Download Ms project for project management for design an managing project and more Lecture notes Project Management in PDF only on Docsity! MS Project Tutorial Prepared by Milton Hurtado CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus How to get MS Project ? Download MS project from following link http://www.microsoft.com/office/project/
O00
ee
|B) File Edt View Inset Fomat Tools Proiect Window Help alx|
[OSR|SAY| tA > |eleses|A CE) -|QQr|e a.
[© > & = Shows | Ara 78 +/B7 Ue | ATasks ove |
“Testane Duron | Sixt [Fish Pediesans [Fesovee in ‘Apr 2002 Way 2000
‘(zt ad[a7|50) 2/5 |e [i 1a i7ia|2e\o6|29|2 |s |e 1
Project Deliverables ‘2days Mon 4/102 Tue 46002
Procure Hardware Delays Wed 4702 Thu a16m2 4
Test Hatcware Says Friaem2 Tue 4002 2
Procure Software Toss 10daye Wed 72, Tue 45002 4
anon
Bn eee
Name:
Percent complete:
|
2 |
I Hde task bar
1B Boll up Gantt bar to summary
Help
Duration: =] estimated
Gm: | see |e
Pronty: [a
Eich +
a
»
Adding tasks and milestones to a Project File 1. On the View menu, click Gantt Chart. 2. In the Task Name field, type a task name, and then press TAB. (Microsoft Project enters an estimated duration of one day for the task followed by a question mark) 3. In the Duration field, type the amount of time each task will take in months, weeks, days, hours, or minutes, not counting nonworking time. (By default the time period will be days, but that can be changed to hours, months, etc.) 4. Press ENTER. 5. It should look like the figure below: 6. To add a milestone the only difference is that the duration of the activity must be zero (below is an example): Note: By double clicking on a Task or milestone, you can modify its information with a form that prompts Grouping Tasks in Logical Order (WBS Outline) 1. Click once on the first activity of the group of activities you want to group. For the example Activities 4 and 5 2. Then click on the option “New Task” in the “Insert” Menu to insert a new task that will represent the name of the group (“Group 1” for this example) 3. Then select the tasks below (4 and 5) and then click in the option “Outline-Indent” in the “Project” Menu Outlining helps organize your tasks into more manageable chunks. You can indent related tasks under a more general task, creating a hierarchy. The general tasks are called summary tasks; the indented tasks below the summary task are subtasks. A summary task's start and finish dates are determined by the start and finish dates of its earliest and latest subtasks. Find Critical Path Critical Path Analysis (CPA) helps you to lay out all tasks that must be completed as part of a project. CPA helps you to identify the minimum length of time needed to complete a project For finding CP list all the activities and enter early start, late start, early finish and late finish info of all the activities. You can do this under insert/columns and selecting each terms. Following screen shot demonstrates how to insert. Project automatically calculates ES, EF, LS and LF based on the starting/ending dates you have provided.
So 2
O00
ea =15/xI
|B) Ble Edt View Insert Fomat Tools Project Window Help alxl
JOSE SAY AEBS ol|eleess|APO/naw -|QQe\eQ.
