









Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
civil engineer interview question
Typology: Summaries
1 / 17
This page cannot be seen from the preview
Don't miss anything!










Aramco Questionnaires on Interview:
Ministry of Communication – Interview tips for Site Inspector
1. What are the main points which you will watch where the earthwork is in progress? -Material is not oversized (not more than 8 cm) -Not over 30 cm per layer -Not exceeding optimum moisture content or less (not rubberizing or foaming) -While grading see to it that material is not segregated -Number of passes of roller during compaction, and weight of compactor (8 passes minimum with ½ overlap) -Smoothness of the finish surface of subgrade. Contractor should use 4-m straight edge. Tolerance limit is 6mm for subgrade, 3mm for asphalt. 2. What are the different types of rollers used for the compaction of asphalt? And the function of each? a. Tandem Steel Roller -Initial rolling of asphalt, only 2 passes at ½ overlap -Final rolling to smoothen the surface and to see to it that the edge of the roller not visible on the asphalt b. Pneumatic Tire Roller -To attained the require compaction (8 passes min, not less than 5 tons) 3. What is the thickness of each layer allowed for an embankment and for subgrade? -For embankment; 30cm thick or as otherwise specified -For subgrade; Earth cut – 30 cm to be laid in two layers (15 x15) Earth fill – 40 cm to be laid in two layers (20x20) if possible to attain the required 100% compaction. -Rock cut: 20cm in one layer.
1. A clear space of ____________ shall be maintained on all sides of the excavation. a. 2 ft b. 3 ft c. 4 ft d.5 ft e. all of the above 2. Shoring shall be installed or sides shall be sloped or benching when the depth of excavation reaches ___________. a. 0.8m b. 1.5m c. 1.2m d. 1.4m e. all of the above 3. Liquid limit and plastic limit test are required for select the material when the percentage passing the #200 sieve is _________. (Liquid & plastic limit test are required if the % passing the #40 sieve is more than 15%) a. 10% b. 14% c. 16% d. (a) & (c) d. all of the above 4. The sufficient thickness for cohesive capping material when sand was used as fill material was a. 150mm b. 200mm c. 250mm d. all of the above e. none of the above 5. What are the two basic type of concrete as per SAES-Q-001? (Write your answer). Structural & **non-structural concrete.
12. The minimum clear distance of anchor bolts or anchor bolts sleeves from the edge of concrete shall be ______ a. 50mm b. 75mm c. 100mm d. 120mm e. none of the above 13. Concrete can be drop freely at a height of ________. a. Half meter b. one meter c. one and a half meter d. a & b e. a & c b. 14. Concrete curing water shall not have more than _______ of total dissolve solids ( TDS) a. 500ppm b. 750ppm c. 1000ppm d. all of the above e. none of the above **TYPICAL INTERVIEW QUESTIONS FOR CIVIL INSPECTOR
11. What is the prime coat and where is it applied (SAES Q-006 & AASHTO)? What is the curing requirement for the Prime coat? a. It is the asphalt bituminous material that is place on the substrate prior to placement of the first asphalt mixture (the blinder course). It must be allowed to cure and soak into the capping layer (usually select fill) b. 24 hours, a good indication that the material cured is when the color turns to pitch black e.i. the brownness is gone. 12. What is Tack Coat (SAES Q-006 and AASHTO)? a. It is the asphalt bituminous material when is applied on existing concrete or asphalt surface to bond the new subsequent asphalt pavement to them. Tack coat is not necessary to place on new asphalt before placing the next layer of asphalt unless it is soiled (dirty). 13. What is the tolerance requirement of sub-grade asphalt surface smoothness prior to placing asphalt (SAES Q-006 and AASHTO)? a. Using a 3 meter edge = 6mm 14. What is the tolerance requirement of finish asphalt surface smoothness (SAES Q-006 & AASHTO)? a. Using 3 meter straight edge 4mm longitudinally, 3mm laterally. **PART 2:
it and the QC inspector notify the field foreman or the site engineer to proceed. If not, the problem is communicated to the site engineer to fix.
