Risk Management Guide, Study notes of Credit and Risk Management

A guide to risk management in project delivery. It covers the roles and responsibilities of team members, the risk management process, and provides a risk assessment worksheet. The guide emphasizes the importance of communication and collaboration in managing risks and provides a flowchart to help visualize the process. useful for students studying project management, risk management, or business management.

Typology: Study notes

2021/2022

Uploaded on 05/11/2023

gaqruishta
gaqruishta 🇺🇸

4.4

(18)

237 documents

1 / 20

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Risk Management Guide
Version 1.0
April 2021
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14

Partial preview of the text

Download Risk Management Guide and more Study notes Credit and Risk Management in PDF only on Docsity!

Risk Management Guide

Version 1.

April 2021

Risk Management Guide i

    1. Introduction Table of Contents
    1. Risk Management
    1. Roles and Responsibilities
    1. Risk Management Process.....................................................................................................................
  • 4.1. Project Initiation Stage (Stage 1)
    • 4.1.1. Purpose
    • 4.1.2. Perform the Initial Risk Identification and Assessment in PSR
  • 4.2. Alignment Defined, Plan-In Hand, PS&E Stages (Stages 2, 3 & 4)
    • 4.2.1. Purpose
    • 4.2.2. Populate & Regularly Update the RAW
    • 4.2.3. Cost Estimate Reviews (CER’s)
  • Appendix A : Risk Management Roles and Responsibilities A- List of Appendices
  • Appendix B : Risk Management Flowchart ...............................................................................................B-
  • Appendix C : Risk Assessment Worksheet (RAW) Guidance and Link to Template................................... C-

Risk Management Guide 1

  1. Introduction

Every day, NCDOT and consultant project staff inherently identify risks as part of their daily routine of working on or managing projects. Risks are defined as uncertainties that, if they occur, would be an obstacle or opportunity in meeting the project objectives. Throughout the planning, design, construction, and maintenance processes, many project staff, Project Managers, and discipline experts handle uncertainties, often in a “fire-fighting” manner. However, early identification and continuous management of risks reduces negative impacts, promotes timely decision making, and improves our success in meeting project objectives and delivering what we promised.

Risk management is an NCDOT best practice required for all projects and business units. This guide focuses on managing risks throughout the preconstruction phase of project delivery, specifically Stages 1, 2, 3 and 4 in the Project Development Network (PDN). This guide describes what Risk Management is, defines the roles and responsibilities and provides a consistent, scalable process to manage risk.

  1. Risk Management

Risk Management is a proactive process designed to minimize potential obstacles that may negatively impact a project’s objectives (scope, schedule, budget, quality, and commitments) and maximize the ability to capitalize on opportunities that may improve project delivery. It’s not a one-size-fits-all process and should be scaled to meet the needs of the project. The Division of Planning & Programming (Feasibility Studies and Corridor Development Units) and Project Managers are responsible for coordinating with their team members, discipline units, Division Engineers, consultants, and the appropriate project Stakeholders to develop and manage their project risks. How well project teams plan for and respond to uncertainties can significantly impact the successful delivery of the project.

Managing risks focuses on communicating with the project team early and often to:

  • Identify uncertainties
  • Assess the potential probability and impact (to help prioritize)
  • Develop a response strategy
  • Develop plan to continuously manage and monitor risks

Risks are initially identified during the Project Initiation Stage (PDN Stage 1), after the project is programmed in the STIP. During this stage, the Project Scoping Report identifies and assesses risks in the Project Initiation Form and in the Screening Checklist, respectively. When a project transitions into the Alignment Defined Stage (PDN Stage 2), these forms should be used to begin developing the Risk Assessment Worksheet (RAW), a tool for the Project Manager to use throughout Stages 2, 3 and 4 to document and manage project uncertainties. The RAW is developed right after Notice to Proceed (NTP), during the Alignment Defined Stage and is refined during the Plan-In Hand Stage (PDN Stage 3) and the PS&E Stage (PDN Stage 4). Risks evolve as the project evolves; therefore, it is essential that risks are continuously identified, evaluated, communicated among team members, monitored, managed, and refined as the project advances through these phases. The RAW can continue to be refined as the project moves through Construction and Maintenance; however, this document focuses on the activities that occur during Preconstruction.

