PrepIQ HAWAII ES Supervising Electrician Ultimate Exam, Exams of Technology

This license allows the holder to supervise and manage journeyman electricians and oversee large-scale electrical projects. The exam includes advanced NEC topics, load design, electrical system layout, supervisory duties, safety coordination, and project management. Candidates must be licensed journeyman electricians with additional experience.

Typology: Exams

2025/2026

Available from 03/28/2026

shilpi-jain-3
shilpi-jain-3 🇮🇳

2.3

(9)

81K documents

1 / 79

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
PrepIQ HAWAII ES Supervising
Electrician Ultimate Exam
**Question 1.** Which NEC article defines the requirements for industrial service
entrances?
A) Article 210
B) Article 230
C) Article 250
D) Article 430
Answer: B
Explanation: Article 230 of the NEC covers services, including the installation of
service-entrance conductors and equipment for industrial facilities.
**Question 2.** In a three-phase, 4-wire wye system, the neutral is grounded at the
service point. This arrangement is known as:
A) Ungrounded system
B) Isolated neutral system
C) Grounded wye system
D) High-leg delta system
Answer: C
Explanation: A grounded wye (or solidly grounded) system has the neutral
conductor bonded to ground at the service equipment.
**Question 3.** The voltage drop limit for feeder conductors supplying continuous
loads in industrial applications is typically:
A) 1%
B) 2%
C) 3%
D) 5%
Answer: B
Explanation: NEC recommends a maximum of 2% voltage drop for feeders feeding
continuous loads to maintain efficient operation.
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a
pf1b
pf1c
pf1d
pf1e
pf1f
pf20
pf21
pf22
pf23
pf24
pf25
pf26
pf27
pf28
pf29
pf2a
pf2b
pf2c
pf2d
pf2e
pf2f
pf30
pf31
pf32
pf33
pf34
pf35
pf36
pf37
pf38
pf39
pf3a
pf3b
pf3c
pf3d
pf3e
pf3f
pf40
pf41
pf42
pf43
pf44
pf45
pf46
pf47
pf48
pf49
pf4a
pf4b
pf4c
pf4d
pf4e
pf4f

Partial preview of the text

Download PrepIQ HAWAII ES Supervising Electrician Ultimate Exam and more Exams Technology in PDF only on Docsity!

Electrician Ultimate Exam

Question 1. Which NEC article defines the requirements for industrial service entrances? A) Article 210 B) Article 230 C) Article 250 D) Article 430 Answer: B Explanation: Article 230 of the NEC covers services, including the installation of service-entrance conductors and equipment for industrial facilities. Question 2. In a three-phase, 4-wire wye system, the neutral is grounded at the service point. This arrangement is known as: A) Ungrounded system B) Isolated neutral system C) Grounded wye system D) High-leg delta system Answer: C Explanation: A grounded wye (or solidly grounded) system has the neutral conductor bonded to ground at the service equipment. Question 3. The voltage drop limit for feeder conductors supplying continuous loads in industrial applications is typically: A) 1% B) 2% C) 3% D) 5% Answer: B Explanation: NEC recommends a maximum of 2% voltage drop for feeders feeding continuous loads to maintain efficient operation.

Electrician Ultimate Exam

Question 4. When calculating ampacity adjustment for conductors in a conduit with more than three current-carrying conductors, which factor is applied? A) Temperature correction factor only B) Derating factor based on number of conductors C) No adjustment required D) Only insulation type factor Answer: B Explanation: NEC Table 310.15(B)(3)(a) provides derating factors for more than three conductors in a raceway or cable. Question 5. A motor rated 15 hp, 460 V, 3-phase, 60 Hz, with a service factor of 1.15, requires a minimum full-load current of approximately: A) 16 A B) 21 A C) 25 A D) 30 A Answer: B Explanation: NEC Table 430.250 gives 15 hp motor full-load current as 21 A (rounded) for 460 V with SF 1.15. Question 6. Which type of grounding electrode is required to be at least 20 ft long and 2 in. in diameter when installed in concrete? A) Ground rod B) Concrete-encased electrode (Ufer) C) Ground ring D) Metal water pipe Answer: B Explanation: A concrete-encased electrode must be at least 20 ft of #4 rebar or equivalent, 2 in. minimum diameter, placed in concrete.

