The project plan for developing smart sticks using AI technology. It includes the project purpose, objectives, scope, milestones, cost breakdown, and risks. The smart sticks aim to help blind people and those with hunchbacks or osteoarthritis to walk more easily. The project includes developing a heat sensor system, AI systems on sticks, appropriateness, a bearing system, and automatic battery charging system. The document also includes a communication strategy and a budget supported by investors.
Typology: Assignments
1 / 26
This page cannot be seen from the preview
Don't miss anything!



















Qualification BTEC Level 5 HND Diploma in Computing
Unit number and title Unit 06: Managing a Successful Computing Project
Submission date Date Received 1st submission
Re-submission Date Date Received 2nd submission
Student Name Hồ Xuân Hồng^ Student ID GCD
Class GCD0705 Assessor name Hong
Student declaration I certify that the assignment submission is entirely my own work and I fully understand the consequences of plagiarism. I understand that making a false declaration is a form of malpractice.
Student’s signature
Grading grid P1 P2 P3 P4 M1 M2 D
Grade: Assessor Signature: Date: IV Signature:
Nguyen Hoang Anh Reaseach and development
William James Reaseach and development
Kaijo Rika Reaseach and development
Thomas Ledison Reaseach and development
Park Jun Hee
Reaseach and development
3. Stakeholders (e.g., those with a significant interest in or who will be significantly affected by this project) Iruka nasato-CEO of the company Thomas Frank - Board member and investor Maroon - Board member and investor Nikvujick - Board member and investor Williams - Board member and investor
4. Project Scope Statement
Project Purpose / Business Justification Describe the business need this project addresses
Objectives (in business terms) Describe the measurable outcomes of the project, e.g., reduce cost by xxxx or increase quality to yyyy
Deliverables List the high-level “products” to be created (e.g., improved xxxx process, employee manual on yyyy)
Project Milestones Propose start and end dates for Project Phases (e.g., Inception, Planning, Construction, Delivery) and other major milestones
Task Name Duration Start Finish Status Analysis 8 days Tues 11/26/19 Mon 12/2/ Collect stakeholder’s requirements
4 days Tues 11/26/19 Fri 11/29/19 completed
Draft and sign the project charter 4 days Fri 11/29/19 Mon 12/2/19 completed
Planning 6 days Tues 12/3/19 Sun 12/8/ Denfine project aim, objectives and scope
2 days Tues 12/3/19 Wed 12/4/19 completed
Calculate cost 2 days Thu 12/5/19 Fri 12/6/19 completed Work breakdown structure and schedule
2 days Sat 12/7/19 Sun 12/8/19 completed
Development 90 days Mon 12/9/19 Fri 3 /13/ Developed heat sensor system 30 days Mon 12/9/19 Thu 1/9/20 Unreached
Developing AI systems on sticks
40 days Fri 1/10/20 Wed 2/19/20 Unreached
Develop appropriateness on smart sticks
10 days Thu 2/20/20 Sun 3/1/20 Unreached
Develop a bearing system of smart sticks
5 days Mon 3/2/20 Sat 3/7/20 Unreached
Developed automatic battery charging system
5 days Sun 3/8/20 Fri 3/13/20 Unreached
Testing 30 days Sat 3/14/20 Tue 4/14/ Endurance test 10 days Sat 3/14/20 Tue 3/24/20 Unreached Check the quality of products 7 days Wed 3/25/20 Wed 4/1/20 Unreached
Check health sensor 8 days Thu 4/2/20 Fri 4/10/20 Unreached
5. Communication Strategy (specify how the project manager will communicate to the Executive Sponsor, Project Team members and Stakeholders, e.g., frequency of status reports, frequency of Project Team meetings, etc. - Monthly status report: The team will send the report including chart showing EV, PV and AC current in addition to future values for stakeholders. - 24/7 connectivity: The group is connected to each other via GitHub servers - Meeting: A meeting will be held at the end of each week to assess the situation and to the project manager give corrective direction if needed. 6. Sign-off
Name Signature Date (MM/DD/YYY Y)
Executive Sponsor IRUKA^ NASATO^ IRUKA NASATO^ 11/26/
Department Sponsor SHIRUKA MAJUI^ SHIRUKA MAJUI^ 11/26/
Project Manager Ho Xuan Hong^ Ho Xuan Hong^ 11/26/
7. Notes
_10. Milestone and schedule .........................................................................................................
II. CONDUCT A SMALL SCALE RESEARCH, INFORMATION GATHERING AND DATA COLLECTION TO SUPPORT THE PROJECT.
_1. Quantitative question ............................................................................................................
- The project budget aims to create a project that is beneficial to consumers and helps those who have lost their
- The project budget is supported by investors and other stakeholders on the software and various related