A roofing construction and estimating exam with complete solutions. it covers various aspects of roofing, including material calculations, installation techniques for different roofing materials (asphalt shingles, wood shakes, epdm membranes, tiles), and safety standards. The questions delve into practical applications, requiring calculations and knowledge of specific building codes and industry best practices. This resource is valuable for students in construction management, architecture, or related fields.
Typology: Exams
1 / 6
This page cannot be seen from the preview
Don't miss anything!




A factory square asphalt-saturated felt underlayment contains _____ square feet. - ANSWER- A roofer is trying to estimate the amount of corrugated steel sheets needed for a 1, square foot roof with a 3" pitch. The specifications require the use of 27-1/2" wide sheets that are 10' in length installed with a two corrugation side lap and a 6" end lap. How many. sheets will be required to cover this roof? - ANSWER- A serrated wood shake pattern is created by: - ANSWER-offsetting shakes up or down 1" beginning with the second row A UL-rated asphalt shingle is most widely accepted for _____ standards. - ANSWER- fire resistance According to roofing construction and estimating, if. you need more than one piece of flashing over the length of a valley, lap the upper layer over the lower by at least _____ inches. - ANSWER- According to roofing construction and estimating, shingles on the upper end of an open valley should be installed to within _______ on each side of the centerline of the valley.
At what rate should mineral granules used as a surface aggregate be applied? - ANSWER-50 to 60 pounds per square Brush apply 1 gallon of approved lap cement per _______ when adhering 3" laps for an EPDM membrane system. - ANSWER-150 to 200 lineal feet Drip edge is installed at the eaves and rake to help shed water. Install drip edge _____ the felt at the eaves and ______ the felt at the rake. - ANSWER-under; over Dubbing shingles at an open valley directs water into the valley and not between the shingle courses, Shingles should be trimmed _______ from the upper corner at a 45 degree angle. - ANSWER-1" to 2" EDPM Sheets are available in what standard thicknesses? - ANSWER-.045 inch and .060inch EPDM membranes should be fastened to wood nailers at the roof perimeter, roof penetrations and at vertical abutments on ______ centers. - ANSWER-8" Flashing a chimney when installing roof tiles requires that the flashing extended _____ to each side of the chimney. - ANSWER-6" Flashing installed on a tile rood at a vertical wall over an unsealed underlayment should be installed continuous with a ______ water guard. - ANSWER-1" For back nailing the underlayment of a two-ply sealed system for tile roofing coverings use only tin tags or simplex nails spaced a minimum of _____ on center. - ANSWER- 12" How many shingles are required per square for four tab asphalt shingles 40"long and 13-1/4" wide? - ANSWER- If the horizontal width of chimney is greater than 24", installed a ______ above the chimney to help divert rainwater around the chimney. - ANSWER-wooden cricket Installation of job fabricated standing seams requires the use of cleats fastened to the deck. Cleats for terse metal planes are _______ wide and spaced on 12 inch centers. - ANSWER-2" Installing insolation over acoustical ceilings is accomplished with either R-11 or R- batts that are _____ in size. - ANSWER-24" X 48" Joints between prestressed concrete deck members should be sealed to prevent: - ANSWER-dripping of bitumen
The installation of shingles in a closed cut valley required the use of ____ fasteners at each end of the shingle when installed across the valley. - ANSWER-two The lapped portion of mechanically fastened EPDM systems should be secured under a termination bar set in sealant and mechanically fastened to the deck at ______ centers.
When installing concrete tiles at the ridge of an unsealed underlayment system, punch ______ weep. holes in the mortar beneath the ridge units. at every course. - ANSWER- 1/8" When installing drip edge, the installer should extend the drip the edge back over the roof deck no less than 3" and nail it on____ centers in high wind areas. - ANSWER-4" When installing gravel stops of roof slopes less than _____ prime both sides of the flashing. - ANSWER-1: When installing roof tiles on roofs with a slope of 7" in 12" or greater, the building code requires the installation of battens. When using the slotted batten system, _______ drain slots are placed _______ on center throughout the entire roof. - ANSWER-1/2";4' When installing strip shingles most manufacturers recommend that the starter course be installed with the: - ANSWER-factory applied adhesive strip When laid with a 3" lap, concrete tiles weigh approximately ______ pounds per square.