INSTANT PDF DOWNLOAD — NERC prep test 1 with 200 questions and correct answers for 2025–2026 certification preparation. Covers grid reliability standards, system operations, emergency procedures, compliance rules, transmission operations, and exam-style practice questions designed to help candidates pass the NERC certification exam. NERC Exam, Power Systems, Grid Operations, Reliability Standards, Exam Prep, Practice Questions, Study Guide, Certification Test NERC Prep Test, NERC Exam PDF, 200 Questions NERC, NERC Practice Test, Grid Operations Exam, Power System Test, NERC Study Guide, Reliability Standards Exam, NERC Questions Answers, NERC Mock Exam, Transmission Operations Test, NERC Certification Prep, Power Grid Exam, NERC Test Prep, System Operations Questions, NERC Review Guide, Electrical Grid Exam, NERC Practice Questions, NERC Exam Prep, NERC Answer Sheet
Typology: Exams
1 / 123
This page cannot be seen from the preview
Don't miss anything!





























































































a. Generator MVAR output would increase
b. All system capacitors would trip off-line
c. Generator MVAR output would decrease
d. All automatic reactors would connect to the system>ANS a. Generator MVAR output would increase
a. Shed firm load
b. Implement Active Load Management
c. Return outaged equipment to service
d. Request a voltage reduction>ANS c. Return outaged equipment to service
a. Request that a phase shifting transformer be installed
b. Reduce interchange transactions impacting the path
parameters
d. Reduce voltages on the transmission system>ANS c. Raise system voltages as high as possible, but within their operating parameters
a. Open all tie-lines to your neighbor
b. Ask the Reliability Coordinator for assistance
c. Shed load to mitigate the violation
d. Wait for the neighboring system to contact you>ANS b. Ask the Reliability Coordi- nator for assistance
a. Place all system capacitors in service
b. Reduce system load
c. Inform the Reliability Coordinator
d. Dump firm load>ANS c. Inform the Reliability Coordinator
outage will cause a thermal violation on a parallel path, which of the following actions would be the first one you would implement?
1 0. 1 0. If a Reliability Coordinator had to implement any type of line loading relief procedures, which of the following entities would they be coordinated with? Pick two.
a. Purchasing Selling Entities
b. Balancing Authorities
c. Transmission Operators
d. Load Serving Entities>ANS b. Balancing Authorities
c. Transmission Operators
1 1. 1 1. If a generator is lost in a neighboring Balancing Area, what would the impact be on the BAs transmission tie lines?
a. Nothing
b. A net increase of MW would come into your BAs system
c. A net increase of MW would go out of your BAs system
d. They would exceed their emergency limits>ANS c. A net increase of MW would go out of your BAs system 1 2. 1 2. According to the NERC Glossary, a constrained facility is defined as a transmission facility that is approaching, is at, or is beyond its?
a. SOL or IROL
b. Normal voltage parameters
c. Available Transfer Capability
1 5. 1 5. If your system is experiencing high system loads, high system imports, and transmission facilities loaded to 1 00%, which of the following situations would make the situation worse?
a. Loss of a distribution station
b. An internal generator tripping
c. A bulk capacitor connecting to the system
d. A 500 kV transmission line returned to service>ANS b. An internal generator tripping 1 6. 1 6. If a transmission line has a flow of 500 MW and the LODF for a parallel line due to the loss of this line is .25, how many MW will shift to this line if the line relays out of service?
a. 50 MW
b. 1 25 MW
c. 250 MW
d. 500 MW>ANS b. 1 25 MW
1 7. 1 7. If a transmission path is congested and it is determined that all curtail- able transactions have a 1 5% affect on the path, how many MW of transactions must be curtailed if 30 MW of relief is needed?
a. 1 5 MW
b. 30 MW
c. Within 24 hours
d. Within 30 days>ANS c. Within 24 hours
a. 2 days
b. 5 days
c. 1 0 days
d. 1 4 days>ANS b. 5 days
a. Only local management
b. All entities in the Interconnection
c. Any impacted system
d. NERC>ANS c. Any impacted system
a. By raising the power factor
b. By adjusting the governor control manually
c. By adjusting the generator excitation
d. By changing the speed of the turbine>ANS c. By adjusting the generator
a. Shunt reactors
b. Synchronous condenser
c. Generator
d. Capacitors>ANS a. Shunt reactors
a. Switch reactors in service to remove the peak
b. Request all generators to reserve MVAR for the peak
c. Switch all capacitors in service without regard to voltage levels
d. Get under the voltage by placing capacitors in service while maintaining operating limits>ANS d. Get under the voltage by placing capacitors in service while maintaining operating limits
a. 1 20 MVAR
b. 1 50 MVAR
c. 1 62 MVAR
d. 1 80 MVAR>ANS c. 1 62 MVAR
reactive reserves, when should the reserves be restored?
c. Current transformer
d. Potential transformer>ANS b. Static Var Compensators
a. Increase the excitation
b. Increase the hydrogen pressure
c. Decrease the excitation
d. Decrease the hydrogen temperature>ANS c. Decrease the excitation
a. Transformer
b. Shunt reactor
c. Shunt capacitor
d. Generator>ANS d. Generator
a. It will be increased by 1 0%
b. It will remain unchanged
c. It will be reduced by 1 0%
d. It will be reduced by more than 1 0%>ANS d. It will be reduced by more than