DBIA Exams 2024: Questions and Answers for Design-Build Project Delivery, Exams of Building and Prefabrication

A collection of questions and answers related to dbia (design-build institute of america) exams for 2024. It covers key concepts in design-build project delivery, including best practices, procurement methods, contracting approaches, and project delivery systems. Useful for students preparing for dbia exams or professionals seeking to understand the fundamentals of design-build.

Typology: Exams

2024/2025

Available from 11/08/2024

keith-daniel
keith-daniel 🇺🇸

5

(1)

2.7K documents

1 / 98

Toggle sidebar

Related documents


Partial preview of the text

Download DBIA Exams 2024: Questions and Answers for Design-Build Project Delivery and more Exams Building and Prefabrication in PDF only on Docsity!

DBIA EXAMS 2024 (EXAM 1, 2 &3) QUESTIONS AND CORRECT ANSWERS VERIFIED BY EXPERTS ACCURATE ACTUAL EXAM WITH FREQUENTLY TESTED QUESTIONS AND STUDY GUIDE GUARANTEED PASS ALREADY GRADED A+ LATEST UPDATE 2024/ Purpose Statement: DBIA is the only organization that _____ , _____, and _____ best practices in design-build project delivery.

  • CORRECT ANSWER >>>>- defines
  • teaches
  • promotes _____ _____ is the belief that there is a technique, method or process that is more effective at delivering a particular outcome than any other. - CORRECT ANSWER >>>>Best practice

With proper ____, ____, and ____ a desired outcome can be delivered with fewer problems and unforeseen complications. - CORRECT ANSWER >>>>- process

  • checks
  • testing Implementing the best practices on any type of DB project _____ the probability of a _____ project that meets the expectations of all _____. - CORRECT ANSWER >>>>- increases
  • successful
  • stakeholders If the best practices are NOT implemented, there is a(n) ____ probability that the project's _____ will be compromised and that some or all of the stakeholders will be

disappointed. - CORRECT ANSWER >>>>- increased

  • performance _____ _____ are high level principles. - CORRECT ANSWER >>>>Best practices What 3 topics are the Best Practices organized into? - CORRECT ANSWER >>>>- procurement
  • contracting
  • execution How many Best Practices are there? - CORRECT ANSWER >>>> What are the discrete ways to implement the Best Practices? - CORRECT ANSWER

Implementing Techniques

The Implementing Techniques are essentially "____" best practices - CORRECT ANSWER

mini How many Implementing Techniques are there? - CORRECT ANSWER >>>> One key factor in project success is the Owner's choice of _____ _____ system and _____ approach. - CORRECT ANSWER >>>>- project delivery

  • procurement The owner's choice of project delivery system and procurement approach established how the project is _____. - CORRECT ANSWER

executed The owner's choice of project delivery system and procurement approach determines how and when the project players_____ with each

other. - CORRECT ANSWER >>>>- communicate Owners should make strategic decisions to take full advantage of _____ _____. - CORRECT ANSWER >>>>Design-Build Owners should consider the _____ and _____ of each project. - CORRECT ANSWER >>>>- particulars

  • circumstances Best Practice No. 1: an Owner should conduct proactive and _____ assessment of the unique ____ of its project and its organization before deciding to use DB. - CORRECT ANSWER >>>>- objective
  • characteristics BEST PRACTICE No. 2: an Owner should implement a procurement plan that enhances

_____ and other benefits of DB and is in _____ with the reasons that the Owner chose DB delivery system. - CORRECT ANSWER

  • collaboration
  • harmony BEST PRACTICE No. 2: an Owner should implement a(n) _____ _____ that enhances collaboration and other benefits of DB and is in _____ with the reasons that the owner chose DB delivery system. - CORRECT ANSWER >>>>- procurement plan
  • harmony BEST PRACTICE No. 3: an Owner using a competitive DB procurement that seeks price and technical proposals should establish clear evaluation and _____ processes - CORRECT ANSWER >>>>selection

