

























Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
A set of questions and answers related to pjm (pjm interconnection) operations, covering topics such as balancing control modes, system load forecasting, generator limits, regulation requirements, and emergency procedures. It offers insights into the practical aspects of power system management and control within the pjm region.
Typology: Exams
1 / 33
This page cannot be seen from the preview
Don't miss anything!


























Which of the following balancing control modes is used by PJM under normal operations? - ANSWER- Tie-Line Bias Which of the following influences does PJM consider when performing their system load forecast? - ANSWER-Weather Conditions & Day of the Week All of the following are limits that must be submitted to PJM for generating units EXCEPT:
Based on a generator capability curve, in order to maximize the MVAR output of the generator, it may be necessary to: - ANSWER-decrease the MW output of the unit PJM maintains a regulation quality standard which states that a generator may be certified to provide regulation only after it achieves three consecutive regulation test scores of at least - ANSWER-75% Which of the following would NOT be a cause for a sudden deviation in the balancing area ACE?
What is the hourly threshold for reporting to PJM that the unit cannot operate at its maximum capacity due to the fuel limitation? - ANSWER-72 hours What is the regulation requirement for the PJM balancing area during on-peak hours? - ANSWER-1.0% of the forecasted peak load What is the time requirement that a generator that wishes to self-schedule itself must provide to PJM? - ANSWER-20 minutes The PJM Peak Period Maintenance season occurs: - ANSWER-Between the 24th & 36th Wednesdays of the year Maintenance outage extensions may be granted provided that the request for an extension is made - ANSWER-Prior to the end of the outage What is the maximum time limit for the maintenance outages that occur during the PJM Peak Period Maintenance season? - ANSWER-9 days Which of the following is NOT a control mode that PJM considers? - ANSWER-Frequency Bias What are the two NERC control standards that PJM must score at least 100% in order to be compliant? - ANSWER-DCS (Disturbance Control Standard) and CPS When PJM activates shared reserves with NPCC, what is the normal ramp of the MW when the event is activated? - ANSWER-0 minutes What is the regulation required for operating the PJM balancing area during the midnight period? - ANSWER-1.0% of the forecasted peak load What is the threshold for PJM assigning or de-assigning regulation to generators? - ANSWER-+ / - 15 MW of the requirement
During system restoration, where is the most effecting operating point for those generators that are supplying regulation to the system? - ANSWER-At t he middle of their regulating operating range If you have three 150 MW generators with each having an eco min of 50 MW and emergency min of 20 MW, what would be the total Emergency Reducible amount that you would report to PJM? - ANSWER- 90 MW What would be the normal first step to be taken by the PJM Generation Dispatcher after a 1,000 MW unit tripping caused the ACE to indicate and the balancing area to be in a situation of severe under generation? - ANSWER-order all generators to load spinning reserve During severe Geomagnetic activity, PJM observes an indication of > 10 amperes at Missouri Avenue facility that is confirmed by a second source. The PJM operator should immediately implement: - ANSWER-Conservative Operation What emergency procedure would cause all Generation Owner Operators to submit emergency reducible information to PJM control center? - ANSWER-Min Gen Alert PJM issues a Cold Weather Alert when the forecasted temperature in Philadelphia is expected to be less than or equal to: - ANSWER-10 degrees F Which of the following facilities would be given a priority in restoring auxiliary power following a PJM system blackout?
During minimum generation conditions, in addition to having excess generation online, what is another problem that is usually incurred? - ANSWER-High voltages During restoration conditions, what amount of load must be shed in order to attain an increase in frequency 1.0 Hz? - ANSWER-6 - 10% During restoration conditions, sufficient load and generation must be available due to reactive charging currents. What is the approximate MVAR per mile of 500 kV transmission that should be anticipated? - ANSWER- 1.70 MVAR per mile Following a system shutdown, system frequency during the restoration process should be maintained at which of the following levels? - ANSWER-between 59.75 and 61.00 Hz Leading up to PJM emergency conditions, if PJM has the appropriate warning and time to implement all of their emergency procedures, what would be the typical order for issuing them? - ANSWER-Alerts, Warnings, Actions What is the dynamic reserve for a Generation Owner who has a steam generator online capacity of 1,000 MW and a CT online capacity of 200 MW assuming the rule of thumb is steam 5%, CT 25%, and hydro 15%? - ANSWER-100 mw Which of the following generators would quality for synchronized reserve under non-restoration conditions? a quickstart CT that can be loaded in 8 minutes a 300 mw steam unit that is at full output a hydro unit that is offline
a 150 MW steam unit that is loaded at 75 mw - ANSWER-a 150 MW steam unit that is loaded at 75 mw Following a system disturbance that caused a partial blackout, what would be the order of actions to be taken by the system operator?
According to the PJM market timeline, if a generator is not accepted in the day ahead market, it can submit a new bid during what period? - ANSWER-4:00 - 6:00 PM If a company has a regulation obligation, which of the following is NOT an option for satisfying their obligation?
What is the deadline for submitting generator bids into the DA market? - ANSWER-1200 hrs Which of the following items is NOT considered when clearing e DA market?
Which of the following, is the first reliability related action that a Generation Owner dispatcher should take when one of its generation facilities develops a problem that will require the generator to reduce is MW output? - ANSWER-Inform PJM dispatch and updated eDART A PJM Member has been granted a maintenance outage for one of their generators and has scheduled the generator to be removed from service at 2300 this evening. at 1900, the generator's tube leak worsened, and the generator tripped offline. The generator outage will be listed as: - ANSWER-Forced outage All of the following elements must be reported to PJM when an IRC is requested EXCEPT:
The Generation owner dispatcher should notify PJM and their Local Control Center: - ANSWER- immediately Daily capacity numbers that are reported to PJM dispatcher throughout the operating day should be based on what generator limit? - ANSWER-Eco Max What is the benefit of the PJM system operators requesting members to submit information for completing and IRC? - ANSWER-I.D. any reserve shortages that may exist How many synchronized reserve MWs should you report to PJM for a generator that has an eco min of 50 MW, Eco Max of 150 MW, current output of 100 MW, and can ramp at a rate of 8 MW per minute? - ANSWER-50 mw Real time transmission constraints or contingencies may be alleviated with generators operating - ANSWER-off cost (out of merit) Monitoring LMP may give insights into - ANSWER-system contraints PJM calls for which of the following to recover the ACE so that tie line schedules are maintained? - ANSWER-100% spinning If not cancelled by PJM, the min gen alert expires: - ANSWER-at the end of the specified light load period When PJM declares a hot weather alert, the generation dispatcher should:
Which of the following one-way communication system is used to disseminate information to market operation centers? - ANSWER-All-Call Real time bus prices may be monitored using - ANSWER-eDATA Which of the following actions is a violation of PJM two settlement market rules?
b. IRCs c. LMP information d. generator reactive capability changes - ANSWER-LMP Info Which of the following generating units would be eligible to set LMP? a. a self-scheduled (must run) steam unit b. a unit dispatched for constraint control c. a unit that is on for testing only d. a hydro unit in condensing mode - ANSWER-a unit dispatched for constraint control A tie line with MW flowing into the PJM control area trips. The system operator will see which of the following occur? a. ACE will decrease, frequency will decrease b. ACE will increase, frequency will increase c. ACE will decrease, frequency will remain the same d. ACE and frequency will remain the same - ANSWER-ACE and frequency will remain the same