Download Understanding the Competitive Bidding Process and Specification Writing in Construction and more Exams Nursing in PDF only on Docsity! CDT-Practice Questions (specguy, et al) with 200+ correct question and answers Sheet keynote or reference keynote - >>>a notation on a single drawing sheet "A facility's "life cycle" includes all of the following EXCEPT: a. Project conception b. Financing c. Construction d. Facility management" - >>>1. b - PRM 1.4 Life cycle Stages: Conceptions, Delivery Method, Design, Psrocurement, Construction, What does CSI's UDS do ? what does it stand for ? - >>>UDS uniform drawing system CMa stands for... - >>>Construction Manager as Advisor "The objective of the competitive bidding process is: a. To ensure that all qualified bidders may submit bids on public work projects b. To ensure that public works contracts are always awarded to the lowest bidders c. To ensure that the intent of the governing public laws is maintained in the awarding of contracts d. To ensure that the cost of the project is reasonable and consistent with the prevailing conditions in the building industry" - >>>2. d - PRM 3.4 What is included in PART 3 of SectionFormat? - >>>PART 3- EXECUTION: describes field/site installation or application, including preparatory actions and post-installation cleaning and protection. Field/site- built assemblies and field/site-manufactured products and systems are included. "A unit price contract or contract portion is used when: a. Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated. b. Extent of work is known, but the owner desires a break-out cost for portions of the work. c. It is anticipated that bidders will not examine soil bearing reports prior to submitting bid. d. Bidding quantities of equipment. Review: PDPG 7.1.6.2" - >>>"a. Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated. Use of unit prices, allowances and alternates should always be limited to those items required for accurate bidding, in order to keep bidding documents and processes as simple as possible." "The contractual relationship governed by the Conditions of the Contract is between: a. Owner and contractor b. Architect/engineer and contractor c. Owner and Subcontractors d. Owner, contractor, and architect/engineer Review: PDPG 5.5 and 11.3.9" - >>>"a. Owner and contractor The owner and the contractor are the parties to the construction contract, hence they are subject to the Conditions of the Contract. Yes, the duties of the architect are described in the Conditions of the Contract, but they are governed by the separate Owner/Architect or Owner/Engineer Agreement." Review: PDPG 11.2.9" - >>>"c. Are expanded upon by the provisions of Division 01 The key word is ""expanded."" Division 01 General Requirements are detailed. They address administrative and procedural level issues. The Conditions of the Contract say: ""Do this."" The General Requirements say: ""Do it like this."" And don't forget the concept of ""complementary documents."" No provisions have priority over, are superseded by, or are independent of, other provisions in the contract documents - they are ""complementary.""" "In the specifications, the stated requirements address: a. The owner's responsibilities b. The contractor's responsibilities c. The subcontractor's responsibilities d. The architect's responsibilities e. All of the above Review: PDPG 11.3.4.3" - >>>"b. The contractor's responsibilities The owner and the contractor are the sole parties to the contract. The requirements of the specifications address the contractor. Other statements regarding owner and architect activities serve as information only." What defines substantial completion of the Work? - >>>when the Work, or designated portions of the Work, are sufficient complete in accordance with the Contract Documents such that the Owner may occupy or utilize the Work for its intended use. "When outside consultants are responsible for the production of major portions of the project specifications: a. One design team member should be responsible for overall specification coordination b. Different document formats should be used to identify the work of the separate consultants c. The lead design professional should avoid the liability inherent in reviewing consultants' work d. Information should be collected and the project A/E assume responsibility for preparing each section Review: PDPG 11.3.4.3" - >>>"a. One design team member should be responsible for overall coordination The project manual is the work of an entire team, but it is a unified document and must have one experienced individual reading and coordinating all content. This means no ""consultants will just email their sections directly to the print house.""" "Since he or she is most familiar with a product, the manufacturer's representative should: a. Write the specification section. b. Review the specification section. c. Supply