Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
NCCCO MOBILE CRANE EXAM LATEST EXAM AND STUDY GUIDE TEST BANK 2024-2025 ALL 350 QUESTIONS AND CORRECT VERIFIED ANSWERS.pdf
Typology: Exams
1 / 92
QUESTION: 1. What applies to the capacities below the bold line shown on a load chart? a. They are based on the structural strength of the crane b. They must not be used c. They are based on the stability of the crane d. They should only be used if the crane is set up on outriggers - ANSWER-c. QUESTION: 2. In which quadrant are rough terrain crane capacities generally greater? a. Over the front b. Over the rear c. Over the right side d. Over the left side - ANSWER-a. QUESTION: 3. According to federal requirements, under what conditions is it okay for a person to ride the headache ball? a. When there is no other way to gain access b. When the lift has been approved by an engineer
c. When other means would be more dangerous d. It is never okay - ANSWER-d. QUESTION: 4. According to OSHA 1926.1413, how many randomly distributed broken wires in rotation-resistant rope are cause for replacement of the rope? a. 1 broken wire in 6 rope diameters b. 2 broken wires in 30 rope diameters c. 3 broken wires in one strand in one lay d. 2 broken wires in 6 rope diameters - ANSWER-d. QUESTION: 5. What is the net capacity of a crane on main boom unless the manufacturer states otherwise? a. The capacity listed in the load chart minus the weight of the rigging and all attachments b. The capacity listed in the load chart plus the weight of the rigging and all attachments c. The capacity listed in the load chart minus the weight of the rigging and all attachments not in use d. The capacity listed in the load chart minus the weight of the rigging alone - ANSWER-a. QUESTION: 6. What may happen to a properly rigged load when lifted off the ground unless the operator takes account of boom deflection?
a. It could swing out away from the crane b. It could swing in towards the crane c. It could raise absolutely vertically d. It could shift in its rigging - ANSWER-a. QUESTION: 7. What Standard Method hand signal is being illustrated? a. Swing b. Stop c. Emergency Stop d. Travel - ANSWER-a. QUESTION: 8. Who should an operator respond to a "stop" signal from? a. Appointed signal person only b. Project manager only c. Superintendent only d. Anyone - ANSWER-d.
QUESTION: 9. Which area do truck cranes without a 5th outrigger generally have no lifting capacity unless the manufacturer states otherwise? a. The side b. The rear c. The front d. The outriggers - ANSWER-c. QUESTION: 10. What is the definition of "operating radius?" a. The distance from the base of the boom to the center of the load b. The distance from the front of the crane to the center of gravity of the load c. The distance from the center of rotation of the crane to the center of the load d. The distance from the center of rotation of the crane to the center of gravity of the load - ANSWER-d. 1 1. What action does a signal person intend the operator to perform if he extends his arm at shoulder height, makes a fist with his hand, and sticks his/her thumb up? a. Boom down b. Swing c. Boom up d. Extend boom - ANSWER-c.
QUESTION: 1 2. When hoisting personnel, within what percentage of level must a telescopic boom crane be in order for the gross ratings in the load chart to remain valid? a. 1% b. 2% c. 5% d. 8% - ANSWER-a. QUESTION: 1 3. The load line of the crane you're operating contacts an energized power line. There's no sign of any other danger, such as fire. What should you do? a. Climb down carefully from the crane cab b. Jump down, feet together c. Stay in the cab until the lines are de-energized d. Get as far away from the crane as possible - ANSWER-c. QUESTION: 14. By what percentage do most manufacturers require a crane's load chart capacity to be reduced by for duty cycle operations such as high-volume concrete placement? a. 10%.
b. 15%. c. 20%. d. 30%. - ANSWER-c. QUESTION: 15. From which two points should the boom be measured? a. From the base of the boom to the center of the boom tip sheave b. From the boom hinge pins to the boom tip c. From the boom hinge pins to the center of the boom tip sheaved. d. From the base of the boom to the boom tip - ANSWER-c. QUESTION: 16. What is the preferred method of installing wire rope from a reel onto a hoist drum? a. The rope runs from the top of the reel to the bottom of the drum b. The rope runs from the bottom of the reel to the top of the drum c. The rope runs from the top of the reel to the top of the drum d. There is no preferred method - ANSWER-c. QUESTION: 17. Over which quadrant are truck crane capacities usually greater? a. Over the front.
