In the project below, the time duration and symbol of each activity are given. Identify the critical path (Without using CPM; hint: identify all possible paths and find their lengths)?
a. A B E H
b. A C D H
c. A B D H d. A F G H
The correct answer is: A B D H
Correct
Mark 1.00 out of
longest path in the project (without using CPM; hint: identify all possible paths and find their lengths)?
a. 17
b. A B E H
c. 21 d. 20
The correct answer is: 21
In the project below, the time duration and symbol of each activity are given. What's the slack of path A- C-D-H?
Correct
Mark 1.00 out of
Correct
Mark 1.00 out of
In the project below, the time duration and symbol of each activity are given. Compute the early start of activity 'E' using the CPM method?
Correct
a. 2
b. 12
c. 8 d. 21
The correct answer is: 8
In the project below, the time duration and symbol of each activity are given. Compute the early start of activity 'F' using the CPM method?
a. 21
b. 11
Mark 1.00 out of
Correct
Mark 1.00 out of
a. 8
b. 10
c. 21
d. 9
The correct answer is: 9
In the project below, the time duration and symbol of each activity are given. Compute the slack of activity 'E' using the CPM method?
a. 1
b. 3 c. 0
Correct
Mark 1.00 out of
d. 2
The correct answer is: 3
In the project below, the time duration and symbol of each activity are given. Compute the slack of activity 'B' using the CPM method?
a. 0 b. 7
c. 1
d. 2
The correct answer is: 0
Correct
Mark 1.00 out of
Correct
Mark 1.00 out of
a. A B D F
b. 7
c. A B E F
d. A C D F
The correct answer is: A B D F
Correct
Mark 1.00 out of
before 16 weeks (hint: use the critical path parbability).
Correct
Given the data (below) of all the activities in the EFX-N2 project (also project schematic is given), compute the expected time of path 'C-D'.
a. 12.
b. 16.
c. 13.
d. 22.
The correct answer is: 12.
Correct
Correct
Mark 1.00 out of
a. 0.
b. 4.
c. 0.
d. 1.
The correct answer is: 0.
Given the data below for the EFX-N2 project (also project schematic is given). If a project manager would like to figure out the liklihood of the project finishing before 18 weeks. What would be the z-score of path 'A-B'.
Correct
Mark 1.00 out of
a. 1.
b. 3.
c. 3.
d. 4.
The correct answer is: 3.
Given the data below of the EFX-N2 project (also project schematic is given), what would be the probability of path 'C-D' finishing before 15 weeks?
a. 0.
b. 0.
Correct
Mark 1.00 out of
The correct answer is: 0.
Given the data for the EFX-N2 project (see below). What would be the probability of the project finishing after 15 weeks?
a. 0.
b. 4.
c. 0.
d. 0.
The correct answer is: 0.
Correct
Mark 1.00 out of