information to the specification writer. d. Not be consulted in order to avoid a conflict of interest. Review: PDPG 11.3.4.2" - >>>"c. Supply information to the specification writer. The product representative is a valuable information source. They can supply information that could take hours to obtain elsewhere. They can help A/Es avoid errors in bid documents. However, their job is to sell products of their manufacturer. The specification writer must prepare a specification section in a way that treats other manufacturers fairly and are properly coordinated with the other bid documents." "Use of master guide specifications: a. Relies upon the quality of their update process b. Requires knowledge of the conditions of the contract for which they were prepared c. May be based upon a commercially-produced specification library d. Requires practice knowledge in order to properly create project specifications e. All of the above Review: PDPG 11.3.13" - >>>"e. All of the above In-house AE firm master specifications and commercial master guide specifications are the two most common sources for project specifications; in-house masters are frequently built upon commercial master guide specifications such as MasterSpec©, BSD SpecLink©, or SpecText©." Who issues the Certificate of Substantial Completion? - >>>the A/E "The following are TRUE about closed proprietary specifications EXCEPT: a. Manufacturer and product brand names or unique characteristics are used in the specifications. b. Several products may be named as options. c. The A/E must coordinate the named product with other specification requirements. d. Other products are allowed as substitutions upon approval of the owner. Review: PDPG 11.3.6.4" - >>>"d. Other products are allowed as substitutions upon approval of the owner. Closed proprietary specifications by definition do not allow substitutions of unnamed manufacturers/products." "Which of the following is NOT defined as a contract modification by the PDPG? "7. To be effective in communicating, specifications should be: a. Complete, concise, and correct b. Concise, clear, and correctc. C Clear, correct, complete, and concise d. Concise, correct, and complete" - >>>7. c - PRM 5.8 "6. The procurement documents include all of the following EXCEPT: a. Procurement requirements b. Contract modifications c. Project manual d. Drawings" - >>>6. b - PRM 5.1 "4. The specification-type document prepared during the design development phase is called the: a. Outline specification b. Rough draft specification c. UniFormat™ elements d. Cost estimate" - >>>4. a - PRM 4.9 "5. The contractual relationship governed by the conditions of the contract is between: a. Owner and contractor b. A/E and contractor c. Owner and subcontractors d. A/E and subcontractors" - >>>5. a - PRM 5.1 "3. Multiple-prime contracts are normally a part of: a. Turn-key construction b. Negotiated contracts c. Long duration construction projects d. Fast-track construction" - >>>3. d -PRM 3.4 "All of the following could be Articles in Part 1 of a specification EXCEPT: a. References b. Action Submittals c. Source Quality Control d. Measurement and Payment Review: PDPG Figure 11.13 and SectionFormat" - >>>"c. Source Quality Control An example of Source Quality Control is the special inspection for structural steel fabricators required under model building codes. This is specified in Part 2 - Products. The inspection of the jobsite installation of steel will be specified under the article Field Quality Control in Part 3 - Execution." "In the CSI CDT program, construction document production is defined to be all of the following EXCEPT: a. A separately-defined activity and phase that commences once design decisions have been made b. A process integral to the design phase of a project c. A component of the input into, and reporting out of, a BIM model d. An ongoing effort by many entities reflecting the collaboration and fast track delivery typical of modern construction projects Review: PDPG 1.2,2.3,3.4" - >>>"b. A process integral to the design phase of a project While the AIA, AGC, and EJCDC all define construction document production as part of a design phase, CSI draws a distinction between design and construction documentation. Make sure you do your reading from up to date CDT resources. This answer is different from what the previous resource, the Project Resource Manual (PRM) says. The PRM material has been rapidly overtaken by industry practices associated with design-build, IPD, and BIM. We're adjusting our study materials to reflect this change." "The nationally-recognized California AIA ""Integrated Project Delivery Guide"" redefines the stages of a project to include which of the following: a. Conceptualization b. Criteria Design c. Detailed Design d. Implementation Documents e. All of the above Review: PDPG 3.3" - >>>" e. All of the above Phases also include Agency