This is solved assignment for Management course. It was submitted to Prof. Ethaha Grewal. In this course, i learned many different concepts and basic topics of Management. Like in this file, you can see I learned about Pert, Chart, Network, Activity-On-Arrow, Node, Critical, Path, Aoa, Expected, Completion, Time
Typology: Exercises
1 / 3
This page cannot be seen from the preview
Don't miss anything!


Q. 1: Develop the PERT Chart/Network for this project. PERT Chart: Activity-on-arrow (AOA) network Activity-on-node (AON) network
Start a 10 b 6 c 15 d 12 e 20 f 5 g 3 h 6 i 3 End
Q. 2: Identify the Critical Path and Expected Completion Time. Critical Path: For critical path, we need to calculate earliest start and earliest finish time for each activity. At starting point the time is 0. Expected Completion Time: Expected completion time is equal to the sum of times of activities on the critical path. So Expected Completion Time = 6 + 15 + 12 + 20 + 3 + 6 + 3 = 65 Or it is the earliest finish time of last activity i.e. i and its earliest finish time is 65 Critical Path (in terms of events) for AOA Critical Path (in terms of activities) for AOA and AON 1-2-3-4-5-6-7-8 b-c-d-e-g-h-i
a (0, 10) 10 d (21, 33) 12 e (33, 53) 20 f (53, 58) 5 i (62, 65) 3