Instructions for a pre-class exercise in the csci577a fall 2006 course at the university of southern california. The exercise involves using microsoft project to create a plan based on a provided tree diagram. Students are expected to submit their work during the cocomo/cocots and ms project tutorial session. Relevant readings include the ms project 2000 tutorial and leanmbase guideline v1.6.

Typology: Study Guides, Projects, Research

Pre 2010

Uploaded on 02/24/2010

koofers-user-2vc
koofers-user-2vc 🇺🇸

10 documents

1 / 2

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CSCI577a Fall 2006
Pre-class Exercise Microsoft Project Tutorial
Due: As per your schedule for the COCOMO/COCOTS and MS Project Tutorial
(I.e. you have to submit the exercise in during your tutorial COCOMO/COCOTS
and MS Project tutorial session)
Readings:
MS Project 2000 tutorial
(http://greenbay.usc.edu/csci577/fall2006/site/coursenotes/
LCP guideline - LeanMBASE Guideline V1.6
(http://greenbay.usc.edu/csci577/fall2006/site/guidelines/
Use the tree diagram below to generate an MS Project plan.
Hint:
The straight line arrows in the diagram indicate summary tasks child tasks relationship, while
the curved dashed lines indicate dependencies between tasks. Every block in the tree diagram
includes a stereotype which indicates if it is a summary task, mile-stone or a task. Note that
summary tasks and milestones do not have resources or durations.
PDF created with pdfFactory Pro trial version www.pdffactory.com
pf2

Partial preview of the text

Download Microsoft Project Tutorial Exercise for CSCI577a Fall 2006 and more Study Guides, Projects, Research Software Engineering in PDF only on Docsity!

CSCI577a Fall 2006 Pre-class Exercise – Microsoft Project Tutorial

Due: As per your schedule for the COCOMO/COCOTS and MS Project Tutorial

(I.e. you have to submit the exercise in during your tutorial COCOMO/COCOTS and MS Project tutorial session)

Readings:

  • MS Project 2000 tutorial (http://greenbay.usc.edu/csci577/fall2006/site/coursenotes/
  • LCP guideline - LeanMBASE Guideline V1. (http://greenbay.usc.edu/csci577/fall2006/site/guidelines/

Use the tree diagram below to generate an MS Project plan.

Hint: The straight line arrows in the diagram indicate summary tasks – child tasks relationship, while the curved dashed lines indicate dependencies between tasks. Every block in the tree diagram includes a stereotype which indicates if it is a summary task, mile-stone or a task. Note that summary tasks and milestones do not have resources or durations.