Coordination, Buyout, Construction/Construction Contract Administration, and Closeout. This evolution from the more typical project stage framework integrates the commissioning process (commencing under Criteria Design) and realistically provides for multi-party collaboration that is part of IPD." "The goal of the project is defined by the PDPG as: a. Completion of the construction project on time and on budget b. The delivery of the facility to the owner c. Maximizing the benefit to the owner and the community d. Creating a facility with the lowest possible embedded energy Review: PDPG 1.5" - >>>"b. The delivery of the facility to the owner Review: PDPG 11.3.7.3 and MasterFormat Introduction and Applications Guide" - >>>"d. 05 21 19 Open Web Steel Joist Framing The MasterFormat numbering system is described in the PDPG section cited above and in the introductory pages in the MasterFormat document; understanding of the Levels concept used in applying MasterFormat is a valuable tool for specifiers." "The goal of the ASTM sustainability standards, the EPA Energy Star program, and the NIST BEES program is to: a. Serve as the basis for the development of national model code regulation of the use of building products b. Provide a rational assessment of the environmental impact of building products c. Promote emerging green buildng product businesses d. Simplify building design practices Yesterday's Review: PDPG 8.7.2 Environmental Design Tools and 8.7.3 Assessing Product Sustainability. " - >>>" b. Provide a rational assessment of the environmental impact of building products National sustainable model codes are developing, but the goal of these programs is clearly stated in the PDPG; other results such as the emergence of green building product businesses have been a secondary result of these technical undertakings." What is included in PART 2 of SectionFormat? - >>>PART 2-PRODUCTS : describes the systems, assemblies, equipment, fabrications, and mixes that are to be incorporated into the project. "Experienced owners may require project teams to utilize integrated project delivery based upon: a. Previous negative experience with adversarial project team relationships b. Desire for reduction in project claims and disputes c. Desire to utilize collaboratively-produced BIM as a facilities management asset d. Expectation of benefit from innovation stemming from collaborative effort e. All of the above Yesterday's Review: PDPG 7.7.2 The Nature of Integrated Project Delivery" - >>>e. All of the above - Collaboration involves a change in project team habits. More intensive planning requires dedication of owner resources. Owners willing to work and to contract for services in new ways are finding high payoffs in terms of technology utilization and lower ultimate construction costs. Under what circumstances can the Owner suspend the Work for Convenience? - >>>whenever s/he wants with written notice to the Contractor "Which of the following is TRUE concerning application of integrated project delivery? a. Collaborative team effort reduces planning and design expenses. b. Determination of liability for decisions is generally made by the team leader in order to reduce arbitration expenses. c. Technologies such as data exchange protocols evolve on a phase-by-phase basis. d. Team culture based upon problem resolution rather than determination of liability. Yesterday's Review: PDPG 7.7.2 The Nature of Integrated Project Delivery Delivery" - >>>d. Team culture based upon problem resolution rather than determination of liability. - IPD takes increased planning effort and expense, change in practice habits including risk management, early agreement on use of technology, and the ability to play multiple roles. Mutual efforts toward risk management and assignment of responsibility, as well as emphasis on collaborative action, seeks to minimize the isolation of risk and associated damage claims. "According to the BEES model, life cycle analysis (LCA) is characterized by all of the following EXCEPT: a. Questions regarding the materials and impacts related to the six stages of the product life cycle b. Estimates of the cumulative environmental impacts resulting from all stages of a product life cycle over a 50-year period c. Support for selection of products with the lowest total environmental impact d. Market analysis of demand for sustainable products Yesterday's Review: About GreenFormat" - >>>"d. Market analysis of demand for sustainable products - Market analysis of demand is a separate discipline outside of the questions related to environmental life cycle analysis. It's interesting, and necessary, but only indirectly related to LCA." "Which of the following is not included in the quoted description of benefits that BIM brings to the design and construction process? a. Opportunity for increased evaluation of design options b. Building components conflict