Risks are “the effects of uncertainty on objectives”

International Standard ISO

Risk Management is the art of managing uncertainties.

Risk Management Guide 2

  1. Roles and Responsibilities

Many individuals are involved in the delivery of a project. Strong teamwork, communication and collaboration throughout the process creates transparency allowing team members to have a mutual understanding of the project objectives, awareness of the efforts of other team members, and coordination on how they can collectively work together to meet those objectives. This improves decision making and allows the team to react quickly to uncertainties when they are realized. The chart below describes the various risk management roles and responsibilities across the life of a project.

Risk Management

Roles^1 and Responsibilities

Responsible, Consulted, Informed

Value Management ProgramManager

Project Initiation

Alignment Defined, Plan-In Hand, PS&E

Division Project Delivery /Development Engineer

3

Division of Planning &Programming Planning Team Members

2

Division Project Delivery /Development Engineer

3

Project Manager Project Team Members Risk Owner

4

Initial Risk Identification & Assessment

Provide expectations and assumptions to project objectives C R I

Identify project risks in Project Initiation Form I R C

Assess risks in Screening Checklist I R

Develop RAW Provide expectations and assumptions to project objectives C R I

Place RAW on the Preconstruction SharePoint site I R Review risks in the Project Scoping Report (PSR), develop all sections in the Risk Assessment Worksheet (RAW) and identify any additional risks R^ C Notify VMO when initial RAW is developed I R

The biggest risk is the failure to communicate.

Risk Management Guide 4

  1. Risk Management Process

NCDOT requires all staff to proactively manage risks for all projects programmed in the STIP, regardless of project size; however, this process is scalable to fit the need of the project. Going through the risk management process is a collaborative team effort, which can take very little time or can require extensive coordination with multiple discipline units, Divisions, Chief’s Office, or Secretary’s Office. Risk management requires the Division of Planning & Programming and the Project Manager to lead teams and seek input from the appropriate stakeholders throughout all stages of the project.

4.1. Project Initiation Stage (Stage 1)

4.1.1. Purpose The purpose of risk management in the Project Initiation Stage is to identify potential uncertainties that may impact the project scope, schedule, budget, quality or commitments because projects that experience major changes in these areas later, may be required to go through reprioritization.

4.1.2. Perform the Initial Risk Identification and Assessment in PSR During the Project Initiation Stage (PDN Stage 1), after the project is programmed in the STIP, the Division of Planning & Programming and Planning Team Members are responsible for identifying risks in the Project Initiation Form and assessing risks in the Screening Checklist (forms are available on the Scoping Connect Site).

Project Initiation Form The Project Initiation Form has a Risk Section intended to provide a high-level overview of what risks exist at this stage of the project. The individual or team identifying risks at this stage, indicate which risks or potential uncertainties exists on the project by checking the associated boxes in this section of the form and adding any additional risks that may not be included on this form. If a certain risk does not exist for the project, then it remains unchecked.

Objectives

  • Identify risks in the

Project Initiation Form

  • Assess risks in the

Screening Checklist

  • Provide risks to be

considered for Project

Scoping

Roles Involved

  • Division Project Delivery/

. Development Engineer/

. PMU Team Lead

  • Division of Planning &

. Programming

  • Planning Team Members
  • Value Management

. Program Manager - for

. support

  • Local Stakeholders

Risk Management

Sections

  • Risk Identification
  • Risk Assessment

Risk Management Guide 5

Screening Checklist The Risk Section in the Screening Checklist lists possible risks on a project and focuses on assessing the impact of the risks identified in the Project Initiation Form. The individual or team assessing the risks is expected to identify the potential impact associated with the risks identified on the Project Initiation Form. If a risk does not apply to a particular project, N/A can be placed in the comments section of the risk to indicate this.

