FOREMAN CERTIFICATION TEST EXAM COMPLETE ACCURATE EXAM QUESTIONS WITH DETAILED ANSWERS, Exams of Nursing

FOREMAN CERTIFICATION TEST EXAM COMPLETE ACCURATE EXAM QUESTIONS WITH DETAILED VERIFIED ANSWERS (100% CORRECT ANSWERS) /ALREADY GRADED A+ FOREMAN CERTIFICATION TEST EXAM COMPLETE ACCURATE EXAM QUESTIONS WITH DETAILED VERIFIED ANSWERS (100% CORRECT ANSWERS) /ALREADY GRADED A+ FOREMAN CERTIFICATION TEST EXAM COMPLETE ACCURATE EXAM QUESTIONS WITH DETAILED VERIFIED ANSWERS (100% CORRECT ANSWERS) /ALREADY GRADED A+

Typology: Exams

2024/2025

Available from 02/05/2025

TutorSection
TutorSection 🇺🇸

3

(1)

727 documents

Partial preview of the text

Download FOREMAN CERTIFICATION TEST EXAM COMPLETE ACCURATE EXAM QUESTIONS WITH DETAILED ANSWERS and more Exams Nursing in PDF only on Docsity!

FOREMAN CERTIFICATION TEST

EXAM COMPLETE ACCURATE EXAM

QUESTIONS WITH DETAILED

VERIFIED ANSWERS (100% CORRECT

ANSWERS) /ALREADY GRADED A+

What should a foreman do if damage to a shipment is discovered AFTER the delivery driver has left the job site? - ....ANSWER...Notify the Project Manager and note the damage on the daily log

Which of the following represents an effective way to ensure that the job is progressing within the allotted budget? - ....ANSWER...Keep a log of man hours used and compare it to the percentage of the job completed

Under which conditions do most contracts indicate changes to the work are valid? - ....ANSWER...Signed change order authorizing the scope and price

A blueprint is written with a scale of 1/4 inches equals 1 foot. A room scales out to 15 1/4inches. How many feet would the room be? - ....ANSWER...61 feet

Two mechanical contractors are working on a common steam line. Who is responsible for lock out/tag out? - ....ANSWER...Each individual working on the steam line

What is the purpose of a "Separation Notice? " - ....ANSWER...To identify the circumstances surrounding a termination

One of your crew members is a highly experienced journeyman who only wants to "do things their own way." As a foreman, what is the BEST effective way to handle this worker? - ....ANSWER...Listen to their ideas but make the final decision on how to proceed yourself.

"Footing Drain: Furnish and install 4 inch drain tile or other type of material approved by local code authority. The contractor is to furnish and place gravel in accordance with requirements of local code authority. "According to the information above,

As a foreman what should ALWAYS be your FIRST priority when planning for a job? - ....ANSWER...to effectively manage and lead the crew

which of the following is involved in pre- construction planning? - ....ANSWER...developing a job strategy before the job begins

which of the following describe the purpose of "Short interval planning"? - ....ANSWER...breaking the job into small manageable pieces

which of the following is the FIRST thing a foreman must do before beginning to plan a job? - ....ANSWER...read all project related documents

Which of the following provides the BEST examples of prefabriaction? - ....ANSWER...to create a product in the shop and install it in the field

Which of the following is NOT required on a daily log?

  • ....ANSWER...the work completed by individual crew members

Which of the following is NOT likely to lead to improved material handling? - ....ANSWER...have all material and equipment delivered at the beginning of the job

Which of the following purchasing procedures is MOST likely to reduce material handling time? - ....ANSWER...bag and tag all materials as appropriate

What should a foreman do if damage to a shipment is discovered AFTER the delivery driver has left the job site? - ....ANSWER...notify the project manager and note the damage on the daily log

Which of the following locations represents the BEST place to store job site materials in a manner that enhances productivity? - ....ANSWER...as close to the point of installation as possible

which of the following costs should a foreman be MOST concerned? - ....ANSWER...labor