identification and resolution c. Automated product characteristic/specification content coordination d. BIM-driven product delivery scheduling Review: PDPG 7.7.2" - >>>"c - Automated product characteristic/specification content coordination While some softwares are available that enable specification section selection and key product selection within or linked to BIM databases, coordination of BIM model object content and specification document content is not part of BIM software capabilities - there are no pushbutton specs!" "The following are TRUE concerning CSI's GreenFormat online product data resource EXCEPT: a. CSI validates and certifies information contained in GreenFormat. b. GreenFormat product information is organized by MasterFormat numbers. c. Information in GreenFormat supports specifying by proprietary, reference standard, performance, and descriptive methods. d. The Product Lifecycle category provides information on product Life Cycle Analysis, Material Extraction and Transportation, Manufacturing, and Facility Operations. The bidding requirements are: - >>>A part of the construction documents, but not the contract documents, and A part of the project manual EJCDC 1910-16 is a document which: - >>>Suggests the primary location for specific information in the construction documents The Bidding Requirements include: - >>>The instruction to bidders, the invitation to bid and the bid form. The Contract Documents include: - >>>The general conditions, the drawings and addenda The Contract Forms include: - >>>The AgreementThe performance and payment bondsThe certificates The Conditions of the Contract include: - >>>The General ConditionsThe Supplementary Conditions Addenda are: - >>>Changes to the contract documents before the agreement is signed What are the three components of project design team coordination? - >>>Organization, Execution and Quality Assurance The general clauses that establish how the project is to be administered are known as: - >>>General Conditions Under what circumstances can the Owner terminate the Work for Convenience? - >>>whenever s/he wants with written notification to the Contractor On most projects, all of the following are principal entities EXCEPT:A. ContractorB. OwnerC. Electrical ConsultantD. Architect/Engineer - >>>C. Electrical Consultant The Bidding Documents include all of the following EXCEPT:A. Bidding RequirementsB. Contract ModificationsC. Project ManualD. DrawingsE. Addenda - >>>B. Contract Modifications Project specifications should be directed to which of the following: - >>>The Contractor The term Contract Documents typically includes - >>>Contract FormsDrawingsSpecifications Project specifications should be directed to whom? - >>>The Contractor The term Contract Documents typically includes:A. Contract FormsB. DrawingsC. SpecificationsD. All of the above - >>>D. All of the above What are the necessary parts of a construction contract?A. Identification of the parties and the parties make a promise that constitutes an offerB. Both parties sign the contract indicating they understand and agreeC. Both parties - >>>D. All of the above The construction agreement is: - >>>Part of the contract documents which defines the relationships and obligations that exist between the owner and contractor Which best describes the tripartite relationship of the Owner, the Contractor and the Architect/Engineer?A. The Owner has a contact with the Architect/Engineer who has a contact with the ContractorB. The Owner has a contract with the Co - >>>C. The Contractor has a contract with the Owner who also has a contract with the Architect/Engineer Who is responsible for the technical sufficiency of the design and construction documents? - >>>The Architect/Engineer In Competitive Bidding - >>>Bidding is open to any bidder demonstrating the financial ability to perform the work The Single Prime Contract - >>>Is the most common form of construction contract In the Multiple Prime Contract - >>>The Architect/Engineer will prepare a separate set of bidding documents for each contract When the Owner has the Architect/Engineer within house: - >>>The construction contract type is called owner builder The construction contracts are the contracts between the - >>>Owner and the Contractor What is a Change Order? - >>>a written document written by the A/E, signed by the Owner, Contractor and A/E stating terms of agreement on changes in the Work, adjustments to the Contract Sum, and Contract Time, if warranted. The Agreement: - >>>Defines relationships and obligations between the Owner and Contractor The form of contract usually most difficult to administer during construction is - >>>Multiple prime contracts What is a Construction Change Directive? - >>>written order prepared by the A/E, signed by the Owner and A/E directing change in the Work prior to agreement on changes to the Contract Time or Contract Sum What is