An overview of various scrum practices and the responsibilities of different scrum roles, such as the product owner, scrum master, and development team. It covers topics like product backlog management, sprint planning, sprint review, and the definition of done. How the product owner can communicate their marketplace knowledge to the scrum team, the characteristics of a 'ready' product backlog item, and the importance of the sprint goal. It also touches on the relationship between the product owner and the scrum master, as well as the order of scrum events. The document aims to provide a comprehensive understanding of scrum principles and their practical application.
Typology: Exams
1 / 12
This page cannot be seen from the preview
Don't miss anything!







W hen a product grows, it is quite possible that the PO will get help from other Product Managers and others in the organization who interact regarding the customer facing activities and knowledge of the product marketplace. Is it a good idea for the PO to proxy or outsource some of their PO Scrum Team duties to these people (for example, Scrum Team facing duties)? - No
It is a good practice to have at least two Product Owners on big projects. - False
Imagine the following situation. At the Sprint Retrospective meeting the Scrum Team identified some improvements that can be done. What should the Scrum Team do? Select the best option. - Make sure the Sprint Backlog for the next Sprint includes at least one high priority process improvement.
The Scrum Master should not allow the Product Owner to attend the Sprint Planning if the PO is not ready with a Sprint Goal. Is this true or false? - False
Product Backlog Refinement ... - Is an ongoing process,
Takes no more than 10% of the capacity of the Development Team
Is the act of adding detail, estimates, and order to Product Backlog items
Who is responsible for creation of the Definition of "Done"? - The Development Team
Who is responsible for crafting the Sprint Goal at the Sprint Planning? - The Scrum Team
What is the essence of Scrum? - A small team of people that is highly flexible and adaptive
How does the Product Owner communicate his marketplace knowledge to the Scrum Team (select three)? - Sprint Reviews
Product Backlog Refinement
Daily ad hoc interactions
Who is responsible for managing the Product Backlog? - The Product Owner
What are Product Backlog features? - It is dynamic
As long as a product exists, its Product Backlog also exists
It is never complete
Where Scrum can be used? - Managing the operation of an organization
Development of software and hardware
Development and sustaining of Cloud and other operational environments
Development of products and enhancements
Research and identifying of viable markets, technologies, and product capabilities
Development of almost everything we use in our daily lives as individuals and societies
What provides guidance to the Development Team on why it is building the Increment? - The Sprint Goal
All the Scrum Teams working on the same product should have the same Sprint length. - False
Ability to Innovate
Current Value
Select the two meetings in which people outside the Scrum Team are allowed to participate. - The Sprint Planning
The Sprint Review
What does Product Backlog management include? - Optimizing the value of the work the Development Team performs
Ordering the items in the Product Backlog to best achieve goals and missions
Ensuring that the Product Backlog is visible, transparent, and clear to all, and shows what the Scrum Team will work on next
The Scrum Team consists of - The Product Owner
The Development Team
The Scrum Master
What happens when a Sprint is cancelled? - If part of the work is potentially releasable, the Product Owner typically accepts it
Any completed and "Done" Product Backlog items are reviewed
All incomplete Product Backlog Items are re-estimated and put back on the Product Backlog
What factors should be considered by the Product Owner in the release decision (select four)? - Can customers actually absorb the new release?
The costs and benefits of the upgrade
The risk that the product's value can get out of line with the marketplace
The customers that will be constrained by the new release
Who identifies the Key Stakeholders for the Product? - The Product Owner
The Product Owner should be expertly aware of the marketplace for the product. - True
If multiple Stakeholders have varied interests in the product and different viewpoints what is the best strategy for the Product Owner? - Do an intelligent balancing of interests and try to maximize the value of the Product as a whole
How can the Product Owner bring his product vision to life (select 3)? - Utilizing the underlying empirical product planning features of Scrum
Articulating the product vision to the Scrum Team and the Key Stakeholders early and often
Via the Product Backlog and iterating towards that vision every Sprint
What are the characteristics of a Product Backlog Item that is "Ready" for selection in a Sprint Planning? Select three. - Well refined
How does Definition of "Done" help to the Scrum Team? - DoD is used to assess when work is complete on the product Increment
Guides the Development Team in knowing how many Product Backlog items it can select during a Sprint Planning
DoD ensures artifact transparency
How long does the Product Backlog exists? - While the Product exists
Who is the leader in terms of getting feedback from the Key Stakeholders in the Sprint Review? - The Product Owner
How does the Scrum Master help the Product Owner? - Understanding product planning in an empirical environment
Facilitating Scrum events as requested or needed
Finding techniques for effective Product Backlog management
Every Product Backlog Item should be created by the Product Owner personally and only then the Development Team can add details to it at the PO's discretion. - False
Who decides whether to release the latest increment of the product? - The Product Owner
All Development Teams working on the same Product should use the same Product Backlog. - True
A Development Team is waiting for a specific software component that they need to integrate and use.
The component should be ready in two months.
The Backlog Items with highest priorities depend on this specific component.
What should the Product Owner do? - Re-order the Product Backlog to maximize utilization of the Development Team and deliver at least some Increment of product functionality in the next Sprint
Sort Scrum events in the right order. - Sprint Planning
Daily Scrum
Sprint Review
Sprint Retrospective
Select the two focus areas that are not considered in executing Value Driven Development by the Product Owner. - Coach of the Development Team in self-organization and cross-functionality
Remover of impediments to the Development Team's progress
What are the Scrum Artifacts? - Sprint Backlog
Increment
Product Backlog
Please, select a time-box for each Scrum event. - Sprint Review
4 hours or less
Daily Scrum
Who is responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal? - The Development Team
Who is responsible for all estimates in the Product Backlog? - The Development Team
Who should do the legwork of gathering the marketplace data for the Product Owner? - It does not matter who does the legwork
How frequently product releases should occur? - Frequently enough to eliminate the risk that the product's value will get out of line with the marketplace
Who are the typical Key Stakeholders (select three)? - The people responsible for making the funding decisions for the product development effort
The people responsible for paying to use the product
The human people who actually use the product under development
What is the Sprint Backlog? - The Product Backlog items selected for this Sprint plus the plan for delivering them
The Development Team should be able to explain to the Product Owner and Scrum Master how it intends to work as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment. - True
What technique should be used for representing Product Backlog Items? - Any technique, even a mix of several techniques
Technical debt ... - is a real risk which can genuinely be incurred
reflects some extra development work
compromises long-term quality of the Product
The Sprint Review is just a demo of the Product Backlog items completed during a Sprint. Do you agree? - No, the Sprint Review contains much more activities
The Sprint Backlog is created at the Sprint Planning. It is prohibited to add new work into the Sprint Backlog later by the Development Team. - False
Once the Product Owner gained his Product Vision and defined the tactics of bringing this vision to life, it is a bad idea to change them before the next Product Release - False
Who is responsible for the Product Backlog? - The Product Owner
How frequently the Product Owner should communicate and re-iterate his product vision to the Scrum Team and the Key Stakeholders? - Early and often
In which meetings the Key Stakeholders are allowed to participate? - The Sprint Review
What does Cone of Uncertainty show? - How much is known about the Product over time
What is the Increment? - The sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints
If an item in the Sprint Backlog cannot be finished by the end of the Sprint (it turned out there is a lot more work to do than was estimated), the Sprint is cancelled. - False