Both forms are part of an existing process and are included in the Project Scoping Report (PSR). The Value Management Office (VMO) will automatically be notified when a PSR is completed so they can evaluate the project’s level of risk exposure and determine if the project would benefit from having a formal Risk Assessment Study in a future stage. Guidance on formal Risk Assessment Studies is being developed and this document will be updated when that is available. For these projects, the VMO will coordinate with the Project Manager to determine when a formal Risk Assessment Study is appropriate.

4.2. Alignment Defined, Plan-In Hand, PS&E Stages (Stages 2, 3 & 4)

4.2.1. Purpose The purpose of risk management during the Alignment Defined (PDN Stage 2), Plan-In Hand (PDN Stage 3) and PS&E stages (PDN Stage 4) is to proactively identify potential uncertainties that may impact the project scope, schedule, budget, or commitments to improve timely and informed decision-making and successfully deliver what we promised our stakeholders.

Objectives

  • Populate the RAW
  • Regularly update and

refine the RAW

  • Continuously monitor and

manage risks

Roles Involved

  • Division Project Delivery/

. Development Engr./

. PMU Team Lead

  • Project Manager
  • Project Team Members
  • Risk Owners
  • Value Management.

. Program Manager - for

. support

  • Stakeholders & Resource

. Agencies

Risk Management

Sections

  • Risk Identification
  • Risk Assessment
  • Response Strategy
  • Management &

. Monitoring Plan

Risk Management Guide 7

o “if” describes the risk/uncertainty (event) and o “then” describes the potential effect or impact to the project objective (consequence)

For example: If Section 4(f) properties are involved in the project area, then delays to the project schedule may occur if potential impacts and avoidance options are not proactively and realistically identified, assessed and coordinated.

Risk AssessmentEvaluate the Probability and Impact of Uncertainties : Risks are evaluated by assessing the probability of occurrence and the impact the uncertainty may have on the project objectives if the risk is realized/accepted. Assessing these helps the Project Manager prioritize risks. The Project Manager is responsible for coordinating these efforts with the Project Team.

 A score is automatically calculated for each uncertainty to help prioritize risks with high levels

of exposure and is based on the input for probability and impact. Uncertainties with a high score have high levels of exposure and are higher priorities to mitigate/address. The Project Manager is responsible for prioritizing risks.

Response StrategyDevelop and Refine Response Strategies : The Project Team is responsible for collaborating with the Project Manager to select the appropriate response strategies, which consist of defining the approach the team will take to effectively minimize obstacles and/or enhance opportunities (avoid, mitigate, transfer, accept or enhance). The Project Team members are also responsible for developing action items, acting as the Risk Owners and collaborating with the Project Manager to identify sufficient follow-up dates for all risks. The Risk Owner is an individual whose area of expertise relates to a specific risk and is responsible for implementing action items, monitoring progress and updating the Project Manager and Project Team on the status of the risk.

Monitor and ControlDevelop Management and Monitoring Expectations: Frequent monitoring of project risks allows the Project Manager and Project Team to discuss risk mitigation efforts, determine if the strategy identified is effective, if modifications to the action plan need to occur, and make timely decisions. This minimizes the frequency at which risks evolve into significant issues and cause major delays or significant cost increases. This section in the worksheet consists of specifying an update frequency and an area to keep status updates. The Project Manager is responsible for collaborating with the Project Team to identify the update frequency expectations for each risk. The Risk Owner is responsible for documenting any status updates.

Monitor and Manage Risks on a Regular Basis: Effective risk monitoring is a continuous iterative process that extends throughout the life of the project. Project Teams are expected to regularly:

o Identify any new risks

Risk Management Guide 8

o Assess whether the probability or impact to the project objectives have changed (causing the risk score to change) o Allow Risk Owners to provide progress updates and discuss any obstacles encountered with implementing risk response strategies and action items These discussions can be part of a project progress meeting or separately planned risk review meetings. It is the responsibility of the entire team to maintain open communication and transparency with the Project Manager, Project Team, Management, Project Stakeholders, and (if needed) the VMO. This can improve the ability to obtain additional resources and organizational support when risks become realized or accepted.

