A compilation of questions and answers related to nerc (north american electric reliability corporation) standards. It covers various topics relevant to system operators, balancing authorities, and other entities involved in maintaining the reliability of the bulk electric system. The questions address emergency procedures, interchange transactions, system restoration, and compliance with nerc requirements. This resource is valuable for individuals preparing for nerc certification exams or seeking to enhance their understanding of grid reliability principles. Insights into the operational aspects of maintaining a stable and secure power grid, including load shedding, frequency control, and emergency response protocols. It serves as a practical guide for professionals in the electric power industry.
Typology: Exams
1 / 72
This page cannot be seen from the preview
Don't miss anything!

































































QUESTION: If due to a reliability event, an interchange transaction must be modified, how long does the Sink Balancing Authority have to modify the tag? - ANSWER-withing 60 minutes of the start of modification QUESTION: What is an example of a disturbance that has caused you system to become islanded? - ANSWER-Frequency Fluctuations QUESTION: What is an instance is which you use manual load shedding? - ANSWER-Continuous decline in frequency QUESTION: What actions should be implemented during a EEA 2 - ANSWER-Schedule emergency assistance, recall all non-firm exports, start all available generation According to Nerc Standards, an emergency interchange transaction can be exempt from tagging if it is less than - ANSWER-60 minutes
QUESTION: A BA or LSE that requests an EEA 3 must complete and EEA 3 report and submit it to the RC within how many days - ANSWER-2 business days QUESTION: During restoration efforts load pick-ups should not exceed percentage of synchronized generation capacity - ANSWER-5% QUESTION: What are the two components that a system operator should be aware of for controlling frequency during a system restoration if they are in an islanded situation - ANSWER- load and generation QUESTION: What system was put in place to provide RC's with a mechanism to handle energy deficiencies? - ANSWER-Energy Emergency Alerts QUESTION: What would be an appropriate situation for a system operator to shed load? - ANSWER-Transmission facility is overloaded, voltages are rapidly decaying, and no other situations are available
QUESTION: Which EEA is used to announce the change in transmission service priority? - ANSWER-EEA 2 QUESTION: Who is the only entity that can declare an EEA? - ANSWER- Reliability Coordinator QUESTION: Who must a system operator receive approval from to manually shed load? - ANSWER-No one QUESTION: Automatic load shedding schemes should consider the following 3 things.................................................................................................... .. - ANSWER-frequency, the rate of frequency decay, the rate of voltage decay QUESTION: Blackstart capabilities should be verified by------ANSWER-periodic testing QUESTION: Synchroscopes should be calibrated in------ANSWER-degrees QUESTION: What type of relay is relay 87? - ANSWER-Differential relay
QUESTION: If Ace is -50 before a disturbance it must return to - ANSWER-- 50 QUESTION: The disturbance recovery period is minutes after the start of of a reportable disturbance. - ANSWER- QUESTION: What are the 3 types of AGC? and what is AGC? - ANSWER- Constant Frequency, Constant Interchange, Tie-line Bias QUESTION: What type of relay is relay 21? - ANSWER-Distance relay QUESTION: Each BA shall operate its AGC on? - ANSWER-Tie-line frequency bias QUESTION: What type of relay is relay 64 - ANSWER-Ground relay QUESTION: If ACE is 50 before a disturbance it must return to - ANSWER- 0
QUESTION: The purpose of the is to detect abnormal system conditions and isolate fault condition to maintain reliability - ANSWER- protection system schemes QUESTION: the purpose is to ensure that responsible entities conduct a reliability assessment of each arranged interchange before it is implemented
QUESTION: If you lost firm system demand for 15 minutes, and your peak load for the previous year was > 3000MW, what is the threshold for the reporting criteria to NERC? - ANSWER- 300MW QUESTION: DOE requires a report for a sustained voltage reduction that is greater than
shed for system reliability that requires a NERC and DOE report is - ANSWER-100MW
QUESTION: Who is responsible for submitting and updating the Request for Interchange associated with a Dynamic Transfer - ANSWER-Purchase Selling Entity QUESTION: The amount of frequency change that occurs before the governor starts to respond
QUESTION: At what torque angle of operation does power typically begin to flow from the generator to the system? - ANSWER-10 degrees QUESTION: What is one of the criteria used to determine a System Operating Limit? - ANSWER- QUESTION: Which relay uses a combination of CT and PT measurements and operates when the ratio of the PT measurements to CT measurements is below a certain limit for a given time period. - ANSWER-Device 21 QUESTION: Each Generator Operator shall coordinate all new protective systems and all protective system changes with whom? - ANSWER- Transmission Operator and Host BA QUESTION: What type of relay signals can be sent over various types of communication channels - ANSWER-Pilot QUESTION: The is responsible for the Real-time monitoring and forecasting of solar and geophysical events that affect power grids and other technological systems. - ANSWER- SWPC
QUESTION: What is the role of the RC in the system restoration process? - ANSWER-Monitor restoration progress, coordinate restoration activities, restore the BES frequency within acceptable operating limits QUESTION: One or more facilities hosting operating personnel that monitor and control the BES in real-time to perform the reliability task is called a? - ANSWER-Control Center QUESTION: What is a document that identifies specific steps or tasks that should be taken by one or more specific operating positions to achieve specific operating goals - ANSWER- Operating Procedure QUESTION: A document that identifies general steps for achieving a generic operating goal - ANSWER-Operating Process QUESTION: How often must a System Restoration Plan be viewed? - ANSWER-Annually
QUESTION: A condition when the transmission network connections between a generating unit, or a geographic unit and the interconnection become weakened such that cascading events may occur - ANSWER-Dynamic instability QUESTION: The loss of a generating unit or plant after a close-in fault or short circuit that is not cleared quickly enough - ANSWER-Transient instability QUESTION: In NERC priority order, which facilities have the highest priority following a widespread regional blackout? - ANSWER-Bulk Electric System facilities QUESTION: What percentage of load gives a 1 Hz change in an island condition? - ANSWER-6- 10% (Think 6-10 day island vacation) QUESTION: If ACE is Zero but system Hz is off, what should a system operator do? - ANSWER- Nothing! ACE bias and interchange schedule will improve frequency QUESTION: If ACE is Zero, why not adjust generation to help frequency? -
ANSWER-Could overload equipment, this is a NERC violation