What is the core of every DBIA certification course? - CORRECT ANSWER >>>>Design- Build Done Right What are the 3 "fixes" to the trust issue? - CORRECT ANSWER >>>>- picking the right DB team

  • giving flexibility, opportunity to succeed, and accountability
  • rewarding for superior performance What are the 3 synergistic elements? - CORRECT ANSWER >>>>- source selection
  • contract incentives
  • requirements In the Acquisition Strategy, one should select the best combination of what 3 components?
  • CORRECT ANSWER >>>>- project delivery system
  • procurement method
  • contracting approach Each project is unique so make informed _____. - CORRECT ANSWER >>>>choices What best describes: "How team members are organized?" - CORRECT ANSWER

Project Delivery Systems What best describes "How team members are selected?" - CORRECT ANSWER Procurement Method What best describes "How team members are paid?" - CORRECT ANSWER Contracting Approach

List 4 examples of procurement methods. - CORRECT ANSWER >>>>- QBS

  • Best Value
  • Low Price
  • Sole source List 5 examples of contracting approach. - CORRECT ANSWER >>>>- fixed price
  • GMP
  • Cost reimbursement
  • Target price
  • unit price In developing acquisition strategies, what are 4 factors to consider?
  • Owner's _____.
  • Unique project _____.
  • Owner ____ & ____.
  • _____ considerations. - CORRECT ANSWER
  • Owner's objectives
  • unique project considerations
  • owner profile and personality
  • marketplace considerations What are the 5 Owner's objectives? - CORRECT ANSWER >>>>- Control
  • relationships
  • project budget
  • project schedule
  • risks IMPLEMENTING TECHNIQUE No. 1(G): Owners should understand all _____ constraints imposed or _____ afforded by their legislative, regulatory, or internal requirements. - CORRECT ANSWER >>>>- procurement
  • flexibilities

IMPLEMENTING TECHNIQUE No. 1(G): Owners should understand all procurement constraints imposed or flexibilities afforded by their _____, _____, or _____ requirements. - CORRECT ANSWER >>>>- legislative

  • regulatory
  • internal IMPLEMENTING TECHNIQUE No. 1(C): Owners should _____ and _____ key project _____ at the early stages of project planning.
  • CORRECT ANSWER >>>>- identify
  • involve
  • stakeholders When should owners identify and involve key project stakeholders in the stages of project planning? - CORRECT ANSWER >>>>Early on

Owners should carefully research and assess current market conditions as they plan their DB programs, as this will identify potential risks and opportunities. Among the issues to be researched and assessed include: _____ actions that could limit or expand competition; projected labor, material, and equipment _____; _____ learned from similar projects; and _____ of budget and schedule estimate. - CORRECT ANSWER >>>>- procurement

  • availability
  • lessons
  • realism IMPLEMENTING TECHNIQUE No. 1(A): Owners should understand the potential _____, _____, and _____ of DB and make an

informed decision as to whether the use of DB will _____ their project. - CORRECT ANSWER >>>>- benefits

  • limitations
  • attributes
  • benefit What are 3 fundamental concepts that influence the move to integration? - CORRECT ANSWER >>>>- Cost-Influence curve
  • benefits of fast tracking
  • spearin doctrine What are the 4 phases of the Cost-Influence Curve? - CORRECT ANSWER >>>>- Planning
  • Design
  • Construction
  • Operations In which project delivery method is the construction team brought on AFTER design,

with open bidding? - CORRECT ANSWER

  • DBB In the planning phase, Influence has a _____ impact on the project. - CORRECT ANSWER high In which project delivery method is the construction team brought on EARLY, facilitating fast-tracking? - CORRECT ANSWER DB Spearin Doctrine: Owner hiring designers provides contractors two specific implied warranties: Plans and specs are _____; Plans and specs are suitable for _____ _____. - CORRECT ANSWER >>>>- accurate
  • intended purpose What are the 5 types of project delivery systems? - CORRECT ANSWER >>>>- DB