Electrician Ultimate Exam

Question 10. An industrial motor control center (MCC) must be supplied with a grounding conductor sized at least: A) 12 AWG copper B) 10 AWG copper C) 8 AWG copper D) 6 AWG copper Answer: C Explanation: NEC 250.122 requires the grounding conductor for an MCC to be sized based on the overcurrent device; for typical MCCs, 8 AWG copper is the minimum. Question 11. The appropriate NEC article for grounding and bonding of piping systems is: A) Article 250 B) Article 300 C) Article 430 D) Article 110 Answer: A Explanation: Article 250 governs grounding and bonding, including requirements for metal piping. Question 12. A transformer with a primary voltage of 13.8 kV and a secondary voltage of 480 V, rated 500 kVA, requires a minimum grounding electrode conductor size of: A) #6 AWG copper B) #4 AWG copper C) #2 AWG copper D) #1/0 AWG copper Answer: C Explanation: NEC Table 250.66 indicates a #2 AWG copper grounding electrode conductor for a 500 kVA transformer.

Electrician Ultimate Exam

Question 13. Which of the following is the correct NEMA rating for an enclosure used in a wet, outdoor industrial environment that also protects against dust? A) NEMA 1 B) NEMA 3R C) NEMA 4X D) NEMA 7 Answer: C Explanation: NEMA 4X provides protection against water, ice, and corrosion, suitable for outdoor wet and dusty industrial settings. Question 14. The NEC defines a “continuous load” as a load that: A) Operates for more than 2 hours continuously B) Operates for more than 3 hours continuously C) Operates intermittently throughout the day D) Operates only during peak demand periods Answer: B Explanation: A continuous load is any load expected to run for 3 hours or more without interruption. Question 15. For a 4-wire, 120/240 V single-phase service, the minimum size of the equipment grounding conductor (EGC) for a 100-A service is: A) 12 AWG copper B) 10 AWG copper C) 8 AWG copper D) 6 AWG copper Answer: B Explanation: NEC Table 250.122 specifies a 10 AWG copper EGC for a 100-A overcurrent device. Question 16. Which calculation is required to determine the neutral load on a three-phase, four-wire feeder supplying both single-phase and three-phase loads?

Electrician Ultimate Exam

B) Flameproof (Ex d) C) Increased safety (Ex e) D) Both A and C are acceptable Answer: D Explanation: Both intrinsically safe (Ex i) and increased safety (Ex e) are permitted for Class III, Division 1 lighting. Question 20. For a conduit system containing 5 current-carrying conductors, each rated 75 °C, the ampacity must be multiplied by which derating factor according to NEC Table 310.15(B)(3)(a)? A) 0. B) 0. C) 0. D) 0. Answer: B Explanation: For 4-6 conductors, the derating factor is 0.80; however, for 5 conductors at 75 °C, the factor is 0.80 (the table shows 0.80 for 4-6). The correct answer is therefore A. (Correction: The factor for 4-6 conductors is 0.80, so answer A is correct.) Question 21. The minimum size of a grounding electrode conductor for a 400 - amp service is: A) 8 AWG copper B) 6 AWG copper C) 4 AWG copper D) 2 AWG copper Answer: B Explanation: NEC Table 250.122 lists a 6 AWG copper grounding electrode conductor for a 400-A overcurrent device. Question 22. Which OSHA standard addresses lockout/tagout (LOTO) procedures for industrial electrical equipment?

Electrician Ultimate Exam

A) 29 CFR 1910.

B) 29 CFR 1910.

C) 29 CFR 1910.

D) 29 CFR 1910.

Answer: A Explanation: 29 CFR 1910.147 specifically covers the control of hazardous energy (LOTO). Question 23. In a PLC wiring diagram, the term “fieldbus” refers to: A) A high-voltage power distribution bus B) A digital communication network for sensors and actuators C) The main power supply to the PLC CPU D) The grounding bus for the control panel Answer: B Explanation: A fieldbus is a digital communication system that connects field devices (sensors, actuators) to the PLC. Question 24. The required spacing between a conduit and a metal water pipe that is used as a grounding electrode is: A) No spacing required if bonded B) Minimum 1 in. separation C) Minimum 2 in. separation D) Minimum 4 in. separation Answer: A Explanation: When a metal water pipe is used as a grounding electrode, it must be bonded; no separation distance is required. Question 25. For an industrial lighting circuit fed from a 480 V three-phase system, the recommended voltage drop limit for the branch circuit is: A) 1 % B) 2 %