4. Tell me about ITP and the QCP? Roads and Bridges Site Inspection Guidelines (Question and Answers) 1. What are the duties and responsibilities of a Site Inspector? -Supervise the actual construction on the site as guided and instructed by the civil or resident engineer -Bear direct responsibility for application of specification on site -Make sure that safety measures are applied by the contractor -Prepare daily work report in addition to memoranda -Not act as a foreman for the contractor -Not change specification and plans 2. Min & max temperature of asphalt at the site of paving? -Min is 139®C, Max is 163®C 3. Min atmospheric (air) temperature prior to paving? -Min is 4®C 4. Min & Max temperature of concrete at the site prior to paving? -Min concrete temperature is 10®C, Max is 32®C 5. Atmospheric (air) temperature allowed for paving? -5®C Min for cold weather -33®C Max for hot weather 6. Min atmospheric temperature prior to spraying MC-1 or MC-2? -Min is 15®C 7. What are the purposes of curing? -To maintain the amount of water in the concrete mix -To minimize hairline cracks
17. What is the purpose of retarder? -To delay initial setting of concrete -To accelerate the effect of hot weather on the setting of concrete 18. What is the purpose of slump test? -To determine the consistency or workability of the concrete mix and to check for the required slump 19. Allowable slumps? -2.5cm to 7.5 cm (for vibrated structure & without additive) -If with additive, slump depends upon the special specifications 20. Type of curing? -Water curing, as in ponding, burlap, spraying, wet sand and wet earth -Membrane curing is a plastic film, liquid membrane curing compound and reinforced paper -Team curing 21. What is plasticizer? -Usually applied at a low water-cement ratio concrete to make workable -Usually use in pre-stressed concrete 22. What is composite structure? -It is a structure composed of two materials as in steel and concrete 23. What is non-composite structure? -It is a structure made of either concrete or steel 24. Types of cement -Type I = Normal or standard cement (for general use) -Type 1-A = Air-entraining cement same as type I -Type II = Moderate Sulfate resistance cement -Type II-A = Air-entraining cement same as type II -Type III = High-early strength cement usually used in pre-stressed concrete -Type IV = Low Sulfate Resistance cement -Type V = High Sulfate Resistance cement 25. What is the effect of seawater on concrete? -It increases the risk of corrosion of rebars -It weakens the strength of concrete -Cracks occur due to the crystallization of salts in the concrete mix
26. Can you use seawater as mixing water in concrete and or embankment? -Yes, if suitable fresh water is not available 27. Two types of pre-stressed concrete -Pre-tensioned Concrete = The tendons are tensioned to a desired force before pouring of concrete, then released after the concrete has attained the desired strength. -Post-tensioned Concrete = The tendons are positioned to their locations, then poured concrete mix. After the concrete has attained the required strength, then the tendons are stressed to the specified force. 28. Minimum compressive strength of concrete before applying force? -At least 350kg/cm 29. What is the minimum strength of concrete before applying force? -300kg/cm 30. Reason behind cracks? -Poor curing practice, poor design, poor vibration which result in segregation, less rebar covering, poor quality of concrete, movement of falsework or forms, higher water cement ratio. 31. What part water-cement ratio plays in concrete? -The lower the ratio the stronger the concrete mix, provided it can be consolidated properly. 32. What are the concrete samples? -The cylinder and the cubes 33. What is the difference between the two and which is preferable? -The difference is in there deformation when subjected to compressive loads. The deformation in cylinder is bigger than in the cube. The cube can withstand bigger loads because of its L/D ratio. But the strength of the cylinder is nearer to the actual strength of the structure being poured than the strength on the cube. That’s why when we use the cube, we multiply the strength that was gotten by a correction factor depending on L/D ratio. While in cylinder there is no correction factor applied for the reason cylinder sample is more preferable. 34. Within how many hours should concrete mix be discharged after leaving the batching plant or after all the aggregates, cement and water are in the mixer? -Within one hour if the mixer is an agitated mixer -Within 30mins if the mixer in non-agitated mixer
-By just looking and smelling, MC-1 smells kerosene and look dull and its thicker, while RC-2 smells benzene (gasoline) and looks shiny and is thinner and dries rapidly.