b. Over the rear. c. Over the front right outrigger. d. Over the side. - ANSWER-b. QUESTION: 18. According to OSHA, which accessible area of an operating crane must always be barricaded? a. The swing radius of the crane b. The carbody or chassis c. The swing radius of the rear of the rotating superstructure d. The distance between the car body or chassis and the boom tip - ANSWER-c. QUESTION: 19. What is the OSHA regulation governing cranes in construction? a. 1910. b. 1926. c. 1926. d. 1910.184 - ANSWER-b. QUESTION: 20. Under which circumstance is a crack in the windshield of a crane cab okay?
a. As long as it causes no visible distortion that would interfere with safe operations b. As long as it is less than 6 inches long c. As long as the windshield is replaced on the next annual inspection d. It is never okay - ANSWER-a. QUESTION: 21. Under which circumstance does OSHA permits hoisting of personnel by crane? a. As long as the prevailing wind speed is less than 35 mph b. As long as there is no less hazardous or practicable way c. As long as all personnel have CPR training d. As long as no aerial work platform is available - ANSWER-b. QUESTION: 22. Unless the manufacturer states otherwise, what crane capacity chart is appropriate when a crane is set up with 3 of its 4 outriggers extended and the fourth is retracted? a. On-outrigger chart b. On-rubber chart c. On-outrigger chart minus 20% d. On-rubber chart plus 20% - ANSWER-b.
QUESTION: 23. According to OSHA, while hoisting personnel, the total load must not exceed what percentage of the crane's rated capacity?" a. 45% b. 50% c. 75% d. 85% - ANSWER-b. QUESTION: 24. When is side loading of crane booms permitted? a. When the operator says it's OK b. So long as no jib is installed c. Only when the outriggers are fully extended d. Only with freely suspended loads - ANSWER-d. QUESTION: 25. What is indicated if an operator makes two audible signals when moving a crane? a. He/she intends to stop b. He/she intends to back up c. He/she intends to go ahead d. He/she intends to stop (emergency) - ANSWER-c.
QUESTION: 26. When may blocking (cribbing) be placed under outrigger beams? a. When beams cannot be extended all the way out b. To increase capacity c. To improve stability d. Never - ANSWER-d. QUESTION: 27. What is the result of placing timber blocking under the tips of the tracks on a crawler crane? a. Decreases the permitted capacity of the crane b. Makes the crane more stable c. Reduces the capacity of the crane d. Makes the crane less stable - ANSWER-b. QUESTION: 28. According to ASME, what percentage of the manufacturer's crane rating must not be exceeded if a load test is done on a repaired crane? a. 110% b. 100% c. 85%
d. 75% - ANSWER-b. QUESTION: 29. Where is the tipping axis of a crawler crane located? a. It is always at the centerline of the idler or sprocket b. It depends if the idler or sprocket are in line or offset from the track rollers c. It is through the centerline of the crane cab d. It is through the boom butt section - ANSWER-b. QUESTION: 30. What should be done with materials placed under overhead energized power lines? a. Be dragged out b. Be lifted as normal c. Not be lifted by crane d. Handled with extra care - ANSWER-c. QUESTION: What standard method hand signal is being illustrated? a. Boom up
b. Boom down c. Retract boom d. Hoist - ANSWER-c. QUESTION: 32. Where should the crane's outrigger pads or tracks be placed when working at ground floor level near a cellar wall? a. As close as possible to the wall b. At least as far back as the depth of the wall below ground c. At a distance at least half the depth of the cellar wall below ground d. Anywhere, since the wall is unaffected by the weight of the crane - ANSWER-b. QUESTION: 33. How should the wheels of a crane be positioned when it is set up for working on outriggers? a. Just touching the ground b. As high as possible off the ground c. Just high enough off the ground to relieve the tires of crane weight d. Firmly on the ground to support the crane - ANSWER-c. QUESTION: 34. What happens to ground bearing pressure if you move a crawler crane from soft ground to harder ground?
a. It increases b. It decreases by a third c. It remains the same d. It decreases by half - ANSWER-a. QUESTION: 35. When may a swivel be used with rotation resistant wire rope? a. Always b. Never c. If the rope manufacturer approves d. If the operator decides it's OK - ANSWER-c. QUESTION: 36. What should you do on pick and carry operations? a. Keep the boom as short as possible b. Keep the load as high above the ground as possible c. Ensure the load is as far from the carrier/carbody as possible d. Use maximum boom length - ANSWER-a.