|) & = Shows | Al 78 +|B zu All Tasks = ¥e|-S_|
(e Name Duration Start Finish | Predecessors Gtr 41,2002 [Gtr 2, 2002 | @tr 3,202 | atr 4, 2002 | atr 1, =]
dan [Feb | Mar Apr May (dun | Jul |Aug /Sep| Oct Nov Dec [Jan |F_|
1 Project Delerables —12deys.—_ Mon 402. Tue 4/16m2
2 Procure Herswre 2aays Wed 472 Thu aaa 1
3 Test Hrcwre Says Fringe Tue #30102 2
4 Procure Software Tools dOdays Wed47i02 Tue 4/30/02 1
8 ‘Write Programs: 45days WedS02 Tue 7/202 4
5 Test and Debug ETE Column Definition
7 instal 8 days
8 Training: Tdays: fiednene
3 Acceptance Seeys THe; fear
Effrt riven
fee best Ft
External Task
Align ta enc
Fish
width
ol
[ica scr owe
Re ee
O00
ee eae Ea
BT Ele Edt View Inset Fomat Tools Project Window Help BIx|
[DO SR/SRY |S BRI HlelewelaCelnomw QQriaa|
| ‘i =f [pz uleeg At -%|/S_|
Actus Dates | Ms) Ance Timescale fiatair Faced | [] PERT Analysis
7 [Tue 4j16i02
| “Tesctane [Parion [Slat [Fick [P| Ea [earirrih] atest [talon [era 2002 [ars ze [ah «2a
‘Nar Ape [May un JU ‘Aug Sep Oct Now]
7 FrojectDelverabies 12days,—-Wan47 M2 Tues/i6M2, Man 4/2 Tue 4/602 Mor 4/12 Tue an602
ea 2 Frocurs Hardware 2days Wed 4702 ThudMten2 1 ARRARARERE Thu 4nan2 Fi 7HQm2, BRRFRRATRD
3 Test Hatalwere Bdays FridngO2 TuedG002 2 FriaNgiO2 Tue 46002 Tue "M2 Thus/.02
4 Frocure Software Tools 10days Wed 4/172 Tue 4/302 1 aA#KEREAAL Tue AGOID2 #RERRRARAE Tue 4/3002
ers 5 Write Frograms 4Sdays WedS02 Tue 72M2 4 Wed S402 Tue 7/202 Wee SAAD Tue 7/202)
6 Test ane Drtig Doeays Wed TEND Thu VLD 5 Wa 79ND Thu RLM. Wien THAD Tha LTO
7 Install Bdeys FrI8RQO2 Tues3N2 36 — Fri8QO2 TueenaM2 Fr a/2M2 Tue Anan
3 Training Todays Wed 8/1402 Thu8i22m2 7 — AIRARHRRE Thu 82MN2 aAxDERRAH Thu B/2202
a korerance Rays FHRDOND Tue ARMA FIRMA) Tun RIND FATA Tue AIR?
na
ea
« He
i
— II ree er ee
astail |} @ ||[Eweooa rear [GB risen
Ean
(2!) File Edit View Insett Foimat Tools Project Window Help
sh
ing Critical Path using Detailed Gantt Chart
O00
i
JOSR|SRY| SOAS @leete| ACE) roi +|QQariag
| @ & & = Shows | Avia +8 + Bs ulz | AlTasks + ve |S.)
|EIE ES Ga fe se
| Fil AdustDates | $B) Analyze TinescledDatain Excel. | [5] PERT Anabsic|
Task Name Leveling Delay | Durstion Start | Finish ‘Successors: [Gtr 2,2002 | atr 3, 2002__|@tr 4, 2002 + |
“Apr May [Jun | dul [Aug /Sep Oct |Nov [Deo |
Project Dlverahles Dedays Zdays Mon 412 Tue 4602 24
ee Procure Hariware Oedays Zaye Wed N72 Thu atem2 3
Test Herawere Oedays EdeysFriANOD2, Tue 402 7 67 day
Prneura Safwnte Tonle esiays AT days, Wena? Tun ann? 5
‘Write Programs Dedays 4€deys Wed S02 Tue 7/202 6
Test and Deaug Dedays, 2ideys, Wed 702, Thuanm27
install Oedays Edeys, —FABDO2 Tue ar3n2 @
Training Oedays Pdays Wed enan2 Thuacam2 @
‘Acceptance Oedays edeys Friezoc2 Tue sism2
Miestane Rallup
[Network Diagram
Pa_PERT Entry Shee:
Relationship Diagram
Resaurce Allocation
|
|
New
Et
ony,
Srganizer
ee
|
[era ee vo eo
See Showing (tical path using Hetwork Dingram |
|B) Ele Edt View Insert Format Tools Project Window Hel
JOea|eQa¥|sems|5le@le
[4% + = Shows | dia 78 -|Bru
L
FICS Ge ee oe es
| FlAdust aes | Ba] Anatze Timessaled Daain Excel. [SE PERT Arabic
I
alxl
Vows:
ar Rolup
Calendar
New.