Division 00 titled? - >>>Procurement and contracting requirements If a division is not used in a Project Manual, the specifier should - >>>List the Division number with the words not used The third part of the Three Part Section Format is: - >>>Execution Specifications are: - >>>Documents that define the quality of the project, materials, and workmanship for a given project Which is true concerning MasterFormat?A. It is used to establish the proper location of information within the sixteen divisionsB. It contains a complete listing of topics covered in each divisionC. It contains a key word index - >>>D. All of the above The type of line used to represent the extent of the property boundary for a site is called the: - >>>Property line The type of drawings whose purpose is to provide the owner with a set of documents that will facilitate operation, maintenance, and future modifications of the project throughout its useful life are called: - >>>Record drawings Resource drawings serve which purpose - >>>Show construction related to work, but which is not included in the contract Section drawings are cut vertically through and perpendicular to project materials to: - >>>Show their detailed arrangement Record drawings are: - >>>Often required of the Contractor to indicate changes incorporated during construction Drawings prepared by the contractor, subcontractor, or material/equipment supplier that show how a particular aspect of the work is to be fabricated and installed, are called: - >>>Shop Drawings Which of these types of dimensions are likely to be included on one drawing:A. Actual dimensionsB. Nominal dimensionsC. Modular dimensionsD. All of the above - >>>D. All of the above When cross-referencing between the Drawings and Specifications the proper term is: - >>>the practice is discouraged A disadvantage of repeating a requirement on both Drawing and Specification is when a discrepancy arises:A. An addendum covering a change in one location may overlook it in anotherB. It causes bidders to make different interpretations o - >>>D. All of the above Detailed written information should appear only in the: - >>>Specifications A role of specification in describing a construction project is: - >>>Describing administrative procedures and workmanship Reference Drawings serve which purpose:A. Show existing work that is to be modifiedB. Show construction related to the work, but which is not included in the contractC. Provide the Owner with a set of documents that will facilitat - >>>B. Show construction related to the work, but which is not included in the contract 8. The Uniform Location of Subject Matter jointly published by the EJCDC and AIA provides a recommended location of topics in all of the following except:A. Supplementary ConditionsB. Division 1C. AgreementD. Drawings - >>>D. Drawings When placed in the specification section, schedules are: - >>>To help simplify communications by using tabular form or matrix Record Drawings are - >>>Marked up or corrected contract drawings that indicate changes incorporated in the Work during construction as well as actual locations of items show diagrammatically. the purpose of record drawings are to provide the owner a document of the the actual construction to be used for O&M Administrative provision of the construction contract are: - >>>Written in Division 1 to expand on provision in the Condition of the Contract Division 1 sections specify: - >>>Administrative requirements, procedural matters, and temporary construction facilities Which is true regarding the Drawings?A. Have no direct relationship to Division 1 of the specificationsB. Need not be coordinated with Division 1C. Graphically define certain subject matter specified in Division 1, such as Scope - >>>F. Both C and D What is included in PART 1, 2, and 3 of SectionFormat? - >>>PART 1 - GENERAL : describes administrative and procedural requirements unique to the section PART 2-PRODUCTS : describes the systems, assemblies, equipment, fabrications, and mixes that are to be incorporated into the project. PART 3- EXECUTION: describes field/site installation or application, including preparatory actions and post-installation cleaning and protection. Field/site-built assemblies and field/site-manufactured products and systems are included. Which of the following items should not be included in Section 01110?A. Owner-furnished items of workB. Site traffic regulating during constructionC. Sequence of work and Owner occupancyD. Contractors use of site - >>>B. Site traffic regulating during construction Submittal requirements for Mechanical and Electrical work are specified in: - >>>Division 1 Describe the role of the Owner. - >>>Establishes the design requirements, budget, and time constraints for the project. As the ultimate purchaser of installed products, the owner may have significant input on equipment and finish selections and may require