- DBB

- CMAR

- IPD

  • Multiple prime contracting _____ is a linear sequential process. - CORRECT ANSWER >>>>DBB In DBB, the A/E is typically selected on _____ and the GC is typically selected on _____ _____. - CORRECT ANSWER >>>>- qualifications
  • low price In DBB, design is fully completed _____ input from the GC. - CORRECT ANSWER

without In _____, the A/E is acting in the owner's interests. - CORRECT ANSWER >>>>DBB

Who controls the design team selection in DBB? - CORRECT ANSWER >>>>The Owner The _____ project delivery method is well established and understood. - CORRECT ANSWER >>>>DBB Which project delivery system is consistent with public sector procurement laws and the most prevalent delivery system through the 20th century? - CORRECT ANSWER >>>>DBB In DBB the _____ _____ is incompatible with expediting project delivery. - CORRECT ANSWER >>>>Linear sequence in _____, the contractor's input is absent during the design process. - CORRECT ANSWER >>>>DBB

In DBB, the Owner has a "_____ of _____ relationship" with the A/E. - CORRECT ANSWER >>>>Standard of Care Relationship In DBB, the Owner has a "_____ relationship" with the Contractor. - CORRECT ANSWER

Spearing Relationship What 2 methods of selection (procurement methods) does CMAR use? - CORRECT ANSWER >>>>- QBS

  • Best Value Who provides the pre-construction services for CMAR? - CORRECT ANSWER

Contractor What kind of contracting approach is usually DBB In DBB, the A/E is typically selected on _____ and the GC is typically selected on _____ _____. - CORRECT ANSWER >>>>- qualifications - low price In DBB, design is fully completed _____ input from the GC. - CORRECT ANSWER >>>>without In _____, the A/E is acting in the owner's interests. - CORRECT ANSWER >>>>DBB Who controls the design team selection in DBB? - CORRECT ANSWER >>>>The Owner The _____ project delivery method is well established and understood. - CORRECT ANSWER >>>>DBB Which project delivery system is consistent with public sector procurement laws and the most prevalent delivery system through the 20th century? - CORRECT ANSWER >>>>DBB In DBB the _____ _____ is incompatible with expediting project delivery. - CORRECT ANSWER >>>>Linear sequence in _____, the contractor's input is absent during the design process. - CORRECT ANSWER >>>>DBB In DBB, the Owner has a "_____ of _____ relationship" with the A/E. - CORRECT ANSWER >>>>Standard of Care Relationship In DBB, the Owner has a "_____ relationship" with the Contractor. - CORRECT ANSWER >>>>Spearing Relationship What 2 methods of selection (procurement methods) does CMAR use? - CORRECT ANSWER >>>>- QBS - Best Value Who provides the pre-construction services for CMAR? - CORRECT ANSWER >>>>Contractor What kind of contracting approach is usually used in CMAR? - CORRECT ANSWER Negotiated GMP

What is special about the estimating process in CMAR? - CORRECT ANSWER >>>>it is an open-book Which delivery methods have the chance to fast track the schedule? - CORRECT ANSWER

  • DB
  • CMAR In CMAR, the construction cost is determined _____ the design is completed. - CORRECT ANSWER >>>>before In CMAR, the Owner procures and manages designers and contractors under (one / two separate) contracts? - CORRECT ANSWER

two separate DBB Which project delivery system is consistent with public sector procurement laws and the most prevalent delivery system through the 20th century? - CORRECT ANSWER >>>>DBB In DBB the _____ _____ is incompatible with expediting project delivery. - CORRECT ANSWER >>>>Linear sequence in _____, the contractor's input is absent during the design process. - CORRECT ANSWER >>>>DBB In DBB, the Owner has a "_____ of _____ relationship" with the A/E. - CORRECT ANSWER >>>>Standard of Care Relationship In DBB, the Owner has a "_____ relationship" with the Contractor. - CORRECT ANSWER >>>>Spearing Relationship What 2 methods of selection (procurement methods) does CMAR use? - CORRECT ANSWER >>>>- QBS - Best Value Who provides the pre-construction services for CMAR? - CORRECT ANSWER >>>>Contractor What kind of contracting approach is usually used in CMAR? - CORRECT ANSWER >>>>Negotiated GMP What is special about the estimating process in CMAR? - CORRECT ANSWER >>>>it is an open-book Which delivery methods have the chance to fast track the schedule? - CORRECT ANSWER >>>>- DB - CMAR In CMAR, the construction cost is determined _____ the design is completed. - CORRECT ANSWER >>>>before In CMAR, the Owner procures and manages designers and contractors under (one / two separate) contracts? - CORRECT ANSWER >>>>two separate In CMAR, the _____ negotiates the full commercial deal. - CORRECT ANSWER Owner

