CCMP Inputs and Outputs STUDY GUIDE, Exams of Business Systems

CCMP Inputs and Outputs STUDY GUIDE

Typology: Exams

2025/2026

Available from 01/15/2026

Ellah1
Ellah1 🇺🇸

4.3

(11)

11K documents

1 / 18

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CCMP Inputs and Outputs STUDY
GUIDE
Inputs - 5.1.1 Define the Change -
correct answer
✅• Business
Case
• Research
• Charter
• Strategic Plan
• Success Measures
Outputs - 5.1.1 Define the Change -
correct answer
✅- Change
Definition
• Charter
Inputs - 5.1.2 Determine Why the Change is Required -
correct
answer
✅• Business Case
• Change Definition
• Charter
• Strategic Plan
• Success Measures
Outputs - 5.1.2 Determine Why the Change is Required -
correct
answer
✅• Business Case
• Charter
Inputs - 5.1.3 Develop a Clear Vision of the Future State -
correct
answer
✅• Organization Vision, Mission, Values
• Business Case
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12

Partial preview of the text

Download CCMP Inputs and Outputs STUDY GUIDE and more Exams Business Systems in PDF only on Docsity!

GUIDE

Inputs - 5.1.1 Define the Change - correct answer ✅• Business Case

  • Research
  • Charter
  • Strategic Plan
  • Success Measures Outputs - 5.1.1 Define the Change - correct answer ✅- Change Definition
  • Charter Inputs - 5.1.2 Determine Why the Change is Required - correct answer ✅• Business Case
  • Change Definition
  • Charter
  • Strategic Plan
  • Success Measures Outputs - 5.1.2 Determine Why the Change is Required - correct answer ✅• Business Case
  • Charter Inputs - 5.1.3 Develop a Clear Vision of the Future State - correct answer ✅• Organization Vision, Mission, Values
  • Business Case

GUIDE

  • Change Definition
  • Strategic Plan Outputs - 5.1.3 Develop a Clear Vision of the Future State - correct answer ✅• Vision Statement Inputs - 5.1.4 Identify Goals, Objectives, and Success Criteria - correct answer ✅• Business Case
  • Charter
  • Strategic Plan
  • Vision Statement
  • Change Definition Outputs - 5.1.4 Identify Goals, Objectives, and Success Criteria - correct answer ✅• Change Objectives and Goals
  • Success Criteria and Measures Inputs - 5.1.5 Identify Sponsors Accountable for the Change - correct answer ✅• Change Definition
  • Charter
  • Stakeholder Analysis
  • Current Organizational Charts and Profiles Outputs - 5.1.5 Identify Sponsors Accountable for the Change - correct answer ✅• Sponsor Identification

GUIDE

  • Case for Change
  • Risk Plan Outputs - 5.1.8 Assess Alignment of the Change with Organizational Strategic Objectives and Performance Measurement - correct answer ✅-Organizational Alignment Assessment
  • Modifications to Organizational and Enterprise --Performance Targets (Goals and Objectives)
  • Modifications to Strategic Plan
  • Modification of Business Case
  • Modification of Vision Statement Inputs - 5.1.9 Assess External Factors that may Affect Organizational Change - correct answer ✅• Business Case
  • Vision Statement
  • Strategic Plan Outputs - 5.1.9 Assess External Factors that may Affect Organizational Change - correct answer ✅• External Environment Impact Assessment Inputs - 5.1.10 Assess Organization Culture(s) Related to the Change - correct answer ✅• Core Values and Behaviors
  • Current Communication Channels, Tools, and Methods
  • Opinion Surveys and Feedback Assessments