information on product operation, maintenance, and warranties. (PDPG 2.2) What are Instruments of Service? - >>>The work product of architects and engineers that includes a seal attached to the documents. (PDPG 2.3) What was the basis used for OmniClass development? - >>>Derived from internationally accepted standards developed by International Organization of Standards (ISO). (PDPG 11.3.7.1) What are the 4 C's of communication? - >>>Clear, concise, correct, complete. The Construction Manager is normally hired by? - >>>The Owner The form of contract usually most difficult to administer during construction is: - >>>Multiple Prime Contracts In the Single-Prime contract situation the Owner does not have a contractual relationship with which of the following - >>>Sub-contractor In which phase are the specifications produced? - >>>Design Phase - Construction Documents Contract Documents Include - >>>Agreement; Conditions of the Contract; Drawings; Specifications; Addenda; Modifications Contract Documents DO NOT include: invitations or advertisement to bid; instruction to bidders; sample forms; other information furnished by the owner; ; Contractor's bid or proposal ; or sections of Addenda relating to bidding requirements Whose responsibility is it to produce the shop drawings? - >>>The Contractor Which organizational system is used in the preliminary stages of a project? - >>>UniFormat Who developed the first formal UniFormat? - >>>The AIA and The CSI Whose responsibility is the maintenance of the revised UniFormat? - >>>The CSC and The CSI When is the CSI/CSC UniFormat used? - >>>In the planning stage of a project When is the MasterFormat used? - >>>When organization of detailed construction is required on the basis of materials or methods What constitutes a contract modification? - >>>a written amendment to the Contract signed by both parties ( Contractor and Owner); Change Order; Construction Change Directive; a written order for minor change to the Work issued by the Architect. How many Divisions are found within the MasterFormat System? - >>>49 What would be an example of data filing with the MasterFormat System? - >>>Product literature, What information is found within Division 13 in the MasterFormat System? - >>>Special Construction What defines a warranty?/ an implied warranty? - >>>a promise that a proposition of a fact is true; a promise that are true as represented to be and will remain true, subject to limitations. When a warranty is presumed and not directly stated it is known as an implied warranty. any affirmation of fact or promise made that becomes a part of the basis of the agreement is referred to as what? - >>>an express warranty. a promise that a proposition of a fact is true as represented to be and will remain true, subject to limitations is referred to as what - >>>a warranty a promise that an item sold shall be fit for its intended use is automatically granted by the act of sale is referred to as what? - >>>an implied warranty a warranty to complete performance generally covering labor and materials is referred to s what? - >>>Full Warranty - under a full warranty the grantor must remedy any error without charge in a timely manner without charge after notice of defect The implied promise that eh seller owns thee item offered is referred to as what? - >>>Warranty of Title a separate contract by a third party who assumes responsibility in case the principal fails to perform is referred to as what? - >>>a guaranty True or False? If an action or activity is performed that is not part of teh contract, it can be held that that action is, after execution, part of the contract. - >>>true 31- The dollar amounts of cash allowances are: a. In the Instructions to Bidders a. revising cost estimates, schedules b. value engineering studies c. checklist for selecting products d. serving as the basis for subcontracts in fast track construction Review: PDPG 3.4.3.2 - >>>d. serving as the basis for subcontracts in fast track construction Outline specifications typically do not contain QA and QC requirements or project administration provisions, therefore are not intended to serve as the basis for contracts or subcontracts 39-All of the following may be accomplished through issuing of a Change Order EXCEPT: a. Decrease in Contract Sum b. Extension of Contract Time c. Change in Bid Date d. Reduction in scope of work Review: PDPG 11.3.12.3 and 13.9.2 - >>>c. Change in Bid Date Change Orders are modifications to the contract issued after the Agreement is executed. Addenda rather than Change Orders are used to modify procurement documents. The Bid Date is information included in the procurement documents, as it is information needed for bidding, but not for construction. 