General crane safety-122 Questions and Answers-
100% Accurate.
1. The minimum crane team for a mobile crane on outriggers would consist of-
A)
The Crane Operator, Rigger Supervisor, and Crane Rigger
B)
The Crane Operator, Crane Supervisor, Rigger Supervisor, and Crane Rigger
C)
The Crane Operator, Crane Supervisor, and Crane Rigger
D)
The Crane Operator and Rigger-in-Charge
E)
The Crane Operator, Crane Walker, and Crane Rigger: C) The Crane Operator, Crane
Supervisor, and Crane
Rigger
2.
When operating floating cranes, you must start swinging or rotating quickly and stop
smoothly to prevent excessive barge list.
A)
True
B)
False:
B) False
3.
Extending a telescoping boom without lowering the hoist may result in "two-blocking"
the crane.
A)
True
B)
False: A) True
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a
pf1b
pf1c
pf1d
pf1e
pf1f
pf20
pf21
pf22
pf23
pf24
pf25
pf26
pf27
pf28
pf29
pf2a
pf2b
pf2c
pf2d
pf2e
pf2f

Partial preview of the text

Download General crane safety-122 Questions and Answers-100% Accurate. and more Exams Workplace Safety in PDF only on Docsity!

1 / 47

General crane safety-122 Questions and Answers-

100% Accurate.

1. The minimum crane team for a mobile crane on outriggers would consist of-

A) The Crane Operator, Rigger Supervisor, and Crane Rigger

B) The Crane Operator, Crane Supervisor, Rigger Supervisor, and Crane Rigger

C) The Crane Operator, Crane Supervisor, and Crane Rigger

D) The Crane Operator and Rigger-in-Charge

E)The Crane Operator, Crane Walker, and Crane Rigger: C) The Crane Operator, Crane Supervisor, and Crane

Rigger

2. When operating floating cranes, you must start swinging or rotating quickly and stop

smoothly to prevent excessive barge list.

A) True

B) False: B) False

3. Extending a telescoping boom without lowering the hoist may result in "two-blocking"

the crane.

A) True

B) False: A) True

2 / 47

4. All of the following require a license to operate EXCEPT a(n)-

A) Cab-operated category 3 bridge crane

B) Mobile hydraulic truck crane

C) Non-cab operated category 3 bridge crane

D) Articulating boom category 4 crane

E)Floor-operated category 2 bridge crane: C) Non-cab operated category 3 bridge crane

5. Which of the following lift types would NOT be considered a complex lift?

A) Multiple-crane lifts

B) Oxygen/Acetylene bottles in racks designed for lifting O C) Large

geometric shapes

D) Loads with multi-level attachment points

E)Hazardous or explosive materials: B) Oxygen/Acetylene bottles in racks designed for lifting

6. What is the minimum amount of rope that shall be on a grooved drum and a smooth drum?

A) There is no minimum

B) 4 full wraps, 2 full wraps

C) 2 full wraps, 3 full wraps

D) 6 full wraps, 4 full wraps

4 / 47

B) to prevent the load from swinging or rotating

C) when the supervisor approves their use

D) only when lifting the load to extreme heights: B) to prevent the load from swinging or rotating

10. What is the weight of a 24 square foot, 2 inch thick aluminum plate with a unit

weight of 15 lbs. per square foot of material per inch of thickness?

A) 348 pounds

B) 720 pounds

C) 6,720 pounds

D) 60 pounds

E) 120 pounds: B) 720 pounds

11. The two expiration dates that are of particular importance to crane operators are-

A) Vehicle registration expiration date

B) Hydraulic oil expiration date

C) CAC card expiration date

D) The certification expiration date of the crane

E)The crane operator's license expiration date: D) The certification expiration date of the crane

5 / 47 E) The crane operator's license expiration date

12. Which of the following is NOT an acceptable method of communication between

the signal person and the crane operator?

