Download Measurement Form for Construction Project: Units of Measurement & Payment and more Slides Architecture in PDF only on Docsity!
Measurements in Estimating
PROFORMAS USED IN ESTIMATE
1. Measurement form
The details of measurements of each
item of work are taken out
and quantities of each and every
item is computed in a prescribed
form known as measurement form as under :-
Cont.
2. Abstract of cost form
The cost under each item of the work is
determined from the quantities and total cost is
worked out in a prescribed form called abstract
of cost form as shown on next slide
Cont.
Cont.
item no Description quantity unit of payment Rate Amount
Cost Form :
in the account of work and
when the cost is debited to
the suspense head “Materials”, the
account is called “Material at site
account “ M.A.S. accountis maintained
monthwise in form 35 as under
Name of Work …….
Cont.
total issues to the work principal items
unit quantity
pettyitem^ total
Dated initialssub-divisional of officer
Dated initialsdivisional as token ofaccountant check
1. Mass,voluminous and thick works shall
be taken in cubic unit or
volume. the measurements of length,
width and height or depth shall
be taken to compute the volume
or cubic contents
Cont. docsity.com
2. Shallow,thin and surface works shall
be taken in square unit or
in area. the measurement of length
and width or height shall be
taken to compute the area.
UNITS OF MEASUREMENT & PAYMENT
Earth Work
PARTICULARS OF ITEMS Measure Payment
- Earth filling under floors cu.m % cu.m
- Rock excavation cu.m %cu.m
- Puddle clay core cu.m %cu.m
PARTICULARS OF ITEMS Measure Payment
- Surface dressing and leveling,etc. Sq. m per sq. m
- cutting of trees no per no.
- Sand filling cu m per cu m
PARTICULAR OF ITEMS measure payments
- Precast cement concrete cu m per cu m
- Cement concrete jali work sq. m per sq. m
- Cement concrete bed plates cu m per cu m
PARTICULARS OF ITEMS measure payment
- First class burnt bricks in mud
mortar in foundation and plinth cu m per cu m
- First class burnt bricks in mud
mortar in super structure cu m per cu m
BRICK WORK
STONE WORK
PARTICULARS OF ITEMS measure payment
- Coursed rubble masonry in mud mortar in foundation and plinth cu m per cu m
- Coursed rubble masonry in mud mortar in super structure cu m per cu m
PARTICULARS OF ITEMS measure payment
- Coursed rubble masonry in lime mortar 1:3 in foundation and plinth cu m per cu m
- Coursed rubble masonry in cement mortar 1:7 in foundation and plinth cu m per cu m
- Coursed rubble masonry in cement mortar 1:7 in super structure cu m per cu mdocsity.com