40-All of the following are AIA Instruments of Change EXCEPT: a. Change Order b. Architect's Supplemental Instruction c. Field Order d. Construction Change Directive Review: PDPG 13.9.2 - >>>c. Field Order The term "Field Order" is not used under AIA contracts, but is used in the EJCDC family of documents as well as in common usage in the industry. 41-The mood that is recommended for specifications is: a. The imperative mood b. The indicative mood c. The symbolic mood d. The conflicting mood Review: PDPG 11.3.5.2 - >>>a. The imperative mood It's the most clear, correct, complete, and concise construction for English grammatical sentences. 42-The parties to an owner/design-builder contract are: a. The Owner, the designer, and the builder. b. The Owner, the Architect, and the Contractor c. The Owner and the construction manager d. The Owner and the design-builder Review: PDPG 7.5 - >>>d. The owner and the design-builder - The single entity providing both design and construction services is the identifying characteristic of design-build contracts 33-Which of the following should be avoided in a specification? a. Articles (the, an, a) b. Symbols (#, $, &, ") c. Abbreviations (conc., ptwd, aess) d. All of the above Review: PDPG 11.3.5 - >>>d. All of the above This chapter in the PDPG provides a clear, concise, correct, and complete presentation on good specification writing habits (AEs writing drawing notes could learn a thing or two here as well). 34-An information organizing framework for the A/E/C industry that assigns built environment data into 15 discrete, coordinated tables to facilitate the organization of project information and databases is known as: a. Industry foundation classes (IFCs) b. OmniClass c. Building Information Model (BIM) d. Building Information Management (BIM) Review: PDPG 11.3.7 - >>>b. OmniClass CSI has been responsible for the development of OmniClass, which is finding increased application in organizing information within BIM. 35-To be effective in communicating, specifications should be: a. Contractor's surety b. Owner c. Contractor d. Financing agency e. None of the above Review: AIA A201 Article 11 and EJCDCC-700 Article 5 - >>>b. Owner - Unless the Supplementary Conditions specifically assign the responsibility for providing property insurance to the contractor, the clause in the General Condistions assigning responsibility to the owner will govern. 57- If the contractor is delayed in the progress of the Work by Owner, he should: a. Write Architect/Engineer protesting the changes b. Notify his bonding company c. Write the Architect/Engineer requesting a change order granting an extension of time d. Stop the Work until Owner makes up his mind. Review: AIA A201 8.3 , EJCDC C-700 Article 12 - >>>c. Write the Architect/Engineer requesting a change order granting an extension of time - Prompt notification and resolution of claims is a key to successful contract administration. 56- Lump Sum, Unit Price, or Cost-Plus-Fee constitute the basis of: a. Selection b. Payment c. Award d. Contract Review: PDPG 7.1.6 - >>>b. Payment - The three listed methods are used for different types of construction contract payment arrangements. It is also common to use Unit Price basis and Cost-Plus-Fee basis as a means of making small adjustments to the scope of a Lump-sum contract. 54- Drawings prepared by the contractor, subcontractor, or material/equipment supplier that show how a particular aspect of the work is to be fabricated and installed, are called: a. Record drawings b. Construction Documents c. Shop Drawings d. Details Review: PDPG 13.6.3.1 - >>>c. Shop Drawings - And remember - shop drawings are not contract documents under AIA and EJCDC documents; under AGC contract documents, approved submittals become contract documents, with significant ramifications for the AE and the owner. 55- All of the following are Articles in Part 3 Execution EXCEPT: a. Examination b. Application c. Fabrication d. System Startup Review: See PDPG Figure 11.13 and SectionFormat - >>>c. Fabrication - Fabrication is a process that takes place in the manufacturing plant or fabrication shop, prior to delivery to the site. Execution takes place on the job site. 53- The correct title for Division 10 is: a. Accessories b. Specialties c. Equipment d. Special Construction Review: PDPG 11.3.7.3 and MasterFormat - >>>b. Specialties - Be sure to study the names of Divisions 10, 11, 12 and 13, which often confuse new users of MasterFormat. 52-The following are the types of clauses that might be included in Supplementary Conditions EXCEPT: a. Project insurance requirements b. Liquidated damage amounts c. Tax exempt status of owner d. Submittal requirements Review: PDPG 11.5.4.3 - >>>d. Submittal requirements - Submittal requirements are addressed generally in the General Conditions. Specific requirements related to submittals appear in Division 01 General Requirements. 58-A requirement set by authority, custom, or general consensus which is established as an accepted criterion is called a: a. Building code b. Industry standard