Which of the following is NOT considered a direct job cost? - ....ANSWER...home office overhead

steps should be completed? - ....ANSWER...sketch, layout, order material, install

When is the BEST time for a foreman to hold information sharing "Toolbox Safety Talks" - ....ANSWER...regularly on a weekly basis to address safety issues and learn about new tools or materials

The big documents associated with your project state "do not remove or disturb any asbestos containing material (ACM)." You have three days before a planned outage/shutdown to remove a 12- inch insulated gate valve that you suspect has an asbestos covering. What should you do? - ....ANSWER...verify insulation material

While creating the rough layout for a piping project, you discover a problem with the 2'' hot water supply and hot water return piping. By following the design specifications you determine that these pipes will be interfering with the sheet metal subcontractor's 48'' duct work. Which of the following actions should the piping foreman take? - ....ANSWER...

As a general rule, when is the BEST time for a foreman to schedule effective meetings with their work crew? - ....ANSWER...at the beginning of a shift

Which of the following represents an effective way to ensure that the job is progressing within the allotted budget? - ....ANSWER...keep a log of man hours used and compare it to the percentage of the job completed

Assume each of the following steps below must be taken at some point when ordering materials:

a. call supply house with lists

b. make a deawing

c. list materials

d. call for availability and prices - ....ANSWER...b, c, d, a

Which of the following is a true statement with respect to a foreman's responsibility related to his or her crew? - ....ANSWER...the foreman is responsible for anything that occurs at the job site from the beginning of the work day/shift to the end of the work/day shift

Assume a project blueprint is written with a scale of 1/4 inch = 1 foot. Using a ruler, you determine that 6 3/4 inches of pipe must be ordered (as measured on the blueprint's scale). how many actual feet of pipe must be ordered to complete the project? - ....ANSWER...27 feet

What hanger size would be required for use with a 6 inch outside diameter pipe that is covered with 1 inch thick insulation - ....ANSWER...8 inches

A waste line is pitched at 1/8th inch per foot. It passes through two walls 72 feet apart. What is the difference in the elevation of the two sleeves? - ....ANSWER...9 inches

On a drawing that is written to 1/8 inch scale, the pipe from point A to point B is 6 1/2 inches. How long is the actual pipe? - ....ANSWER...52 feet

Assume that you need to purchase 1,000 feet of pipe for your assigned project. If pipe costs $1.25 per foot, what is the cost of purchasing 40% of the total pipe needed? - ....ANSWER...$

What standard is applied with respect to the abuse of substances on the job site? - ....ANSWER...a zero tolerance policy has been established by the United Associations and it is applied to all locals

According to the united associations standard for excellence, how should an employer handle an ineffective employee? - ....ANSWER...return them to the union hall with an explanation of why they are being discharged

if it becomes necessary for a foreman to discipline an employee, which of the following is the BEST way to handle it? - ....ANSWER...meet privately with the employee and his or her job steward

What is the purpose of a separation notice? - ....ANSWER...to identify the circumstances surrounding a termination

which of the following prohibits discrimination based on gender, race, or national origin? - ....ANSWER...The civil rights act

A member of your crew has come to you complaining they are being harassed by another crew member. What is the FIRST step that you, as a foreman should take? - ....ANSWER...document the event and bring it to the attention of supervisors

If a foreman from a different trade approaches you claiming that one of your crew members has been injured while working outside of his scope of work, what would be the FIRST action you should take? - ....ANSWER...get the crew member medical attention

if a crew member is repeatedly absent or tardy on the job, it may be a symptom of: - ....ANSWER...all of the above: personal problems, substance abuse, not being well suited to their current position

When a "routing conflict" occurs between coordinated trades, what strategy should be applied to resolve the conflict? - ....ANSWER...request information from the engineer on how progress should proceed

one of your crew members is a highly experienced journeyman who only wants to "do things their way."

