Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Community
Ask the community for help and clear up your study doubts
Discover the best universities in your country according to Docsity users
Free resources
Download our free guides on studying techniques, anxiety management strategies, and thesis advice from Docsity tutors
Technical Assignment 1 summarizes the existing conditions and construction management methods utilized on The Salamander Resort and Spa.
Typology: Summaries
1 / 22
Technical Assignment 1 summarizes the existing conditions and construction management methods utilized on The Salamander Resort and Spa. This report is broken up into eight sections, each of which is briefly described below. This report includes an analysis of the local conditions of the site and some issues that are prevalent to the contractor. The next section gives some background information on the owner of the project. The owner is very involved and focused on the resulting quality of the building. The building systems overview outlines the types of systems present and issues surrounding the construction. Two different project cost estimates were performed, a parametric and a square foot. These two estimates vary significantly with the actual project cost but the differences are justified in the analysis. A summary schedule highlights the major activities and milestones through the life of the project. The existing site conditions plan outlines the building footprint, utilities, and pedestrian/vehicular traffic flow. Finally, a project delivery organizational plan and on‐site staffing plan is included. These help to familiarize you with the people and companies involved. The Salamander Resort and Spa, owned by Salamander Hospitality, is being constructed as a luxury high end resort. Located less than 40 miles from Washington D.C., they hope to bring in guests looking for a weekend vacation. The main building is one story above grade with an attached four story guest house that lodges all the rooms. The joined basement houses all the service rooms and mechanical spaces. The project duration is four years and will cost approximately $93 million. The building exterior is a combination of stone veneer and stucco. Turner Construction is contracted with the owner through a cost plus fee and GMP. Turner holds lump sum contracts with all subcontractors while the owner hold contracts with all the architects, engineers, and consultants. The Salamander Resort is looking to become the first Resort of its kind to be LEED Certified.
Figure (1) Figure (2) The project is located in the town of Middleburg, Virginia on route 50, about 40 miles west of Washington D.C. and 120 miles north of Richmond (Figure 1). Figure (2) shows the site boundary in blue and the resort location in red. Preferred Methods of Construction: Much of the residential properties in old town Middleburg are masonry and brick construction. To match this look, Salamander Resort uses a stone façade on the main entrance area. Construction Recycling: All recycling is collected on site and removed by a third party company to a local recycling plant. Tipping Fee: In 2008, the tipping fee in Loudon County is $60/ton. (Loundon County Solid Waste Management Planning District) Soil Type: The regional soil consists of a blend of deep, well drained, silty soils and clays. During footing excavation, the subsurface water level was not reached.
Salamander Hospitality is a company formed in 2005 in part by the current CEO Sheila Johnson. Her goal is to grow the company by acquiring one of a kind properties and managing them to provide an unforgettable experience. Salamander Hospitality specializes in the management of luxury resorts and hotels, like the Salamander Resort and Spa. Their focus on owner and customer satisfaction is what drives this company. Salamander Hospitality also owns and manages the Innisbrook Resort and Golf Club in Florida and the Woodlands Inn in South Carolina. Both of these properties reflect the mission that Salamander Hospitality set out to achieve. Owner Expectations: Cost: Most of the funding for this project comes directly from Salamander Hospitality. The high‐end nature of this project can lead to changes in interior and exterior finishes throughout the project and it is one of the goals of the contractor to minimize the cost impact of these. Quality: The owner is looking for a very high quality finished product that will serve the needs of her client base. Only the finest fixtures, furniture, and wood details are used. This requires the contractor to provide special attention to the installation process in order to ensure the best looking product. Schedule: The owner had initially set a Spring 2010 completion date but has since pushed that back to Spring 2011. This has provided the contractor with significant float time, and allows for easier trade coordination. Safety: It is critical that the contractor provide a safe environment for all the workers on site.
