Project Status Summary Report, Exercises of Engineering

A project status summary report for the fse100 | master project at arizona state university. It provides an executive summary, key schedule milestone tracking, tasks completed and planned, an updated gantt chart, and team evaluations for the first two days of implementation. The report covers the project manager, submission date, implementation week, project status schedule, project document repository, and detailed information on the kill switch task, including its current status and next steps. This comprehensive report aims to keep stakeholders informed about the project's progress, challenges, and upcoming plans to ensure successful project delivery.

Typology: Exercises

2023/2024

Uploaded on 10/24/2024

shanthi_48
shanthi_48 🇺🇸

4.8

(36)

891 documents

1 / 1

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Project Status Update: Master
Project [FSE100]
Project Status Summary Report [FSE100 |
Master Project]
Executive Summary
The project manager, Mohsen Sheibanian, has submitted the project status
report on 10/5/23 for the implementation week. The project status schedule
indicates that the launch is slightly behind schedule due to technical
difficulties with the kill switch.
Key Schedule Milestone Tracking from Gantt Chart
| Tasks | Target Date | Actual Date | Status (%) | Comments | | --- | --- | --- | ---
| --- | | Kill Switch | 10/3/23 | 10/5/23 | 50 | - Kill switch code written, no tests
on EV3
- Kill Switch implemented
- Building an apparatus for the motors and creating the code
- Testing the sensors |
Tasks Completed this Week
The report does not provide any information about the tasks completed this
week.
Tasks Planned for next Week
The report does not provide any information about the tasks planned for the
next week.
Gantt Chart Updated
The report indicates that the newest Gantt Chart has been added.
Team Evaluation for the Week
The team evaluation for the first day of implementation is provided, with
each team member (A.V, Y.L, J.J, Akshar, M.Z, Yi, Jonathan) being rated on a
scale of 0/5 (Absent) to 5/5 (Outstanding).
The team evaluation for the second day of implementation is also provided,
with the same team members being rated on the same scale.

Partial preview of the text

Download Project Status Summary Report and more Exercises Engineering in PDF only on Docsity!

Project Status Update: Master

Project [FSE100]

Project Status Summary Report [FSE100 |

Master Project]

Executive Summary

The project manager, Mohsen Sheibanian, has submitted the project status report on 10/5/23 for the implementation week. The project status schedule indicates that the launch is slightly behind schedule due to technical difficulties with the kill switch.

Key Schedule Milestone Tracking from Gantt Chart

| Tasks | Target Date | Actual Date | Status (%) | Comments | | --- | --- | --- | --- | --- | | Kill Switch | 10/3/23 | 10/5/23 | 50 | - Kill switch code written, no tests on EV

  • Kill Switch implemented
  • Building an apparatus for the motors and creating the code
  • Testing the sensors |

Tasks Completed this Week

The report does not provide any information about the tasks completed this week.

Tasks Planned for next Week

The report does not provide any information about the tasks planned for the next week.

Gantt Chart Updated

The report indicates that the newest Gantt Chart has been added.

Team Evaluation for the Week

The team evaluation for the first day of implementation is provided, with each team member (A.V, Y.L, J.J, Akshar, M.Z, Yi, Jonathan) being rated on a scale of 0/5 (Absent) to 5/5 (Outstanding).

The team evaluation for the second day of implementation is also provided, with the same team members being rated on the same scale.