Descrint ve Network Diagram ae
Copy.
Network
cet
Milestone Dale Rulay
Milestone Roll Orgsnizer.
Relationship Diagram
Resource fllocatin =|
car
O00
Ea eee
sho
only ra asks
O00
|B) File Edt View Insert Fomat Tools Project Window Help alx|
JD SRSRY| PRBS o|eleet | SCE/isu -|QQr|ez |
| % & = Show~ | Ail +8 s/B7Ujee2 = + |S
HSS8e2e8 oneal :
ust Dates | a] Analyze Timescaled Data in Exoe..| [ic] PERT Anais Cecitned a
~ Cost Overbudget
Created After.
Task Neme ‘Duration Fish Stat ie Fish 2 |@ir2,2002 _[air3,2002__|air4, 2014]
Date Range. ‘Mar Apr [May Jun | Jul /Aug|Sep Oct Nev]
Project Deliverables 12 days
Procure Software Tools 10 days
te Programs 45 days
Test and Debug days
Install Bays:
Training T days:
Acceptance Bays:
MaTerieel sToserlinviogers Take 2 Tue 462
Wetain2 Tue a PEO Tay RRRA Tue 50102
Wed Shi? Tue 7iLnked Fes siia2 Tue 722
Wed7lic2 Thushe2'S Wea Am2) Thuerin2| Wed 7n2 Thu ita2
Fieo2 Tweeiana 38 Fram Tue e302 Frenne Tue eriama
Wedsian2 Thust2n2 7 ateennnwes Thu crz202 #eReeeeRH Thu 82202
Fiezam2Twesam2.@ — Frensn2 Tuesan2 Fiena02| Tue anna
Ho >
(ira eres or ae
Closing Project When you are saving a file it asks you whether you want to save with baseline/without baseline. You can choose either options. If you choose to save with baseline, a copy of your schedule and other things will be saved and any changes when you are making when the project progress can be viewed clearly using the baseline. If you choose to save without baseline, you will not be able to view the changes.
O00
EE
H EE
(A) file Edt View Insert Fama Zoos 2roect Wwincow Helo alx!
OB RSAY/ SERBS) Ol eee HSE/ nom -“|Qae aa.)
se o[B 7 Ue = [aren = v/a]
| Ju {
Task Name ssbur | PesStat | PesFinsh un 02 02 (aug 02 Sep'0z __|oct'0z 4]
[2 (3 fe[2si90 7 [ta[2tl2e 4 [11 falas 1 |8 i1si22 29/6 11]
Apr C2 | May "02
2a [st |7 (14 [21 [ae] 9 [12 13 ]25
Project Celveracles —14days,—Mon4/i02_‘Thu ar 82
ae Procure feriware days, ‘FrieIEN2 Wed A242
. Test Hardware Aidays _Thu2802_ Thu s/8K2 fgg
Pe Procue Sot were Ta 13de\ EAT x
Wife Programs SRS ead you lke te save a beselhe for Project"? A baseline is 3
Test and Dooug 27 day snapshot af your schedule 35 I's now. 1: Is useful because you can
aa 1Sukays_conpare Rvith later versione of your echadtle ta eva wha: change
Irainng 11 days, ee es
Acceptance 11555 Van pan
(© Save reject" wthaik abesehne!