In CMAR, what is the direct contractual relationship between the contractor and designer? - CORRECT ANSWER >>>>There is no direct contractual relationship In CMAR, there is _____ public sector authority for its use. - CORRECT ANSWER

limited In _____, the owner contracts with one single entity for both design and construction. - CORRECT ANSWER >>>>DB In which project delivery method do the designer and contractor have a direct contractual relationship? - CORRECT ANSWER DB

Which project delivery method has multiple organizational structures? - CORRECT ANSWER >>>>DB In DB, How is the Design-Builder generally selected? - CORRECT ANSWER >>>>QBS or Best Value Which delivery methods generally uses the selection process of QBS and Best Value? - CORRECT ANSWER >>>>- DB

  • CMAR Which delivery method has a wide spectrum of contracting approaches? - CORRECT ANSWER >>>>DB The DB system has a(n) _____ _____ of responsibility. - CORRECT ANSWER >>>>Single Point

In DB, the Owner (does / does not) manage the designer. - CORRECT ANSWER >>>>Does NOT What creates innovation potential in DB? - CORRECT ANSWER >>>>Collaboration between the Owner, Contractor, and Designer Which delivery method gives early knowledge of the project cost? - CORRECT ANSWER

DB In DB, the Owner's exposure to _____ is significantly reduced. - CORRECT ANSWER claims What is the Single Point of Responsibility Risk? - CORRECT ANSWER >>>>one of the main concerns for practitioners using DB

What does EPC stand for? - CORRECT ANSWER >>>>Engineer - Procure - Construct _____ is a delivery system that is for ALL practical purposes DB - CORRECT ANSWER

EPC EPC is a term used by _____ and _____ generation sectors. - CORRECT ANSWER

  • industrial
  • power In EPC, systems and performance testing are central to _____. - CORRECT ANSWER

scope The EPC contractor will typically perform engineering with its _____ _____. - CORRECT ANSWER >>>>in-house staff

In EPC, the Owner has need for _____ _____ of responsibility. - CORRECT ANSWER

Single Point In EPC, contracts include plant and process _____ guarantees. - CORRECT ANSWER performance What 2 main things do EPC contract terms include? - CORRECT ANSWER >>>>- liquidated damages

  • limitations of liability "Owner has the ability to schedule and coordinate the work" best describes what delivery method? - CORRECT ANSWER

Multiple Prime Contracting

In Multiple Prime Contracting, the Owner contracts with multiple _____ _____. - CORRECT ANSWER >>>>trade contractors. What does the Multi-party agreement essentially mean? - CORRECT ANSWER

all parties are equal What contract approach does IPD tend to use? - CORRECT ANSWER >>>>Target Price What procurement method is typically used in IPD? - CORRECT ANSWER >>>>QBS What is the key to IPD? - CORRECT ANSWER Owner's ability to accept risk P3 is typically used in what delivery system? - CORRECT ANSWER >>>>DB

The 2 main responsibilities of the owner under ALL delivery systems: Executing ______; and Executing actual _____ _____. - CORRECT ANSWER >>>>- procurement

  • project delivery Owner's often retain ___ _____ assistance. - CORRECT ANSWER >>>>3rd party What is one characteristic of the scope in 3rd party assistance? - CORRECT ANSWER

The scope of services varies widely Using a 3rd party professional does NOT constitute a new _____ _____. - CORRECT ANSWER >>>>delivery system Delivery systems alone, do not predict _____

  • CORRECT ANSWER >>>>success