GUIDE

  • Vision Statement Outputs - 5.1.10 Assess Organization Culture(s) Related to the Change - correct answer ✅• Culture Assessment Inputs - 5.1.11 Assess Organizational Capacity for Change - correct answer ✅• Competency Assessment
  • Culture Assessment
  • Organization's Historical Experience with Change
  • Stakeholder Assessment
  • External Environment Impact Assessment
  • Change Impact Assessment
  • Inventory of Change-Related Resources Outputs - 5.1.11 Assess Organizational Capacity for Change - correct answer ✅• Organizational Change Capacity Assessment Inputs - 5.1.12 Assess Organizational Readiness for Change - correct answer ✅• Change Objectives and Goals
  • Culture Assessment
  • Organizational Change Capacity Assessment
  • Organizational Alignment Assessment
  • Sponsorship Alignment Assessment
  • Vision Statement
  • Risk Assessment

GUIDE

Inputs - 5.1.15 Conduct Change Risks Assessment - correct answer ✅• Stakeholder Analysis

  • Change Impact Assessment
  • Culture Assessment
  • Organizational Change Capacity Assessment Outputs - 5.1.15 Conduct Change Risks Assessment - correct answer ✅• Change Risks Assessment
  • Risk Register Inputs - 5.2.1 Develop the Communication Strategy - correct answer ✅• Change Definition
  • Change Impact Assessment
  • Current Communication Channels, Tools, and Methods
  • Organizational Change Readiness Assessment
  • Project Charter and Project Documentation
  • Stakeholder Analysis
  • Vision Statement Outputs - 5.2.1 Develop the Communication Strategy - correct answer ✅• Communication Strategy Input - 5.2.2 Develop the Sponsorship Strategy - correct answer ✅• Change Risks

GUIDE

  • Organizational Change Readiness Assessment
  • Sponsorship Alignment Assessment
  • Stakeholder Analysis Output - 5.2.2 Develop the Sponsorship Strategy - correct answer ✅• Sponsorship Strategy Inputs - 5.2.3 Stakeholder Engagement Strategy - correct answer ✅• Current State Analysis
  • Change Impact Assessment
  • Current Communication Channels, Tools, and Methods
  • Communication Strategy
  • Sponsorship Strategy
  • Stakeholder Analysis Outputs - 5.2.3 Stakeholder Engagement Strategy - correct answer ✅• Stakeholder Engagement Strategy Inputs - 5.2.4 Develop the Change Impact and Readiness Strategy
  • correct answer ✅• Stakeholder Engagement Strategy
  • Change Impact Assessment Outputs - 5.2.4 Develop the Change Impact and Readiness Strategy - correct answer ✅- Change Impact Assessment
  • Change Impact and Readiness Strategy

GUIDE

  • Success Criteria and Measures Outputs - 5.2.7 Develop the Sustainability Strategy - correct answer ✅• Sustainability Strategy Inputs - 5.3.1.1 Resource Plan - correct answer ✅• Change Management Resources, Roles, and Responsibilities Strategy
  • Communication Strategy
  • Learning and Development Strategy
  • Change Resources Inventory
  • Procurement Guidelines and Policies Outputs - 5.3.1.1 Resource Plan - correct answer ✅• Resource Plan Inputs - 5.3.1.2 Communication Plan - correct answer ✅• Communication Strategy
  • Current Communication Channels, Tools, and Methods
  • Key Messages
  • Learning and Development Strategy
  • Project Charter and Documentation
  • Project Schedule and Plan
  • Sponsorship Strategy
  • Stakeholder Analysis
  • Stakeholder Engagement Strategy

GUIDE

  • Transition Strategy Outputs - 5.3.1.2 Communication Plan - correct answer ✅• Communication Plan Inputs - 5.3.1.3 Sponsorship Plan - correct answer ✅• Sponsorship Strategy
  • Sponsorship Alignment Assessment
  • Stakeholder Analysis
  • Sponsor Assessment Outputs - 5.3.1.3 Sponsorship Plan - correct answer ✅• Sponsorship Plan Inputs - 5.3.1.4 Stakeholder Engagement Plan - correct answer ✅• Stakeholder Analysis
  • Stakeholder Engagement Strategy
  • Communication Strategy
  • Sponsorship Strategy
  • Change Risks Outputs - 5.3.1.4 Stakeholder Engagement Plan - correct answer ✅• Stakeholder Engagement Plan Inputs - 5.3.1.5 Learning and Development Plan - correct answer

