT)?
- They are instrumental in the development of the right solution
- Individuals can make decisions based on their own expertise
- The team can make decisions within the agreed boundaries
- Senior stakeholders need to ensure they appoint the right people A. 1 & 2 only B. 2 & 3 only C. 1, 3 & 4 only D. All of the above. (5.3) - - - correct answer ✅D Q Which of the following are correct in relation to the Solution Development Team (SDT)?
- They are instrumental in the development of the business case
And Answers
- Individuals can make decisions within the agreed boundaries
- They are expected to make day-to-day decisions
- Senior stakeholders needs to ensure they appoint the right people A. 1 & 2 only B. 2 & 3 only C. 1, 3 & 4 only D. All of the above. (5.3) - - - correct answer ✅C Q Which of the following are correct in relation to the Solution Development Team (SDT)?
- The project could be put at risk if team members are changed
- Its members should have good communication skills
- They need core business knowledge and technical expertise
- They need to be able to work with others A. 1 & 2 only
And Answers
B. 2 & 3 only C. 1, 3 & 4 only D. All of the above. (5.3) - - - correct answer ✅D Q Which of the following are correct in relation to the Solution Development Team (SDT)?
- The project could be put at risk if team members are changed
- Its members should have good communication skills
- They need basic business knowledge and common sense
- There is no limit suggested for the size of the team A. 1 & 2 only B. 2 & 3 only C. 1, 3 & 4 only D. All of the above. (5.3) - - - correct answer ✅A
And Answers
Q
What is the optimum size of a Solution Development Team (SDT)? A. 5 (+/- 2 people) B. 6 (+/- 2 people) C. 7 (+/- 2 people) D. 8 (+/- 2 person) (5.3.4) - - - correct answer ✅C Q Which series of words correctly complete the DSDM philosophy? "best business value emerges when projects are .............. to clear business goals, deliver ............... and involve the collaboration of ................... and ................. people." A. aligned, frequently, motivated, empowered B. connected, timely, motivated, skilful C aligned, timely, partners, empowered D. connected, frequently, partners, skilful
And Answers
(5.2) - - - correct answer ✅A Q Which series of words correctly complete the DSDM philosophy? "best business value emerges when projects are .............. to clear business goals, deliver ............... and involve the collaboration of ................... and ................. people." A. aligned, timely, partners, empowered B. connected, timely, motivated, skilful C. aligned, frequently, motivated, empowered D. connected, frequently, partners, skilful (5.2) - - - correct answer ✅C Q Which of the following are true in relation to the ISF of "Embracing the DSDM Approach"?
- It includes embracing the DSDM Philosophy
- It must be accepted by all project stakeholders
- Participants must understand and accept the DSDM approach
And Answers
- It includes accepting less than 100% of the solution A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 3 only D. All of the above (5.2) - - - correct answer ✅D Q Which of the following are true in relation to the ISF of "Embracing the DSDM Approach"?
- It includes embracing the DSDM Philosophy
- It must be accepted by all project stakeholders
- Participants must understand and accept the DSDM approach
- It includes accepting nothing less than 100% of the solution A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 3 only D. All of the above
And Answers
(5.2) - - - correct answer ✅C Q Which of the following are true in relation to the ISF of "Embracing the DSDM Approach"?
- It includes embracing the DSDM Philosophy
- It must be accepted by all project stakeholders
- It includes getting things right first time
- It includes accepting nothing less than 100% of the solution A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 3 only D. All of the above (5.2) - - - correct answer ✅A Q Finish the sentence. "An organisation amenable to incremental delivery of solutions into live use will benefit from........"
And Answers
A. An early return on investment. B. An early reduction in project risk. C. An early deployment of the solution. D. An early end to the project. (5.5) - - - correct answer ✅A Q Finish the sentence. "Each Timebox should ideally deliver a complete, potentially deployable increment of the solution even though ......"? A. It may not be fully integrated B. There may be significant overheads associated with it C. The organisation is not amenable to incremental delivery D. There may not be enough at that point in time to physically deploy it. (5.5) - - - correct answer ✅D Q
And Answers
Which of the following are true in relation to the ISF of "Iterative Development, Integrated Testing and Incremental Delivery"
- Each Timebox should ideally deliver a complete, potentially deployable increment of the solution
- Testing is key to reducing risks and the success of the project
- Incremental delivery into live use results in an early RoI
- Each increment should result in a deployment A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 3 only D. All of the above (5.5) - - - correct answer ✅C Q Which of the following are Instrumental Success Factors (ISF's)?
- Embracing the DSDM Approach
- Effective Solution Development Team
- Business Engagement - Active and On-Going
And Answers
- Transparency A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (5.2-6) - - - correct answer ✅D Q Which of the following are Instrumental Success Factors (ISF's)?
- Embracing the Iterative Approach
- Effective Solution Development Team
- Business Engagement - Active and On-Going
- Transparency A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above
And Answers
(5.2-6) - - - correct answer ✅B Q30 Which of the following are Instrumental Success Factors (ISF's)?
- Embracing the DSDM Approach
- Effective Solution Development Team
- Business Collaboration - Active and On-Going
- Iterative Development, Integrated Testing and Incremental Delivery A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (5.2-6) - - - correct answer ✅C Q31 Which of the following are true in relation to the absence of Instrumental Success Factors (ISF's)?
And Answers
- They could impact on the positive outcome of the project
- They must be identified as early as possible and mitigated
- Their absence is considered an acceptable risk
- Without them, the DSDM approach will not offer a reduced risk compared to other approaches A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (5.1) - - - correct answer ✅A Q32 Which of the following are true in relation to the absence of Instrumental Success Factors (ISF's)?
- They could impact on the positive outcome of the project
- They must be identified as early as possible and mitigated
- Their absence is considered a significant risk
- Without them, the DSDM approach will still offer a reduced risk compared to other approaches
And Answers
A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (5.1) - - - correct answer ✅D Q33 Which of the following are true in relation to the absence of Instrumental Success Factors (ISF's)?
- They could impact on the positive outcome of the project
- They must be identified as early as possible and mitigated
- Their absence is considered an acceptable risk
- Without them, the DSDM approach will still offer a reduced risk compared to other approaches A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above
And Answers
(5.1) - - - correct answer ✅C Q34 Which of the following are true in relation to the ISF of "Transparency"?
- It can involve Team Boards and Daily Stand-ups
- It can include demonstrations of the evolving solution
- It underpins the demonstration of control
- It can include information on the current state of work A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (5.6) - - - correct answer ✅D Q35 Which of the following are true in relation to the ISF of "Transparency"?
And Answers
- It can involve Team Boards and Daily Stand-ups
- It can include demonstrations of the evolving solution
- It underpins the demonstration of collaboration
- It can include information on the current state of work A. 1 & 2 only B. 2 & 3 only C. 1, 2 & 4 only D. All of the above (5.6) - - - correct answer ✅C Q36 Finish the sentence. "The earlier a defect is found....."? A. The easier and cheaper it is to fix B. The earlier the Timebox can be closed C. The earlier the risks can be addressed D. The easier the deployment will be (9.3) - - - correct answer ✅A