QUESTION: 37. What boom position would cause the greatest ground pressure when lifting with crawler cranes? a. Over the right side b. Over the end c. Over the corner d. over the left side - ANSWER-c. QUESTION: 38. Where should the hook be positioned when preparing to hoist a light load? a. Slightly to the side you're planning to swing to b. Slightly to the side opposite you plan to swing to c. Directly above the load's center of gravity d. Above the edge of the load closest to the crane - ANSWER-c. QUESTION: 39. According to OSHA 1926.1408, what minimum clearance must be maintained between any part of the crane/load and 850kV energized overhead power lines. a. 25 ft. b. 30 ft. c. 35 ft. d. 45 ft. - ANSWER-d.
QUESTION: 40. How many parts of line are required to hoist a 36,500 lb. load if the maximum allowable line pull is 9,000 lb.? a. 3 b. 4 c. 5 d. 6 - ANSWER-c. QUESTION: 41. What determines the amount of deduction required for an erected jib that is not being used? a. The actual weight of the jib b. The effective weight of the jib c. Nothing, since the jib is not in use d. The difference between the crane's actual weight and its effective weight - ANSWER-b. QUESTION: 42. What capacity should you use when the boom length of the crane falls between the lengths listed in the load chart? a. The next longest boom length b. The next shortest boom length
c. A length estimated between the lengths in the chart d. The next longest or the next shortest boom length, whichever is the lower capacity - ANSWER-d. QUESTION: 43. When is it okay to temporarily bypass a crane's overload warning system? a. When a supervisor tells you to b. When the load to be lifted exceeds the capacity in the chart c. Never d. During assembly/disassembly operations - ANSWER-d. QUESTION: 44. What happens to the leverage of the load on a crane as the boom is being lowered? a. It increases b. It decreases c. It stays the same d. It depends on the weight of the load being lifted - ANSWER-a. QUESTION: 45. Where are the Standard Method hand signals found? a. OSHA Subpart CC
b. OSHA 1926. c. ASME B30.R d. They are determined by each manufacturer - ANSWER-a. QUESTION: 46. What should an operator do if a crane's load moment indicator (LMI) malfunctions? a. Cease crane operations and report the condition to the supervisor b. Turn it off and continue as if the LMI were not installed c. Make mathematical allowances for any error d. Attempt to repair the fault - ANSWER-a. QUESTION: 1. Where must the operator's manual be kept during crane operations? a. The operator's manual must be kept in a location that is readily available b. The operator's manual must be kept in the cab at all times c. The operator's manual must be kept in the dispatch office d. The operator's manual must be kept in a secure place - ANSWER-b. QUESTION: 2. According to ASME B30.5, what are the minimal requirements to meet crane operator
qualifications? a. High School Diploma b. CDL with on the job training c. Physical, Written Test, Practical Test d. CDL physical, employers written permission - ANSWER-c. QUESTION: 3. What hand signal must be obeyed at all times? a. Swing b. Clog-everything c. Stop d. Hoist Slow - ANSWER-c. QUESTION: 4. When removing pins or bolts from a boom assembly, workers shall remain a. clear of sledge hammers b. out from under the boom c. on top of boom holding pendants d. in sight of the operator - ANSWER-b.
QUESTION: 5. When may a crane be overloaded? a. When the supervisor says it's OK b. Never c. When testing the crane d. When proof testing a man basket - ANSWER-c. QUESTION: 6. When can the operator leave the crane? a. Break time b. End of the shift c. After securing the crane d. When a storm is coming - ANSWER-b. QUESTION: 7. When can a crane be side loaded? a. Dragging a load b. With a freely suspended load c. Never d. Pile-driving - ANSWER-b.
