Conditional SWPPP Example Narrative
CONTRACTOR would like to start clearing trees from the work sites to prepare
them for construction activity. We intend on cutting down the trees and leaving
them in place until a later date. The trees will be cut with chain saws fueled with
gasoline. Vehicles fueled with either gasoline or diesel will be used to access the
locations but will be parked at the peripheries of the work sites to minimize soil
disturbance. Access to the individual tree locations will be via foot. Drainage
conveyances will be avoided during the tree falling operation. Tree falling activities
will not result in blocked drainage pathways and drainage inlets. Portable toilets will
be towed to the sites via truck. They will remain hitched to the truck for the
duration of each work day and towed off the site at the end of shift.
(
Equipment/Tools
(
Trucks (gasoline or diesel)
Chain Saws (gasoline)
Hand saws
Axes
(
Support Facilities
(
Portable toilets (mobilized and demobilized daily)
(
BMPs
(
SS-01 Scheduling
SS-02 Preservation of Existing Vegetation
SC-04 Check Dams
SC-06 Gravel Bag Berm
NS-09 and -10 Vehicle/Equip Fueling and Maintenance
SC-07 Street Sweeping
WM-04 Spill Prevent/Control
WM-09 Sanitary/Septic
((
CONTRACTOR SIGNATURE, DATE

Partial preview of the text

Download Conditional SWPPP approval for Tree Felling and more Summaries Forestry in PDF only on Docsity!

Conditional SWPPP Example Narrative CONTRACTOR would like to start clearing trees from the work sites to prepare them for construction activity. We intend on cutting down the trees and leaving them in place until a later date. The trees will be cut with chain saws fueled with gasoline. Vehicles fueled with either gasoline or diesel will be used to access the locations but will be parked at the peripheries of the work sites to minimize soil disturbance. Access to the individual tree locations will be via foot. Drainage conveyances will be avoided during the tree falling operation. Tree falling activities will not result in blocked drainage pathways and drainage inlets. Portable toilets will be towed to the sites via truck. They will remain hitched to the truck for the duration of each work day and towed off the site at the end of shift. Equipment/Tools Trucks (gasoline or diesel) Chain Saws (gasoline) Hand saws Axes Support Facilities Portable toilets (mobilized and demobilized daily) BMPs SS-01 Scheduling SS-02 Preservation of Existing Vegetation SC-04 Check Dams SC-06 Gravel Bag Berm NS-09 and -10 Vehicle/Equip Fueling and Maintenance SC-07 Street Sweeping WM-04 Spill Prevent/Control WM-09 Sanitary/Septic CONTRACTOR SIGNATURE, DATE