Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
CDT practice exam Questions with 100% Correct Answers | Verified | Latest Update 2024 The method of computation of Contractor's overhead and profits for Change Order prices, where both additions and deletions are involved, is found in the: - Correct Answer-conditions of the contract General Requirements are part of: - Correct Answer-Specifications The three essential considerations in the evaluation of a product are - Correct Answer-Requirements, Criteria, and Tests Whose responsibility is it to furnish the Shop Drawings - Correct Answer-The Contractor The division of the Work among multiple prime Contracts is described in: a) Instructions to Bidders. b) Supplementary Conditions. c) Division 01. d) Special Conditions. - Correct Answer-c) Division 01.
Typology: Exams
1 / 23
The method of computation of Contractor's overhead and profits for Change Order prices, where both additions and deletions are involved, is found in the: - Correct Answer- conditions of the contract General Requirements are part of: - Correct Answer- Specifications The three essential considerations in the evaluation of a product are - Correct Answer-Requirements, Criteria, and Tests Whose responsibility is it to furnish the Shop Drawings - Correct Answer-The Contractor The division of the Work among multiple prime Contracts is described in: a) Instructions to Bidders.
b) Supplementary Conditions. c) Division 01. d) Special Conditions. - Correct Answer-c) Division 01. During the Project Conception Stage, the A/E may be retained to: a) Develop outline specifications b) Describe the character of the mechanical system c) Prepare renderings d) Assist in financial feasibility studies - Correct Answer-d) Assist in financial feasibility studies The person who becomes secondarily liable for another's debt or performance is called the: a) Guarantee b) Warrantor c) Guarantor d) Warrantee - Correct Answer-c) Guarantor What is the main purpose of MasterFormat?
a) for scheduling, value management, recording of design data and managing costs. b) used during the planning stage of a project. c) to organize the Project Manual, reference keynotes and detailed cost estimates. d) when there is a standardized need for information to appear upon each page of a project manual. - Correct Answer- c) to organize the Project Manual, reference keynotes and detailed cost estimates. Integrated projects are distinguished by all of the following characteristics except: a) Development of virtual project model through input from a collaborative team b) Trust-based collaboration between project team members c) Maximized efficiency through design, fabrication, and construction d) "Just as needed" team involvement to reduce owner's pre- construction expenses - Correct Answer-d) "Just as needed" team involvement to reduce owner's pre-construction expenses Outline Specifications are written for
a) only Divisions 02-14 where actual products are discussed b) Divisions 01- c) only Divisions 01-14 (excluding mechanical and electrical) d) the exclusive use of the A/E - Correct Answer-b) Divisions 01- An example of a MasterFormat Level 3 specification Section is: a) 05 00 00 Metals. b) 05 20 00 Metal Joists. c) 05 21 00 Steel Joist Framing. d) 05 21 19 Open Web Steel Joist Framing - Correct Answer-d) 05 21 19 Open Web Steel Joist Framing What activities take place in the Project Conception Stage? a) The engineers develop the mechanical and electrical systems. b) The site is selected and the demolition is done. c) Feasibility studies and budget is set. d) The program is evaluated and the engineers are selected. - Correct Answer-c) Feasibility studies and budget is set.
The document recommended to organize preliminary construction information into a standard order on the basis of systems and assemblies is: a) MasterFormat b) Uniformat c) Outline Specifications d) Project Manual - Correct Answer-b) Uniformat All design and construction drawings can be classified as one of two types of views: a) Numeric and graphic. b) Vertical and horizontal. c) Scaled and nonscaled. d) Exterior and interior - Correct Answer-c) Scaled and nonscaled. Substitution requirements and procedures during bidding a) Are not allowed under most public bidding statutes. b) Are modified by the Supplementary Conditions. c) Are stated in the Instructions to Bidders.