Electrician Ultimate Exam

Answer: B Explanation: NEC Table 250.122 indicates a 12 AWG copper EGC for a 30-A overcurrent device. Question 29. Which of the following statements about impedance-grounded (neutral-grounded) systems is correct? A) They provide a low fault current path for all faults. B) They limit the fault current to a predetermined value. C) They are only used in residential wiring. D) They eliminate the need for a grounding electrode. Answer: B Explanation: Impedance-grounded systems intentionally limit fault current to a low, predetermined value to reduce damage and facilitate fault detection. Question 30. The NEC requires that a ground-fault protection of equipment (GFPE) be provided for circuits supplying: A) General-purpose receptacles in dwellings B) Commercial kitchen appliances only C) Metal enclosures of equipment rated 120 V or less D) None of the above Answer: C Explanation: NEC 250.119 requires GFPE for equipment enclosures supplied by circuits 120 V or less to protect against ground-fault currents. Question 31. A transformer’s primary is connected to a 13.8 kV system. The required minimum clearance between the transformer tank and a combustible wall is: A) 12 in. B) 18 in. C) 24 in. D) 36 in.

Electrician Ultimate Exam

Answer: C Explanation: NEC 110.26 requires a minimum of 24 in. clearance for equipment rated 600 V or higher from combustible material. Question 32. In an industrial setting, a Class II, Division 1 hazardous location requires that conductors be installed in: A) Rigid metal conduit only B) Plenum-rated cable only C) Cable listed for direct burial D) Any conduit approved for the hazard class Answer: D Explanation: Conductors must be installed in a raceway or cable listed for the specific hazardous classification; various conduit types may be acceptable. Question 33. The NEC permits the use of “tap conductors” for feeders when the tap length does not exceed 10 ft and the voltage drop is limited to: A) 3 % B) 5 % C) 7 % D) 10 % Answer: B Explanation: The 10-ft tap rule (NEC 240.21(B)(1)) allows a maximum voltage drop of 5 % for taps up to 10 ft. Question 34. For a motor starter with a rated short-circuit current of 30 kA, the protective device upstream must be rated at least: A) 30 kA B) 35 kA C) 40 kA D) 45 kA Answer: C

Electrician Ultimate Exam

Explanation: NEC 300.21 requires at least 1½ in. concrete cover for metal raceways installed in concrete. Question 38. The term “load factor” in industrial power calculations refers to: A) Ratio of demand load to maximum possible load B) Ratio of actual energy used to the nameplate capacity over a period C) Ratio of power factor to voltage drop D) Ratio of continuous load to non-continuous load Answer: B Explanation: Load factor is the average load divided by the peak load over a specific time period, indicating utilization efficiency. Question 39. A fire alarm system in an industrial building requires a dedicated 24 - VDC power supply. The minimum conductor size for the supply circuit (assuming a 5 A load) is: A) 14 AWG copper B) 12 AWG copper C) 10 AWG copper D) 8 AWG copper Answer: B Explanation: Using NEC Table 310.15(B)(16) and a 5 A load, 12 AWG copper is the minimum size for a 24-VDC circuit to avoid excessive voltage drop. Question 40. Which of the following is a requirement of NFPA 70E for arc-flash protection? A) Only a written lockout/tagout program is needed. B) Workers must wear arc-rated clothing based on the incident energy level. C) Arc-flash studies are optional for industrial facilities. D) No PPE is required if the voltage is under 600 V. Answer: B

Electrician Ultimate Exam

Explanation: NFPA 70E mandates the use of appropriate arc-rated PPE based on calculated incident energy for each task. Question 41. The Hawaii Revised Statutes (HRS 448E) specify that an electrician must be supervised by a: A) Licensed master electrician only B) Any person with a construction permit C) Licensed electrical contractor or master electrician D) No supervision required for apprentices Answer: C Explanation: HRS 448E requires that apprentices be supervised by a licensed electrical contractor or a master electrician. Question 42. In a three-phase, 4-wire system, the neutral conductor must be: A) Insulated with at least 600 V rating B) Uninsulated if grounded at the service C) Sized the same as the phase conductors D) Always larger than the phase conductors Answer: C Explanation: NEC 220.61 requires the neutral to be sized based on the calculated neutral load, often equal to the phase conductor size for balanced loads. Question 43. Which of the following is the correct method for calculating voltage drop in a feeder? A) Use the formula V = IR only, ignoring power factor B) Use the formula V = I × R × (1 + PF) C) Use the formula V = 2 × K × I × L / CM D) Use the formula V = I × (2 × R × L) / 1000 Answer: C Explanation: The NEC voltage-drop formula V = 2 × K × I × L / CM (where K is a constant, I is current, L is length, CM is circular mil area) is the standard method.