As a foreman, what is the BEST effective way to handle this worker? - ....ANSWER...listen to their ideas but make the final decision on how to proceed yourself

you believe that there may be a better too available that can be used to more efficiently complete a job. What would be the MOST appropriate way to persuade your supervisor that the better tool should be used? - ....ANSWER...explain the cost effectiveness of using the different tool and demonstrate that it will be more efficient

a member of your crew is being excessively loud and using inappropriate language. As a foremen what is the MOST effective course of action to take - ....ANSWER...explain to them that their behavior is inappropriate any many be considered harassment by fellow crew members any be management

which of the following is NOT a characteristic of a good leader - ....ANSWER...dictorial

Positive motivation should include such practices as

  • ....ANSWER...praising workers for ajob well done

You have an apprentice on your project that is struggling to do their job. What is the BEST approach to helping them? - ....ANSWER...have them work with an experienced journey man

while working at a job site your crew members become hostile toward non-union contractors doing the same type of work right next to them. How would you as a foreman uphold the united associations standards for excellence in this situation - ....ANSWER...tell your crew members that they are professionals and should act professional

there are guidelines for installing the correct size of septic tank. Septic tanks shall have a minimum size of 1,500 gallons. If a larger size is required by local authorities the contractor shall comply with local codes but allow in his or her bid for the cost associated with such increase in size.

If a foreman from a different trade approaches you claiming that one of your crew members has been injured while working outside of his scope of work, what would be the FIRST action you should take? - ....ANSWER...Get the crew member medical attention.

Which of the following is a true statement with respect to a foreman 's responsibility related to his or her crew? - ....ANSWER...The foreman is responsible for anything that occurs at the jobsite from the beginning of the work day/shift to the end of the work day/shift.

Why is preparation so important in a negotiation? - ....ANSWER...Having time to prepare and having a plan makes it easier to keep emotions in check.

The piping specifications required all wall penetrations to have a steel pipe sleeve.The steam piping size is 4 inches SCH 80 carbon steel with 1 inch of fiberglass insulation. What diameter of SCH 40 carbon steel sleeve is the minimum that you can use? - ....ANSWER...8 inches

A member of your crew is being excessively loud and using inappropriate language. As a foreman, what is the MOST effective course of action to take?

  • ....ANSWER...Explain to them that their behavior is inappropriate and may be considered harassment by fellow crew members and by management

Using drawing, what is the elevation of the top of the 24 x 18 duct? - ....ANSWER...31 feet and 10 inches.

On the project blueprint there is a bank of four pipe runs with each pipe measuring three inches in diameter which measure 12 inches in length on the blueprint. The scale used on the blueprint is 1/4 inch equals 1 foot. How many feet of 3 inch pipe should be ordered to complete the runs? - ....ANSWER...192 feet

Using the formula below, what is the correct 45 offset when you have a rolling offset where the roll is 8 inches and the rise is 6 inches? Formula: Offset = roll 2 + rise2 - ....ANSWER...10 inches.

What is the first rule of negotiation? - ....ANSWER...Understand the other person's needs.

Assume that you need to purchase 1,000 feet of pipe for your assigned project. If pipe costs $1.25 per foot, what is the cost of purchasing 40% of the total pipe needed? - ....ANSWER...$

Which of the following describes the purpose of "Short Interval Planning? " or "Look Ahead

Planning"? - ....ANSWER...Breaking the job into small manageable pieces.

Which of the following correctly identifies what is included in legitimate labor costs? - ....ANSWER...Hourly wages, fringe benefit packages, payroll taxes, insurance and safety costs,and small tools and consumables.

Calculate the number of hangers needed to support 275 feet of pipe if you need a hanger placed every 8 feet? - ....ANSWER...35 hangers

The bid documents associated with your project state, "Do not remove or disturb any asbestos containing material (ACM). " You have three days before a planned outage/shutdown to remove a 12- inch insulated gate valve that you suspect has an asbestos covering. What should you do? - ....ANSWER...Contact your supervisor for proper procedures and instructions on how you should proceed.

When is it best to perform site safety inspections? - ....ANSWER...Every day that work is in progress.