GUIDE

Outputs - 5.3.2 Integrate Change Management and Project Management Plans - correct answer ✅• Change Management Plan (updated)

  • Project Plan (updated) Inputs - 5.3.3 Review and Approve the Change Plan in Collaboration with Project Leadership - correct answer ✅• Change Management Plan
  • Project Plan Outputs - 5.3.3 Review and Approve the Change Plan in Collaboration with Project Leadership - correct answer ✅• Change Management Plan (approved) Inputs - 5.3.4 Develop Feedback Mechanisms to Monitor Performance to Plan - correct answer ✅• Communication Plan
  • Learning and Development Plan
  • Measurement and Benefit Realization Plan
  • Stakeholder Engagement Plan
  • Project Schedule and Plan Outputs - 5.3.4 Develop Feedback Mechanisms to Monitor Performance to Plan - correct answer ✅• Communication Plan (updated)
  • Learning and Development Plan (updated)
  • Measurement and Benefit Realization Plan (updated)

GUIDE

  • Stakeholder Engagement Plan (updated) Inputs - 5.4.1.1 Execute Resource Plan - correct answer ✅• Change Management Plan
  • Project Schedule and Plan
  • Resource Plan Outputs - 5.4.1.1 Execute Resource Plan - correct answer ✅• Change Management Plan
  • Financial Resources Update/Impact Reports
  • Human Resources Update/Impact Reports
  • Information Resources Update/Impact Reports
  • Physical Resources Update/Impact Reports Inputs - 5.4.1.2 Execute Communication Plan - correct answer ✅• Project Plan
  • Communication Plan
  • Stakeholder Engagement Plan Outputs - 5.4.1.2 Execute Communication Plan - correct answer ✅• Communication Delivery Inputs - 5.4.1.3 Execute Sponsorship Plan - correct answer ✅• Sponsorship Plan
  • Communication Plan

GUIDE

  • Measurement and Benefits Realization Plan Outputs - 5.4.1.6 Execute Measurement and Benefit Realization - correct answer ✅• Measurement and Benefits Realization Reports
  • Benefits Realization Activities Input - 5.4.1.7 Execute Sustainability Plan - correct answer ✅• Sustainability Plan
  • Measurement Baselines Output - 5.4.1.7 Execute Sustainability Plan - correct answer ✅• Communication Events
  • Benefits Reviews
  • Business Performance Reports
  • Evaluations and Reviews Inputs - 5.4.2 Modify the Change Management Plan as Required - correct answer ✅• Change Management Plan
  • Project Schedule and Plan Outputs - 5.4.2 Modify the Change Management Plan as Required
  • correct answer ✅• Change Management Plan (updated) Input - 5.5.1 Evaluate the Outcome Against the Objectives - correct answer ✅• Change Objectives and Goals

GUIDE

  • Measurement and Benefit Realization Plan
  • Sustainability Plan Output - 5.5.1 Evaluate the Outcome Against the Objectives - correct answer ✅• Change Objectives Analysis Outcomes and Next Steps Input - 5.5.2 Design and Conduct Lessons Learned Evaluation and Provide Results to Establish Internal Best Practices - correct answer ✅• Case for Change
  • Success Criteria and Measures
  • Change Management Plan Output - 5.5.2 Design and Conduct Lessons Learned Evaluation and Provide Results to Establish Internal Best Practices - correct answer ✅• Lessons Learned Evaluation
  • Remediation Plan Input - 5.5.3 Gain Approval for Completion, Transfer of Ownership, and Release of Resources - correct answer ✅• Change Objectives and Goals
  • Measurement and Benefit Realization Plan
  • Lessons Learned Report
  • Future Strategy Plan
  • Agreement on Ownership Transfer
  • Resource Release Approval