7 Save Project" wth abaseine,
cei) - -
~ Cancel Help
hl
T Dont tellme about this aan,
ale = . 4 ‘
PSC
Now lets try a small example, step by step to practice each of the options we have seen so far about how to create a project using MS Project. We are going to use a small set of tasks (Table Below) related to the initial phases of a System Testing Plan (Definition and Design) Design Phase1 days•Test Leader •Tester E, A and B Activity 810. Add Design Documents to CMS (Milestone) Design Phase1 days•Tester E, A and BActivity 79. Check that System is Ready to be Tested Design Phase2 days•Test Manager •Test Leader •Tester E Activity 78. Review Test Plan and Attachments Design Phase3 days•Tester A and BActivity 67. Prepare Tools and Test Scripts Design Phase1 days•Tester A and BActivity 5 6. Develop Test Item Transmittal Report Design Phase3 days•Tester A and BActivity 4 5. Develop Test Procedure Specification Design Phase5 days•Tester A and BActivity 3 4. Develop Test Case Specification Design Phase8 days•Tester A and BActivity 23. Develop Test Design Specification Design Phase5 days•Test Manager •Test Leader •Tester E Activity 12. Develop Test Plan Definition Phase3 days•Test Manager •Project Manager •Test Leader Requirements Specification Document completed. (Not part of System Testing Plan) 1.RSD Analysis * System Testing PhaseEffort ResponsibilityPredecessorActivity Step by Step Example Step by Step Example (Step 2 – Add Tasks Continued) 3.1 Insert a new task at the beginning that will group everything 3.2 Highlight the tasks that are going to be added as subtasks 3.3 Click on the option “Outline - Indent” 3.4 The final result should look like this, now repeat this steps to create the Subgroups that will represent the phases (Definition and Design) Step by Step Example (Step 2 – Add Tasks Continued) 3.5 Insert a new task at the beginning of the definition tasks Highlight the tasks that are going to be added as subtasks Click on the option “Outline - Indent” The final result should look like this, now repeat this steps to create the Subgroup that will represent the phase “Design” 3.6 3.7 3.8 Step by Step Example (Step 2 – Add Tasks Continued) Click on the option “Outline-Outdent” to move the activity to the left The final result should look like this 3.11 3.9 Insert a new task at the beginning of the Design tasks (Notice that the new task that will work as a group for the “Design Phase” is inside the group “Definition Phase”, therefore we need to Outdent one position to put it at the same level as the Definition Phase) 3.10 Highlight the tasks that are going to be added as subtasks in the design phase and then Click on the option “Outline - Indent” 3.12 1. Got to the view “Resource Sheet” 2. Add the necessary resources to the “Resources Sheet”, we are going to use only the Name, Initials and Standard Rate in $/hr. The resources are going to be taken from the table showed at the beginning of the example, more specifically from the column “Responsibilities” 3. Now, with the Resources already register in the project file, go back to the View “Gantt Chart” 1 2 3 Step by Step Example (Step 3 – Add Resources) 1. Double click the task you want to link to resources available in the “Resource Sheet” 2. Then got to the Tab “Resources” and look up the resources you want to relate to the activity (For the example lets keep the amount of effort of each Resources as 100%, Leveling Resources wont be covered in this tutorial), finally Click the “Ok” button to finish the assignment. 3. Repeat steps 1 and 2 for the rest of the tasks 1 2 Step by Step Example (Step 4 – Assign Resources) 1. Adjust the length of the Gantt Chart such that it can be seen in one screen (If Possible), to do this perform a Right Click on top of the Gantt Chart first, a pop-up menu will appear, select the option “Networking Time…” 2. In the form that will open go to the tab “Time Scale” and Change the Major Scale Units to “Months” and the Minor Scale Units to “Weeks”, then press the “Ok” button to see the results in the Gantt Chart. (Adjust as necessary the scales once you are familiar with them) 1 2 Step by Step Example (Step 5 – Adjust the Gantt Chart) As explained before, you can add and hide columns from the Spread sheet, this lets you show exactly what the people needs to see, below is a view with selected fields: Name, Cost, Duration, Resource initials and Start Date. The reader is welcome to experiment with this features and to explore more views that are offered by MS Project, such as resources usage, cost reports, etc. Step by Step Example (Step 8 – A Better View) 1. For this example we are saving the file at the end, but it is recommended that you save the file frequently while you are working to avoid losing data as a result of problems such as a Power Failure for instance. 2. You can chose between saving the file with or without Baseline (the difference was explained before in this Tutorial) 1 2 Step by Step Example (Step 9 –Save the File)