This is solved assignment for Management course. It was submitted to Prof. Ethaha Grewal. In this course, i learned many different concepts and basic topics of Management. Like in this file, you can see I learned about Pert, Chart, Network, Activity-On-Arrow, Node, Critical, Path, Aoa, Expected, Completion, Time

Typology: Exercises

2011/2012

Uploaded on 08/01/2012

akuti
akuti 🇮🇳

4.2

(23)

168 documents

1 / 3

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
PROJECT MANAGEMENT (MGMT627)
ASSIGNMENT NO. 2 SOLUTION
Q. 1: Develop the PERT Chart/Network for this project.
PERT Chart:
Activity-on-arrow (AOA) network
Activity-on-node (AON) network
Start
End
a
10
d
12
e
20
f
5
i
3
8
1
2
5
3
4
7
6
Start
a 10
b 6
c 15
d 12
e 20
f 5
g 3
h 6
i 3
End
pf3

Partial preview of the text

Download PERT Chart, Critical Path-Management-Assignment Solution and more Exercises Business Management and Analysis in PDF only on Docsity!

PROJECT MANAGEMENT (MGMT627)

ASSIGNMENT NO. 2 SOLUTION

Q. 1: Develop the PERT Chart/Network for this project. PERT Chart: Activity-on-arrow (AOA) network Activity-on-node (AON) network

Start End

a

d

e

f

i

Start a 10 b 6 c 15 d 12 e 20 f 5 g 3 h 6 i 3 End

Q. 2: Identify the Critical Path and Expected Completion Time. Critical Path: For critical path, we need to calculate earliest start and earliest finish time for each activity. At starting point the time is 0. Expected Completion Time: Expected completion time is equal to the sum of times of activities on the critical path. So Expected Completion Time = 6 + 15 + 12 + 20 + 3 + 6 + 3 = 65 Or it is the earliest finish time of last activity i.e. i and its earliest finish time is 65 Critical Path (in terms of events) for AOA Critical Path (in terms of activities) for AOA and AON 1-2-3-4-5-6-7-8 b-c-d-e-g-h-i

Start End

a (0, 10) 10 d (21, 33) 12 e (33, 53) 20 f (53, 58) 5 i (62, 65) 3