Regular Updates

The Project Manager is responsible for ensuring the RAW is regularly updated and for continuing the management of risks as the project evolves through Stages 2, 3 and 4 (see flowchart in Appendix B).

At letting, the Project Manager is responsible for ensuring that the latest RAW is uploaded to the Preconstruction SharePoint site and notifying the Resident Engineer. The Resident Engineer is provided with a link to the Project’s Preconstruction SharePoint site in their Construction SharePoint site and will have access to the RAW.

4.2.3. Cost Estimate Reviews (CER’s) Projects that require Federal assistance and exceed $500 million in cost, must follow the Federal Cost Estimate Review (CER) process which requires a risk-based review workshop. CER’s are typically conducted at least 90 days prior to the approval of the NEPA decision and reviewed again before the beginning of the Construction phase. The VMO is available to assist project teams through this process. Additional information regarding CER’s is available at: https://www.fhwa.dot.gov/majorprojects/cost_estimating/index.cfm

Risk Management Guide A-

Risk Management Roles and Responsibilities Table

Role Responsibilities Value Management Program Manager

  • Review the Project Initiation form and Screening Checklist in the PSR and the Risk Assessment Worksheet and coordinate with Division of Planning & Programming or Project Manager to determine if/when a formal Risk Assessment Study is appropriate.
  • Facilitate & Organize Risk Assessment Study if projects have substantial impacts, constructability concerns or many external stakeholders
  • Support Project Managers and Project Teams Division Project Delivery/ Development Engineer or PMU Team Lead
  • Coordinate with the Project Manager and the Division of Planning and Programming to ensure project objectives and assumptions are met Division of Planning & Programming
  • The Division of Planning & Programming includes the Feasibility Study Unit and the Corridor Development Unit
  • Identify and assess risks in the Project Initiation Form and Screening Checklist, which are included in the PSR Planning Team Members (^) • The Planning Team refer to NCDOT staff, MPO, RPO, resource agencies, local stakeholders, and consultants
  • Collaborate with Division of Planning & Programming to identify and assess risks in the Project Initiation Form and Screening Checklist Project Manager (^) • Collaborate with Planning Team to review risks in the Project Initiation Form and the Screening Checklist to develop the RAW
  • Communicate project objectives, assumptions, and expectations with the Project Team and the Project Delivery/Development Engineer or PMU Team Lead
  • Inform the Project Delivery/Development Engineer or PMU Team Lead of the status and progress of major risks
  • Upload the RAW to the VMO library on the Preconstruction SharePoint Site and ensure updated regularly
  • Responsible for collaborating with the Project Team to regularly update all sections of the RAW (Identification, Assessment, Response Strategy and Management and Monitoring strategy)
  • In the event that a RAS is needed, coordinate with the VMO Project Team Members • Project Team members include NCDOT staff and consultants
  • Collaborate with the Project Manager and project team to: o Identify new risks and close out resolved risks o Periodically reassess/validate impact and probability of risks o Identify response strategy, develop action plan & identify risk owner
  • Project Team members could be Risk Owners Risk Owner • Subject matter expert on a risk
  • Lead implementation of action items
  • Manage and monitor progress of the risk response strategy
  • Provide regular status updates to Project Manager and Team
  • Gather approval from Project Managers prior to the acceptance of risks

Risk Management Guide B-

: Risk Management Flowchart

Risk Management Guide C-

: Risk Assessment Worksheet (RAW)

Guidance and Link to Template

Risk Management Guide C-

Risk Assessment Worksheet (RAW) Guidance

There are four sections that make up the RAW:

Risk Identification

Risks are identified by the following characteristics:  Number: Identifier for each risk (I, 2, 3...)  Risk Name: Develop a risk statement by identifying the uncertainty and the effect it has on the project objective (scope, schedule, budget, quality or project commitment). Clear and specific risk statements are essential to effectively managing risks. If risk statements are too vague, they will be hard to manage and can lead to confusion when developing and implementing response strategies. Clear and specific risk statements can be accomplished with “if/then” statements where: o “if” describes the risk/uncertainty (event) and o “then” describes the potential effect or impact to the project objective (consequence)

For example: If Section 4(f) properties are involved in the project area, then delays to the project schedule may occur if potential impacts and avoidance options are not proactively identified, assessed and coordinated.