Electrician Ultimate Exam

Question 47. Which of the following is considered a “special occupancy” under the NEC? A) Residential dwelling B) Agricultural building C) Hazardous (classified) location D) Commercial office space Answer: C Explanation: Hazardous (classified) locations are designated as special occupancies requiring specific installation rules. Question 48. When installing a grounding electrode conductor in a raceway, the conductor must be: A) Bare copper only B) Insulated copper or aluminum with proper marking C) Any type of conductor as long as it is continuous D) Aluminum only Answer: B Explanation: NEC permits insulated copper or aluminum conductors, provided they are properly marked for grounding electrode use. Question 49. The minimum conduit fill for three #4 AWG THHN conductors in a ½-in. EMT is: A) 40 % B) 53 % C) 60 % D) 75 % Answer: B Explanation: NEC Table 1, Chapter 9, specifies a maximum fill of 53 % for three conductors in a conduit.

Electrician Ultimate Exam

Question 50. Which of the following is a required feature of an industrial MCC (Motor Control Center) enclosure? A) Built-in fire suppression system B) NEMA 4X rating for outdoor installations C) Internal explosion-proof rating for all compartments D) Integral power factor correction capacitors Answer: B Explanation: MCCs installed outdoors must meet the appropriate NEMA rating, typically NEMA 4X for protection against water and corrosion. Question 51. The NEC defines a “remote control circuit” (Class 2) as having a maximum voltage of: A) 30 VDC B) 60 VDC C) 100 VDC D) 120 VDC Answer: B Explanation: Class 2 circuits are limited to 60 VDC (or 30 VAC) per NEC 725.2. Question 52. In a medium-voltage substation, the required minimum clearance between live parts and the floor is: A) 3 ft B) 4 ft C) 5 ft D) 6 ft Answer: D Explanation: NEC 110.26 requires a minimum of 6 ft clearance for equipment rated 1000 V or higher. Question 53. Which type of cable is permitted for use in hazardous locations where the cable must be flame-retardant and have a low smoke emission?

Electrician Ultimate Exam

B) Placed in a separate conduit C) Identified with a different color insulation only D) Not required to be separated if the conduit is metal Answer: B Explanation: NEC 300.3(B) requires separate raceways for power and control conductors unless the conductors are insulated for the higher voltage and the conduit is metal. Question 57. The required size of a grounding electrode conductor for a 250-A service is: A) #10 AWG copper B) #8 AWG copper C) #6 AWG copper D) #4 AWG copper Answer: B Explanation: NEC Table 250.122 lists a #8 AWG copper grounding electrode conductor for a 250-A overcurrent device. Question 58. Which of the following is a permissible method for bonding a metal conduit that serves as an equipment grounding conductor? A) Using a bonding jumper at each outlet box B) Relying on the conduit’s continuity alone C) Installing a bonding screw at the service entrance only D) No bonding is required for metal conduit Answer: B Explanation: Metal conduit is permitted to serve as an equipment grounding conductor by virtue of its continuity, per NEC 250.118. Question 59. The NEC allows the use of “exothermic welding” for grounding connections in which situation? A) Only for temporary installations

Electrician Ultimate Exam

B) For permanent grounding of steel structures C) For grounding of flexible cords only D) Never; exothermic welding is prohibited Answer: B Explanation: Exothermic welding is an approved method for creating permanent, corrosion-resistant grounding connections for steel structures. Question 60. When sizing a feeder to a large HVAC unit rated at 150 kW, the design must consider which of the following? A) Only the nameplate rating B) Nameplate rating plus 125 % for continuous load C) Nameplate rating plus 150 % for start-up current D) Nameplate rating multiplied by power factor only Answer: B Explanation: HVAC equipment is considered a continuous load; NEC requires feeder sizing at 125 % of the nameplate rating. Question 61. Which NEC article governs the installation of underground direct-buried conductors? A) Article 300 B) Article 310 C) Article 330 D) Article 352 Answer: A Explanation: Article 300 covers general requirements for wiring methods, including underground direct-buried conductors. Question 62. The minimum conduit size for a 350 kVA transformer secondary conductor (3 AWG copper) is: A) ½ in. EMT B) ¾ in. EMT