d) Are provided by requests by telephone. - Correct Answer-c) Are stated in the Instructions to Bidders. Submittal requirements for Mechanical and Electrical work are specified in: a) General Conditions b) Supplementary Conditions c) Division 01 d) Division 22 and 26 - Correct Answer-c) Division 01 The Procurement Requirements are a) a part of the Procurement Documents, but not the Contract Documents. b) a part of the Contract Documents. c) a part of the Procurement Documents but not the Project Manual. d) in the same part as the Contract Modifications. - Correct Answer-a) a part of the Procurement Documents, but not the Contract Documents. Since he or she is most familiar with a product, the manufacturer's representative should:
a) Write the specification section. b) Review the specification section. c) Supply accurate information to the A/E d) Not be consulted in order to avoid a conflict of interest. - Correct Answer-c) Supply accurate information to the A/E Which of the following requires a Change Order? a) Extension of bid date. b) Modification of the Work. c) Revision of Bidding Documents affecting construction cost. d) Revision of Bidding Documents affecting completion time. - Correct Answer-b) Modification of the Work. Experienced owners may require project teams to utilize integrated project delivery based upon: a) Increased coordination of construction documentation. b) Desire Greater prefabrication opportunities. c) Optimized site utilization. d) All of the above. - Correct Answer-d) All of the above. The Conditions of the Contract include
a) Contract Forms, General Conditions, and Supplementary Conditions. b) General Conditions and Supplementary Conditions. c) General Conditions, Supplementary Conditions, and Division 01. d) Documents within the project manual, except the Bidding Requirements. - Correct Answer-b) General Conditions and Supplementary Conditions. The mood that is recommended for specifications is: a) The imperative mood b) The indicative mood c) The symbolic mood d) None of the above - Correct Answer-a) The imperative mood
What are the three components of project design team coordination? a) Duplication, omissions and discrepancies b) Division One, Division Two and Division Three c) General, Products and Execution d) Organization, Execution and Quality Assurance - Correct Answer-d) Organization, Execution and Quality Assurance The burden of performance is assumed by whom when a descriptive specification is used? a) Manufacturer b) Contractor c) Architect/Engineer d) Owner - Correct Answer-c) Architect/Engineer Which of the following is TRUE concerning application of integrated project delivery? a) Mutual benefit and reward, and because of early involvement, compensation based on the value added and what's best for the project.
b) Collaborative team effort reduces planning and design expenses. c) Determination of liability for decisions is generally made by the team leader in order to reduce arbitration expenses. d) Technologies such as data exchange protocols evolve on a phase-by-phase basis. - Correct Answer-a) Mutual benefit and reward, and because of early involvement, compensation based on the value added and what's best for the project. The construction subcontracts a) are the contracts between the owner and the contractor. b) are the contracts between the owner and the construction manager. c) are the contracts between the contractor and the A/E. d) are the contracts between the contractor and the subcontractors. - Correct Answer-b) are the contracts between the owner and the construction manager. Owner occupancy of the premises during construction: a) Should not be specified in section covering temporary facilities b) Is specified in Section 01 10 00 Summary.
c) Is not a concern of the specifier. d) Precludes Contractor's use of existing facilities such as stairs, elevators and sanitary facilities. - Correct Answer-b) Is specified in Section 01 10 00 Summary. The Invitation to Bid: a) contains detailed requirements for submittal of bids. b) legally defines the Contract Documents for a project. c) is designed to attract qualified bidders. d) includes the Instructions to Bidders and the Bid Forms - Correct Answer-c) is designed to attract qualified bidders. During the bidding process: a) Bids may be discussed before the set time of their opening b) Subcontractors may not use Bid Depositories c) The Contractor should expect his potential Subcontractors to review those plans available in plan rooms. d) The bidder should be allowed to withdraw his bid before the specified time for receipt of bids. - Correct Answer-d) The bidder should be allowed to withdraw his bid before the specified time for receipt of bids.
Which of the following is considered as part of the specifications? a) General Conditions b) Supplementary Conditions c) Division 02-19 Facility Construction d) All of the above - Correct Answer-c) Division 02-19 Facility Construction
d) A system using not more than two decimal places to aid in filing an project identification - Correct Answer-b) A six and eight digit numbering system
c) Show which surfaces are to be finished d) Show Contractor what finished project is to look like - Correct Answer-b) Show their detailed arrangement
methods. - Correct Answer-c) CSI validates and certifies information contained in GreenFormat.
b) See specifications. c) See detail requirements in specifications. d) The practice is discouraged. - Correct Answer-d) The practice is discouraged.
d) Written in a manner to avoid Owner responsibilities - Correct Answer-c) Written in Division 01 to expand on provision in the Conditions of the Contract
d) alternates - Correct Answer-c) substitutions
c) are fixed for level 2 and level 3 sections but can be individually selected for level 4 sections d) are to be shifted as needed when level 4 sections are added