Yes No Work Scope Issues X (^) Demolition required? X Structural steel frame Mobile crane for erection X Cast in place concrete Crane and bucket placement. Wood formwork X Precast concrete X Mechanical system Mechanical room located in basement of main building, northeast corner. Dry sprinkler system X Electrical system Main 3200A 480/277 ‐ 3 phase 4W and secondary120/208V ‐ 3 phase 4W X Masonry Stone veneer on main building at entrance X Curtain wall X Support of excavation Building Systems Summary Excavation: All foundations should be a minimum of 36” below grade Building spread and strip footings shall bear on undisturbed natural soils or compacted fill with a bearing pressure of 3500 psf. Utility lines shall not be placed through of below foundations without structural engineer’s approval Concrete: A 3000 psi reinforced concrete was used for 5” interior slab on grade The guest house utilized 9” and 10” 3500 psi post tensioned reinforced concrete on metal deck with continuous welded wire fabric. Typical 16x28 reinforced concrete columns utilized in guest house. Structural Steel: Rolled shapes and Round HSS Shapes – ASTM A992, ASTM A 2” 18 gage Lok‐Floor composite metal decking used in the guest house 1 ½” deep, wide rib, 20 gage galvanized roof decking used for both the guest house and main building Lightgage steel roof trusses with 8” lightgage purlin at 48” on center
Mechanical System: 15 main AHU’s, 9 Variable Frequency Drive (VFD) and 6 Constant Volume (CV) 6 heat recovery AHU’s. 3 located in the main lodge, 2 in the spa, and 1 in the laundry room 1950 gpm cooling tower located on the main roof serves chillers 1 ‐ 3 Mechanical room located in basement in north east corner Electrical System: From utility, main 3200A 480/277V ‐ 3 phase 4W switchboard with secondary 120/208V 3 phase Uninterrupted Power Supply (UPS) for 4 th floor guest house and 1 st floor main building Indoor emergency diesel generator (650kW 480/277V – 3 phase 4W) Custom designed light fixtures and chandeliers LEED Design Features: “Green” slate roofing made from recycled rubber and PVC piping Minimize irrigation by using native plants and species Maximize opportunity to use building materials made from recycled products Use low emitting paints, carpets, and window treatments Protection procedures in place to conserve 250 of the 340 acres
Construction Cost $ 93,802,046. Construction Cost/SF $ 409. Total Project Cost Estimate $ 135,280,000. Total Project Cost Estimate/SF $ 590. Actual Costs Building System Cost Cost/SF Excavation and Fill $ 277,443 $ 1. Building Concrete $ 7,191,105 $ 31. Structural Steel and Metal Deck $ 2,023,292 $ 8. Plumbing $ 13,766,120 $ 60. Electric $ 10,674,385 $ 46. Finish Carpentry & Architectural Millwork $ 4,120,000 $ 17. Windows, Doors, and Glazing $ 1,285,355 $ 5. Gypsum Drywall Work $ 5,911,608 $ 25. General Requirements $ 1,893,275 $ 8. Building Systems Costs (Cost and Cost/SF) The Total Project Cost Estimate includes land, design/consultant fees, furniture, fixtures, equipment, and development/marketing in addition to construction costs. The Turner Construction Project Manager on site estimated all these additional costs because the owner did not release the official data. As seen in the chart, the most expensive systems in the building are the plumbing and electric.
See Appendix A for the detailed D4Cost Estimate The D4Cost estimate was calculated by selecting two similar projects in the database and combining their attributes into one estimate. The closest projects that D4 had in the database were motel/hotels. I chose The Hampton Inn and Suites Hotel because it is a high end hotel located in Chicago. The Inn on Lake Superior is more similar because of the amenities offered but does not come close to the luxury that the Salamander Resort offers. Use Project Name Size (SF) Floors Building Cost Hotel/Motel Hampton Inn and Suites Hotel 162,000 12 $ 13,797, Hotel/Motel The Inn on Lake Superior 65,345 3 $ 4,073, Projects Used in D4 Cost Estimate Division Name Percent Sq. Cost Amount 0 Bidding Requirements 7.22 $ 9.60 $ 2,200, 1 General Requirements 3.75 $ 4.99 $ 1,144, 2 Site Work 4.08 $ 5.42 $ 1,242, 3 Concrete 21.00 $ 27.92 $ 6,400, 4 Masonry 6.09 $ 8.09 $ 1,855, 5 Metals 1.56 $ 2.07 $ 475, 6 Wood & Plastics 4.78 $ 6.36 $ 1,457, 7 Thermal & Moisture Protection 1.91 $ 2.54 $ 581, 8 Doors & Windows 6.39 $ 8.50 $ 1,947, 9 Finishes 11.38 $ 15.13 $ 3,467, 10 Specialties 0.35 $ 0.47 $ 107, 11 Equipment 0.09 $ 0.12 $ 26, 12 Furnishings 0.05 $ 0.06 $ 13, 13 Special Construction 0.68 $ 0.90 $ 206, 14 Conveying Systems 2.49 $ 3.31 $ 758, 15 Mechanical 19.61 $ 26.08 $ 5,978, 16 Electrical 8.60 $ 11.43 $ 2,620, Total Building Costs 100.00 $ 132.99 $ 30,483, Parametric D4Cost Estimate
The D4Cost estimate reported at $132.99/SF with a total project cost of $30,483,633. This value is approximately one third of the actual project cost. This significant difference is due in part to the use of the building. The D4 projects are mainly hotel oriented while the Salamander project is a full resort with spa, restaurant, guest rooms, and horse stables/pastures. The Hampton Inn utilizes precast concrete, whereas The Salamander Resort does not. If the three projects had more similar structural, mechanical, and electrical systems the estimate would be closer. The amount of custom interior work, lighting fixtures and woodwork, found on this project also contributes to the difference.