A) Signal Flags

B) Direct Voice

C) Hand Signals

D) Sound-powered Phones

E)Approved Radios: A) Signal Flags

13. What is a jib boom?

A) A boom that is attached to the main boom to allow rotation of the load

B) An extension attached to the main boom used when lifting light loads to a higher

elevation than that permitted by the main boom

C) A boom that is used to lift extremely heavy loads: B) An extension attached to the main boom used when lifting

light loads to a higher elevation than that permitted by the main boom

14. If you find cracking or flaking paint on a welded joint of a structural compo- nent on

the boom, you should

A) Look closer to see if it is a crack.

B) Report it immediately to your supervisor.

7 / 47

17. If you find a deficiency that will affect the safe operation of the crane during the pre-

operational check, all of the following actions must be taken EXCEPT-

A) Operate that specific function again to ensure there is a problem

B) Notify your supervisor

C) Note the finding on the ODCL

D) Secure the crane

E)Follow supervisor's instructions: A) Operate that specific function again to ensure there is a problem

18. Components that provide protection for operation and maintenance person- nel working

on or in the path of cranes are?

A) Operational Safety Devices

B) Alterations/Modifications

C) Load Controlling Parts

D) Load Bearing Parts

E)General Safety Devices: E) General Safety Devices

19. When setting up mobile cranes, the minimum clearance between the rotat- ing upper

works and fixed objects should be?

A) 1 foot

B) 2 feet

8 / 47

C) 3 feet

D) 4 feet

E) 5 feet: incorrect

D) 4 feet

20. The rated load of the hook block installed on a crane may limit the crane's lifting

capacity.

A) True

B) False: A) True

21. When crane accidents happen or damage is found, you must do all of the following

EXCEPT

A) Continue operating until the supervisor performs an evaluation

B) Put the load in a safe condition

C) Standby for instructions

D) Stop operations

E)Contact your supervisor: A) Continue operating until the supervisor performs an evaluation

22. When should the rotate locking device be engaged on a mobile crane?

10 / 47

D) Lower the boom prior to raising it

E)Lower the blocks prior to raising them: C) Raise the blocks and boom before lowering them

24. If the crane operator and the Rigger-in-Charge disagree on whether or not a load is

safe to lift, the operator should-

A) Follow the instructions of the Rigger-in-Charge

B) Note the incident on the back of the ODCL card

C) Not operate the crane until contacting the supervisor to resolve the issue

D) Proceed slowly with extreme caution

E)Tell his or her supervisor at the end of the shift: C) Not operate the crane until contacting the supervisor to resolve

the issue

25. Components that control, restrain, or position the load and upon failure W would

cause dropping, shifting, or uncontrolled movement of the load are

A) Alterations and/or modifications

B) Operational safety devices

C) Load bearing parts

D) Load controlling parts

11 / 47

E)General safety devices: D) Load controlling parts

26. The Rigger-in-Charge has primary responsibility for determining the weight of an

object to be hoisted; however, the operator must be satisfied that the estimated weight to be lifted will not exceed the safe load carrying capacity of the crane.

A) True

B) False: A) True

27. The crane operator must check the certification information on the crane for before

operating the crane.

A) Operator's name, license number, and expiration date

B) Certified capacity, gross vehicle weight, and expiration date

C) Crane ID number, OEM capacity, and test date

D) Certification expiration date, crane ID, and certified capacity

E)Crane manufacturer, crane ID, and certified capacity: D) Certification expiration date, crane ID, and certified

capacity

28. During performance of your pre-operational check of the crane, you find minor

deficiencies. What do you do?

A) Stop, secure the crane, and notify your supervisor. Do not operate the crane until the

13 / 47

C) Stop operation and notify engineering of the deficiency.

D) Note the deficiency on the ODCL and keep operating the crane until en- gineering arrives to

perform an evaluation.: B) Stop operations, notify your supervisor of the condition, and annotate the deficiency on the ODCL.

