CE 220
CONSTRUCTION MANAGEMENT
HOMEWORK 5
(Chapter 9)
Assigned: Friday, October 12, 2007
Due: Friday, October 19, 2007
Grade: ___________________Name:___________________________________
Excellent (95-100%) Satisfactory (75%-95%) Unsatisfactory (bel ow
75%)
Computations (9 points) Calculations shown
and fully explained
neatly and logically
Minor errors in
calculation, steps in
calculations not
documented
Incorrect calculations,
missing steps in
calculations
Documentation (1 point) Follows
documentation and
formatting
procedures as shown
in class handout
One of the following
standards missing:
Title information
incorrectly placed.
Messy, illegible
handwriting
Two or more of the
formatting and
documentation
procedures were not
followed
Given the following cost expenditures for a small warehouse project, calculate the peak
financial requirement. Assume a 8% markup. Retainage is 5% throughout the project.
Finance charge is 18% per annum. Payments are billed at the end of the month and are
received one month later. Draw the overdraft profile, and present the total costs,
billings and payment on the same figure. (Note: When calculations give decimals,
round up
to the next dollar) (10 pts)
1
2
3
4
Direct Cost
10000
45000
55000
15000
Indirect Cost
1000
2500
3000
1200
pf2

Partial preview of the text

Download Construction Management - Sample Homework 5 | CE 22000 and more Assignments Building Materials and Systems in PDF only on Docsity!

CE 220

CONSTRUCTION MANAGEMENT

HOMEWORK 5

(Chapter 9)

Assigned: Friday, October 12, 2007 Due: Friday, October 19, 2007

Grade: ___________________ Name: ___________________________________

Excellent (95-100%) Satisfactory (75%-95%) Unsatisfactory (below 75%)

Computations (9 points) Calculations shown and fully explained – neatly and logically

Minor errors in calculation, steps in calculations not documented

Incorrect calculations, missing steps in calculations

Documentation (1 point) Follows documentation and formatting procedures as shown in class handout

One of the following standards missing: Title information incorrectly placed. Messy, illegible handwriting

Two or more of the formatting and documentation procedures were not followed

Given the following cost expenditures for a small warehouse project, calculate the peak financial requirement. Assume a 8% markup. Retainage is 5% throughout the project. Finance charge is 18% per annum. Payments are billed at the end of the month and are received one month later. Draw the overdraft profile, and present the total costs, billings and payment on the same figure. (Note: When calculations give decimals, round up to the next dollar) (10 pts)

Direct Cost 10000 45000 55000 15000 Indirect Cost 1000 2500 3000 1200

CE 220 CONSTRUCTION MANAGEMENT HOMEWORK 5 (Chapter 7)

  1. Given the following cost expenditures for a small warehouse project, calculate the peak financial requirement. Assume a 8% markup. Retainage is 5% throughout the project. Finance charge is 18 per annum. Payments are billed at the end of the month and are received one month later. Draw the overdraft profile, and present the total costs, billings and payment on the same figure. (Note: When calculations give decimals, round up to the next even dollar) (10 pts)

1 2 3 4 5 Direct Cost 10000 45000 55000 15000 Indirect Cost 1000 2500 3000 1200 Total Cost 11,000^ 47,500^ 58,000^ 16,

Total Billed ( 8% markup) 11,880^ 51,300^ 62,640^ 17,

Retainage withheld (5%) 594 2,565^ 3,132^0

Payment received 11,286^ 48,735^ 59,508^ 23,

Total cost to date 11,000^ 58,500^ 116,500^ 132,700^ 132,700^ 132,

Total amount billed to date 11,880^ 63,180^ 125,820^ 143,

Total received to date 11,286^ 60,021^ 119,529^ 143,

Overdraft at end of month 11,000^ 58,665^ 106,260^ 75,319^ 16,941^ -6,

Interest on overdraft balance 165 881 1,594^ 1,130^254 (1.5% interest per month)

TOTAL AMOUNT FINANCED 11,1^65 59,^546 107 ,^854 7 6,4^49 1 7,1^95