QUESTION: 8. The deflection of a boom will cause the load to? a. side load the boom b.decrfrease the radius c. increase the radius d. have no effect - ANSWER-c. QUESTION: 9. When should tag lines be used? a. Always b. Always, except when the use of the tagline become hazardous c. Ehen the rotation of the load becomes hazardous d. When the operator cant see the load - ANSWER-c. QUESTION: 10. What shall be in the operators cab during crane operations? a. load charts b. Inspection reports c. Hand signal chart d. The crane log - ANSWER-a.
QUESTION: 11. Which of the following is considered duty cycle work? a. Pile- driving b. Setting trusses c. Clam - Shell digging d Unloading trucks - ANSWER-c. QUESTION: 12. When doing cycle work, the load chart must be reduced by how much? a. 50% b. 20% c. 30% d. none - ANSWER-b. QUESTION: 13. Which components are not parts of the boom? a. Lacing b. Cords c. Cross members d. Heel pins - ANSWER-d.
QUESTION: Where must the operator's manual be kept during crane operations? - ANSWER- The operator's manual must be kept in the cab at all times. QUESTION: According to ASME B30.5, what are the minimal requirements to meet crane operatorqualifications? - ANSWER-Physical, Written Test, Practical Test QUESTION: What hand signal must be obeyed at all times? - ANSWER-Stop QUESTION: When removing pins or bolts from a boom assembly, workers shall remain _________________. - ANSWER-out from under the boom QUESTION: When may a crane be overloaded? - ANSWER-Never QUESTION: When can the operator leave the crane? - ANSWER-After securing the crane QUESTION: When can a crane be side loaded? - ANSWER-With a freely suspended load QUESTION: The deflection of a boom will cause the load to __________________________. - ANSWER-increase the radius
QUESTION: When should tag lines be used? - ANSWER-When the rotation of the load becomes hazardous QUESTION: What shall be in the operator's cab during crane operations? - ANSWER-Load charts QUESTION: Which of the following is considered duty-cycle work? - ANSWER-Clam-shell digging QUESTION: When doing duty cycle work, the load chart must be reduced by how much? - ANSWER-20% QUESTION: Which components are not parts of the boom? - ANSWER-Heel pins QUESTION: The boom angle is the angle between ___________________. - ANSWER-the ground and centerline of the boom, between sheaves and heel pins QUESTION: Three short audible signals mean - ANSWER-back-up QUESTION: According to ANSI B30.5, hand signal chart shall be posted where? - ANSWER-On the job site
QUESTION: A signal person shall be ________________. - ANSWER-designated person, tested QUESTION: An anti-two-block device can be used _________________. - ANSWER-to test the LMI QUESTION: Cranes should be load tested when? - ANSWER-After modifications QUESTION: Upon completion of assembly of the crane, what must be done? - ANSWER-An inspection to ensure that manufacturer specifications are met QUESTION: During crane assembly, the counter weight should be installed when? - ANSWER- Before raising the boom QUESTION: A long boom crane at a short radius and out of level by 300 can see a reduction incapacity by as much as: - ANSWER-50% QUESTION: Crane stability is based on - ANSWER-lever principle QUESTION: What is the OSHA standard for cranes in construction industry? - ANSWER-29 CFR- 19 26. Subpart CC
QUESTION: What are the requirements to be a crane inspector? - ANSWER-Same as operator QUESTION: What percentage of the crane chart is considered a critical lift? - ANSWER-75% QUESTION: A multi crane lift shall require - ANSWER-Critical lift plan, reduction of gross capacity by 25% and one designated person in charge. QUESTION: When doing a pick and carry, tire pressure must - ANSWER-meet manufacturer's specifications QUESTION: The load chart is matched to the crane by: - ANSWER-Serial number QUESTION: Where do you find recommended reeving for the hoist lines? - ANSWER-Owner's manual QUESTION: Not extending telescoping boom sections equally; what may occur? - ANSWER- Longer section collapse