Critical Path Analysis: Rules for Total Float and Free Float, Lecture notes of Engineering management

The key rules for understanding and applying total float (tf) and free float (ff) in critical path analysis. It covers important concepts such as the minimum value of total float among activities following a node, the relationship between tf and ff for noncritical activities intersecting the critical path, the behavior of tf and ff in activity chains, and the equality of sums of durations and floats across different paths. The rules also address how to calculate ff for activities preceding a node with multiple predecessors. These principles are essential for effectively managing project schedules and identifying critical activities. A comprehensive guide to navigating the complexities of float calculations in network diagrams with at least one critical path.

Typology: Lecture notes

2020/2021

Uploaded on 05/11/2024

wadha-almutairi
wadha-almutairi 🇰🇼

2 documents

1 / 11

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
pf3
pf4
pf5
pf8
pf9
pfa

Partial preview of the text

Download Critical Path Analysis: Rules for Total Float and Free Float and more Lecture notes Engineering management in PDF only on Docsity!

Chapter 1

Rules for TF & FF

CE 435

Dr. Amani S. Bu-Qammaz

January 2021

Example

Activity Predecessor Duration

A

  • 1

B

A 5

C

B 3

D

C 2

E

D 1

F

E, I 3

G

F 3

H

F 5

I

A 7

J

I, K 8

K

A 7

7 Rules

for TF &

FF

These rules apply specifically when an

arrow diagram has at least one critical path

along which the total float is zero.

The accuracy of some of the rules will be

impacted by the placement of dummies in

certain portions of the network, but these

impacts rarely occur. Note that it is

assumed that the late finish date and the

early finish date of the last activity are the

same.

1. There is a minimum value of total float among the activities

following each node, and this minimum value is equal to the

minimum value of the total float values among the activities

that precede the node,

TF =

TF =

TF =

Rule 1

3. The free float of a noncritical activity intersecting the critical

path equals its total float.

0

5

5 9

9 13

15

22

0 3 3 9

15

9

0

7

19

15

15

15

2

7 7 11 11 15 15

22 15

15

18

22

15

9

15

0 3 3 9

8

0

0

22

22

TF =

FF =

2

2

TF=

FF=

8

8

TF=

FF=

3

3

Rule 3

4. In a chain of activities (a series of activities consisting of only

one activity preceding the node and only one activity following

each node), the total float for all activities in that chain is the

same. Also, except for possibly the last activity in the chain,

the free floats of the activities are 0,

Rule 4

0

5

5 9

9 13

15

22

0 3 3 9

15

9

0

7

19

15

15

1

5

2

7 7 11 11 15 15

22

15

15

18

22

15

9

15

0 3 3 9

8

0

0

22

22

FF = 0 FF = 0

FF = 2 FF = 0

FF = 0

FF = 0 FF = 0

FF = 8

FF = 3

FF = 0

Path Sum FF Sum Duration Total
A,B,F and H
D,E,G and H
D,E,G and I
C and I
C and H

0+0+2+0=

0+0+0+0+0=

0+0+0+3=

8+0+0=

5+4+4+7=

3+6+6+0+7=

3+6+6+4=

7+0+7=

2+20=

0+22=

3+19=

8+14=

Rule 5 .. Continued

6. When more than one activity precedes a node, first identify the

activity following the node that has the smallest total float. This

value of total float will also be the smallest total float among the

activities that precede the node. The free float of the preceding

activity with the smallest total float will be 0. The free float of the

other activities can be calculated as follows:

FF

Act

= TF

Act

  • TF smallest TF value prior to node

TF

Act

= FF

Act

+ TF

smallest TF value prior to node

FF

2-

FF

3-

0

5

1

7. For all critical path activities, TF = FF = 0.

Rules 6 & 7