47. What are you going to do if there is bleeding in MC-1 or if the MC-1 is not dry after 48 hours? -I will apply blotting by spreading sand on wet portion only when removing the excess by rake or any suitable equipment 48. What is rutting? -It is the longitudinal settlement of asphalt pavement due to heavy loads of the vehicles passing the road 49. What are the remedies to prevent of minimize rutting? -To limit or minimize the loads of vehicle -To make the gradation of aggregates coarse but conducive to the project -To lower the asphalt content and/or lower the asphalt penetration (as from 60-70 to 40 -50) -To follow the instruction of the MOC as to the limit of air voids which is 3-5 with 4 as the median and actual air voids to be gotten 50. What is the purpose of MC-1 (Medium Curing Cutback Asphalt)? -To stabilize or seal the granular surface of subgrade and to promote bonding to bituminous surface. 51. What is the purpose of RC-2 (Rapid Curing Cutback Asphalt)? -To ensure or promote bonding between the previously laid asphalt pavement and the newly paved layer 52. Minimum and maximum overlapping of asphalt in longitudinal and transversal joints? -For longitudinal joint 15 to 30 cm 53. Why do you overlap? -To prevent cracking at the longitudinal joint 54. What will happen if your asphalt content is more than 0.3%? -It will be more than the required limits and bleeding will occur and thereby weakening the pavement 55. What is the maximum loss of stability for asphalt? -25% 56. What is the maximum variation of asphalt content? -±0.3% from the approve asphalt content
57. Types of compaction and moisture ranges? -Type AAA = 100% compaction, 78% relative density Moisture ranges = MR 3 (Moisture shall not be lower than 3% of the optimum moisture) -Type AA = 95% compaction, 74% relative density Moisture ranges = 0 (moisture shall be ±5% of optimum moisture) -Type A = 90% compaction, 70% relative density 58. Temperature of asphalt pavement before breakdown or initial rolling? -120®C or as what we get from the trial test 59. Heating temperature of MC-1 and RC-2 before spraying? -MC-1 should be heated to 50 - 80®C -RC-2 should be heated to 65 – 95 ®C 60. Rate of application of MC-1 and RC-2? -MC-1 = It is 0.65 – 1.75 liter/m -RC-2 = It is equal or less than 0.25 liter/m 61. What are the two types of asphalt batching plant? -Batching type = It is easy to control and it is batch by weight -Continuous type = It has a greater output 62. What is SPT? -Standard Penetration Test, it is usually made to evaluate the bearing capacity of the soil 63. What is Bleeding? -It is the flow of water in the mix or on to the surface of the mix because of the settlement of the mass of concrete mix. 64. How do you cure cylinder sample? -Cylinder samples are cured in laboratory, in water tank saturated with lime at 23±1.7®C. -It is also advisable to cure in the field, same as the structure being represented. 65. What are the precautionary measures if the air temp is greater than 33®C? -Make shades; cool the water by using ice cubes -Spray the aggregates specially the coarse with cold water -Wet the forms and reinforcement
73. Classifications of Soils? A-1 = gravelly or sandy soil with some stone fragment A-2 = silty or clayey gravel and sand A-3 = sand dunes A-4 / A-5 = silty soil A-6 /A-7 = clayey soil 74. What is California Bearing Ratio (CBR)? -It is the test use to find bearing capacity of soil compacted at optimum moisture content and at a different densities (10, 30, 65 blows) 75. What is Proctor or Moisture-Density Test? -It is the test use to find the moisture and density relation of a soil when compacted at laboratory 76. What is the distance of borrow pit from the structures? -Downstream: Min is 200 meters or as otherwise specified
-The difference is in their compacting effort. Although its layer is compacted (5 layer) is compacted 56 blows, but the weight of the hammer of standard is 5.5lbs with 12- in drop while that of modified is 10lbs and 18- in drop.
83. What is the difference between the CBR5 and CBR 10? -CBR 10 has more strength than CBR 5.