Oracle Primavera P6 Enterprise Project Portfolio Management Professional Actual Exam 2026 Question and Correct Answer With Rationales
Typology: Exams
1 / 23
This page cannot be seen from the preview
Don't miss anything!
















How can project stakeholders benefit from the dashboard functionality in Primavera P6? (Choose two) A. Access filtered metrics through configurable portlets B. Automate role assignments using dashboard data
C. View summary data across all active projects D. Adjust global calendars based on portlet input
When creating tasks under a WBS in Primavera P6, which of the following features are available? (Choose two) A. Assigning roles and resources to tasks directly B. Using WBS filters to display selected task groups C. Creating resource profiles specific to the WBS D. Viewing task hierarchy in outline or tree format
In Primavera P6, activities linked between different projects use __________ relationships to reflect their scheduling dependencies. A. Inter-WBS B. Cross-resource C. External D. Baseline
When should a project manager use the “Schedule All Open Projects” option in Primavera P6?
You want to analyze risks associated with specific activities. Which two actions can be taken directly in Primavera P6? (Choose two) A. Link risks to activities on the Activities page B. Assign risk categories to WBS codes C. View thresholds applied to activity-level risks D. Convert risk types into custom activity calendars
A project manager changes the resource units on a fixed duration task. What happens if the duration type is set to "Fixed Duration and Units"? A. Duration is reduced to match effort B. Units/Time increases to maintain duration C. New baseline values are automatically created D. Float is reset for that activity
You’re tasked with ensuring that resource leveling does not delay project completion. Which two actions would help ensure this in Primavera P6? (Choose two) A. Apply “Preserve Scheduled Early and Late Dates” option B. Level only selected activities with high priority C. Disable leveling for critical activities D. Restrict leveling to within total float
Which of the following actions can be performed on the Activities page in Primavera P EPPM? (Choose two) A. Change system-wide calendar settings B. View activity Gantt charts C. Assign resources directly to an activity D. Modify project-level codes and dictionaries
A. No difference B. Company BP is global; Project BP is shell-specific C. Project BP is global D. Company BP stores documents only Answer: B
A. Backup B. Creating new shells with predefined configurations C. Reporting D. Cost tracking Answer: B
A. Cost tracking B. Storing and controlling project documents C. Workflow routing D. Budget analysis Answer: B
A. User ID B. Budget line item classification C. Document folder D. Workflow stage Answer: B
A. Budget adjustment report B. Tracks funding sources and allocations C. Workflow chart D. Integration tool Answer: B
A. PDF template B. Automated calculation logic C. Workflow setting D. User permission Answer: B
A. Printing reports B. Selecting predefined data C. Deleting records D. Creating shells Answer: B
Answer: Structured interface for data entry
Answer: Upper = header data; Line Item = repeated detailed entries
Answer: Current workflow stage indicator
Answer: Modify multiple records simultaneously
31 – 50 (Advanced Administration Focus)
Answer: Permission Settings
Answer: Move configurations between environments
Answer: Deploying configurations to higher environment
Answer: Configuration design tool
Answer: Tracks system activity history
Answer: Aggregates data from other BPs
Answer: Parent-child shell relationship
Answer: Setting multi-currency support
Answer: Breakdown of contract values
Answer: Combine financial entries
Answer: Defines user permissions
Answer: Individual configurable field
Answer: Linked BP record for related transactions
Answer: Managing users, permissions, configurations
51. Which component allows administrators to define dynamic field behavior based on conditions? A. Cost Sheet B. Data Element Properties
C. Form Rules D. Dashboard Answer: C Rationale: Form Rules allow administrators to configure conditional logic such as hiding, showing, or making fields required based on other field values.
A. Define user IDs B. Auto-generate unique record identifiers C. Track audit logs D. Create cost codes Answer: B Rationale: Numbering schemes automatically generate structured and unique identifiers for Business Process records.
A. Record auto-deletes B. Workflow ends at that step C. Data exports automatically D. Shell closes Answer: B Rationale: Terminal steps indicate completion or rejection and prevent further routing.
A. Project Shell B. Program Shell C. Cost Manager D. Document Manager
A. Manual dropdown B. Field linked to another record or data source C. Dashboard chart D. Financial formula Answer: B Rationale: Dynamic pickers pull data from logs, BPs, or external sources.
A. Track workflow progress B. Display financial trends over time C. Audit user activity D. Configure shell hierarchy Answer: B Rationale: Summary curves visually represent budget, forecast, and actual cost trends.
A. Delete data B. Automatically fill fields based on rules C. Lock workflow D. Create shell templates Answer: B Rationale: Auto-population transfers or fills field data automatically from related records. 61 – 70 (Security & Configuration)
Answer: Administrators test user permissions Rationale: Allows admins to log in as another user to verify access rights.
Answer: User can see but not edit data Rationale: Restricts modification while allowing visibility.
Answer: Authentication integration with external identity provider Rationale: Allows centralized user authentication.
Answer: Directory-based user authentication Rationale: Synchronizes user credentials from enterprise directory services.
Answer: Duplicate shell configuration Rationale: Copies structure and setup from an existing shell.
Answer: Automatic rerouting after inactivity Rationale: Ensures approvals occur within defined timeframes.
Answer: Predicting final project cost Rationale: Combines actuals and projected costs.
Answer: Tracks contractor invoice requests Rationale: Manages payment approvals.
Answer: Tracks budget/scope changes Rationale: Captures approved modifications.
Answer: Visual representation of expenditures over time Rationale: Supports financial planning.
Answer: Defines exchange rate handling Rationale: Ensures accurate financial reporting across currencies.
Answer: Distributing cost across categories Rationale: Improves financial analysis.
Answer: Measure cost and schedule performance Rationale: Combines cost and schedule metrics.
Answer: Move funds between cost codes Rationale: Maintains budget flexibility. 81 – 100 (Advanced Scenario-Based Questions)
Answer: Missing permission assignment Rationale: Visibility depends on security settings.
Answer: Conditional routing configuration Rationale: Incorrect conditions may bypass steps.
Answer: Test in staging environment Rationale: Reduces deployment risk.