Threat / Opp.: Indicate whether a risk is a threat to the project objectives or is an opportunity to improve the project objectives (save project costs, advance the schedule, etc.)  Status: Active, Dormant, or Closed Out

Risk Assessment

Risks are assessed by the probability at which they occur and impact they will have on the project’s objective. The combination of these two is used to prioritize risks. This is identified as the “score” on the worksheet. There are 3 sections that make up the Risk Assessment:  Probability  Impact  Score

Risk Identification

Management & Monitoring Plan Response Strategy

Risk Assessment

Link to Risk Assessment Worksheet – click here

Risk Management Guide C-

Response Strategy

A response strategy identifies an actionable approach to mitigate the risk. There are four sections that make up the Response Strategy:

  1. Strategy – The approach the team will take to effectively reduce negative impacts or take advantage of opportunities: a. Avoid: Eliminate the uncertainty by removing its cause b. Mitigate: Reduce the uncertainty by reducing the probability or the impact. Make sure the costs/impacts of mitigating the risk do not outweigh the cost/impacts of accepting the risk. c. Transfer: Giving the impact and management of the risk to an external organization such as a local entity or contractor. d. Accept: Accept the uncertainty and the impacts associated with it. e. Enhance: Align the project in the best position to be able to take advantage of an opportunity.
  2. Action Plan – The steps an individual(s) will take, by when, to avoid, mitigate, transfer, or enhance the uncertainty (how, who and by when). These may require coordination with the Department’s partners such as FHWA, USACE, SHPO, etc. to adequately execute the strategy.
  3. Risk Owner – This individual is typically a team member whose area of expertise relates to a specific risk. They are responsible for implementing the action items, monitoring the progress, and updating the Project Manager and Project Team on the status of the risk.
  4. Follow-up Date – The date the Project Manager will check in with the Risk Owner to obtain a progress update on the action items. This value is related to the “update frequency” (Management & Monitoring). For example, if the follow-up date is April 3rd and the update frequency is monthly, then after discussions occur on April 3rd, the next follow-up date would be May 3rd.

Management & Monitoring Plan

There are two sections within the Management and Monitoring Plan:  Update Frequency  Update & Comments

The update frequency identifies how frequently the Risk Owner should provide an update to the Project Manager (e.g., weekly, bi-monthly, monthly, quarterly, annually). The frequency will depend on the risk and may change throughout the life of the project. This is directly connected to the “follow-up date” (in the Response Strategy section)

The updates and comments section is a place for the Project Manager and/or Risk Owner to track the progress and work that has been completed to mitigate, avoid, transfer or enhance the risk. If, for example, someone asks what work has been done to mitigate a risk, someone could go to this section to provide that information. Below is an example of the updates and comments that can be provided for a risk:

Risk Management Guide C-

Risk Update & Comments

If Median Emergency Access is not provided, project costs could increase to allow for outside access.

9/15/16 - Ongoing discussion between NCDOT Discipline Leads and the Project Team as to if this type of access is allowed. 10/10/16 - No updates at this time. 11/7/16 – Peter, Paul and Mary will set up a meeting to discuss if this access occurs in other corridors. 12/5/16 - Waiting for a response from NCDOT Discipline Leads. Project Manager will reach out to NCDOT Discipline lead this week. 1/9/17 – NCDOT Discipline Leads did not approve this access and provided a list of reasons. The traffic team will develop a response to try to keep this concept in or develop a modified concept that addresses their concerns. 2/6/17 – Project traffic team assembled a response to address NCDOT Discipline Leads concerns. 3/6/17 - Reached an agreement with NCDOT Discipline Leads to not have a median access through the retaining wall. Retaining walls do not need to be gapped to provide median access. Access will come from the outside and will require some additional real estate acquisition ~$20k.