Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

NERC Transmission Exam | Actual Questions and Answers Latest Updated 2024/2025 (Graded A+), Exams of Communication

NERC Transmission Practice Test-Sample question to help prepare for the NERC Transmission Exam | Actual Questions and Answers Latest Updated 2024/2025 (Graded A+)

Typology: Exams

2024/2025

Available from 11/11/2024

BESTOFLUCK
BESTOFLUCK 🇺🇸

5

(2)

969 documents

1 / 2

Toggle sidebar

Related documents


Partial preview of the text

Download NERC Transmission Exam | Actual Questions and Answers Latest Updated 2024/2025 (Graded A+) and more Exams Communication in PDF only on Docsity!

NERC Transmission Practice Test-Sample question to help prepare for the

NERC Transmission Exam | Actual Questions and Answers Latest Updated

2024/2025 (Graded A+)

Which type of relay operates on the premise of comparing the flow in and out of the area of protection?

  • ✔✔Differential relay Underfrequency load shedding is set-up so that which of the following does NOT occur? - ✔✔Uncontrolled separation Who is responsible to make sure that the operation of voltage control equipment is coordinated with other impacted entities? - ✔✔Transmission Operator The coordination of voltage schedules by system operators would be utilized to reduce all of the following EXCEPT - ✔✔Reactive inadvertent What should a system operator expect to see if the generator increases its excitation? - ✔✔An increase in MVAR output A transmission line between Bus A and Bus B has MW flow from Bus B to Bus A. After the tripping of a parallel line, the line flow from Bus B to Bus A exceeds the lines thermal rating. Which of the following actions would assist the operator in correcting the problem? - ✔✔Increase generation at Bus A What is a major concern for a System Operator during emergency conditions? - ✔✔System remains connected to the Interconnection If your system has lost a large amount of customer load due to a system disturbance, but has remained connected to all of your neighbors, what is the best solution to consider? - ✔✔Coordinate with the neighbors You report for work on a peak summer day with expected high temperatures and load. What can you do to maintain an adequate system voltage profile? - ✔✔Get under the voltage by placing capacitors in service while maintaining operating limits

If a Balancing Authority is unable to calculate ACE for more than _________ minutes it shall notify its Reliability Coordinator. - ✔✔ 30 Your system configuration presents you with a situation of having two parallel lines between two stations. The lines have different ratings. Line A has a rating of 250 MVA, while line B has a rating of 200 MVA. Based on the line ratings, what is the first contingency transfer capability between the two stations? - ✔✔200 MVA