31. A portal crane with a capacity of 120,000 pounds is a crane.

A) Category 1

B) Category 2

C) Category 3

D) Category 4: A) Category 1

32. Crane Configuration: The Grove RT740 is equipped with a stowed tele-off- settable boom

extension. The whip line with a 7 and 1/2 ton headache ball is reeved over the auxiliary boom nose. The main block is a 45-ton 3-sheave w/cheekplates. Use the Grove RT-740 Rough Terrain Load Chart to answer this question: Find the net capacity for the main hook reeved with 6 parts of line using a 75-foot boom length at a maximum radius of 32 feet.

A) 18,988 pounds

B) 16,888 pounds

14 / 47

C) 15,888 pounds

D) 14,978 pounds

E)18,338 pounds: E) 18338?

not B) 16,888 pounds

33. The crane operator can check the accuracy of the load moment indicator (LMI) against

known weights and radii.

A) True

B) False: A) True

34. When making personnel lifts, the capacity of a mobile crane for a given radius is

reduced by-

A) 25%

B) 50%

C) 75%

D) 80%

E)100%: B) 50%

35. What should an operator do if he or she is not sure of the meaning of a signal?

A) Place the load in a safe area

B) Keep operating as long as he or she can see the load

16 / 47

A) Date of manufacture

B) Rated load

C) Manufacturer name, logo, or trademark: C) Manufacturer name, logo, or trademark

39. Manufacturer's load rating charts for cranes must be-

A) Posted outside the cab

B) Visible to the Crane Rigger

C) Available from the engineering department

D) Avallable from the supervisor

E)Visible to the operator: E) Visible to the operator

40. Why should crane swing be relatively slow?

A) so that the crane can be operated for longer periods

B) to prevent outward swing of the load due to centrifugal force

C) to keep the operator from having to correct misalignment

D) to prevent the load from falling out of the rigging gear: B) to prevent outward swing of the load due to

centrifugal force

41. A commercial truck mounted crane with a capacity of 14,000 pounds is a

17 / 47 crane.

A) Category 1

B) Category 2

C) Category 3

D) Category 4: D) Category 4

42. What is the definition of "boom length"?

A) the distance from the boom "heel" or "foot" pins to the jib attachment pins

B) the distance from the rotate base to the center of the boom tip sheave

C) the distance from the center of rotation on the crane to the center of the boom tip sheave

D) the distance from the boom "heel" or "foot" pins to the center of the boom tip sheave: D) the

distance from the boom "heel" or "foot" pins to the center of the boom tip sheave

43. On cranes, lowering the boom with the hook blocks raised will most likely result in

A) tipping

B) two-blocking

C) overloading

D) insufficient hook height

E)none of the above: B) two-blocking

44. Is it necessary for the operator to see the load or work area?

19 / 47

47. Which of the following steps DOES NOT apply to securing lattice boom cranes?

A) Place the boom at approximately 45 degrees

B) Disengage the master clutch

C) Lock down all foot brakes

D) Retract the boom fully

E)Engage all hoist pawls: E) Engage all hoist pawls

48. The maximum capacity for a crane can be limited by the number of parts of wire rope

reeved between the hook block and hoisting sheaves.

A) True

B) False: A) True

49. What is the bridge crane communications hand signal pictured with the palms up,

fingers closed, thumb pointing in the direction of motion, and jerking horizontally?

A) Bridge travel

B) Trolley travel

C) Hoist

D) Move slowly

E)Swing: B) Trolley travel

50. When can an unlicensed crane operator trainee operate a crane?

20 / 47

A) When their supervisor tells them to operate a crane

B) When he or she needs to operate a crane to get the job done

C) In an emergency

D) Only under the direct observation of a licensed operator: D) Only under the direct observation of a licensed

operator

51. Sling angles affect the actual stress on each leg of the sling. Lowering the angle

measured from the horizontal will-

A) Not change the actual stress on each leg

B) Double the stress on each leg

C) Cause the sling to be overloaded

D) Increase the stress on each leg

E)Decrease the stress on each leg: D) Increase the stress on each leg

52. Side loading a crane boom by dragging loads or lifting a load with a non-ver- tical hoist

may result in

A) Destructive stresses placed on the boom and sheaves

B) Possible overload due to swinging of the load after lift-off