See Appendix B for the reference pages from R.S. Means 2009 The following R.S. Means square foot estimate is based off M.350: 4 ‐ 7 Story Hotel with Face Brick and Concrete Back‐Up. The costs are calculated using an area of 229,213 square feet and 2,828’ perimeter. Basement addition along with height, perimeter, and location adjustments were used. A majority of the structural framing is done with reinforced concrete. S.F. Area 195, L.F. Area 850 Steel Frame $159. R/Conc. Frame $157. Face Brick with Concrete Block Back‐up Exterior Wall Story Height Adjustment: 12’ – 10’3” = 1.75’ ‐$1.25/ft * (1.75) = ‐$2.19/sq. ft. Perimeter Adjustment: 2828’ – 850’ = 1978’ +$1.75/100 ft * (1978’) = +$34. Basement Addition: +$32.20/sq ft Sub‐Total Per Square Foot Estimate: 157.60 + 2.19 + 34.62 + 32.20 = $226.61/sq ft. Project Location Adjustment Arlington, Virginia is the closest location listed in RS Means. $226.61 * 0.93 = $210.75/sq ft. Sub‐Total Construction Cost $210.75/sq ft. * (229,213 sq ft.) = $48,306,
Common Additives: (5) 5000 lb. capacity elevators @ $170,700 each +$853, (1) Security camera and monitor @ $1850 and (37) additional cameras @ $1000 each +$38, (4) 125 lb. washers @ $32,800 each +$131, (1) 50 lb. washer @ $12,200 each +$12, (2) Laundry folders @ $66,500 each +$133, (1) Laundry ironer @ $35,500 each +$35, Common Additives Total = +$1,204, Total Construction Cost: $48,306,640 + $1,204,250 = $49,510, $216.00/SF The R.S. Means square foot estimate is about $45 million less than the actual project cost. Part of this difference can be attributed to using a hotel as the basis for the estimate, as R.S. Means does not have a category for resorts. Another reason for the difference comes in the façade, R.S. Means uses Face Brick with Concrete Clock Back‐Up while The Salamander Resort uses a stone veneer and stucco. Other discrepancies were discussed in the analysis of the D4Cost estimate. The R.S. Means estimate for this project is more accurate than the D4Cost estimate partly because the Means estimate is more tailored to this project, while the D4 Cost is based off other buildings. While neither estimate had a good basis for comparison, the R.S. Means estimate is would be fairly accurate if it included more of the specialty items and finishes found in The Salamander Resort.
See Appendix C for the Project Schedule Summary Turner Construction was awarded the construction contract from Salamander Hospitality to construct The Salamander Resort and Spa. The project was originally planned to be completed in March 2010, but was pushed back one year per the owner’s request. This allowed Turner to spread out the trades and even put several on hold. For example, all interior framing was completed by January 2009 but drywall and rough‐ins were put on hold for 11 months to accommodate the new schedule. It also leads to less congestion on site due to fewer trades having to work simultaneously. Foundation The total duration of the foundation work was approximately 6 months. The foundation consisted of reinforced concrete spread footings excavated down to a minimum of 36 inches below the slab on grade. No formwork was needed because the excavation holes were dug to the correct footing size. Structural Superstructure for The Salamander Resort and Spa took about 6 months to complete. It consisted of both concrete and steel framing. The basement and guest wing have concrete framing throughout and the main building has steel framing on the first floor. This created challenges in the schedule when both concrete and^ steel^ were^ being^ installed^ simultaneously. Finishes Turner has allocated a large amount of time to the finishes due to the complexities of the project. A majority of the fixtures are custom designed for this project and are more likely to require additional time to install. Like many of the activities, finishes would be able to finish in less time than the allotted if the schedule was optimized for time.
The project delivery method used is a design build. A design build method was chosen because a large portion of the lighting system and custom interior work was not designed at bid time. When Turner took over the project in 2007 it had already undergone three complete redesigns under a different general contractor. The owner initially wanted to fast‐track the process to make up for lost ground but this was later altered to fit their needs more accurately. The Owner, Salamander Hospitality, holds direct contracts with all the design architects, engineers, consultants. The contract between the Owner and Turner Construction is a Cost Plus Fee with a Guaranteed Maximum Price (GMP). Turner Construction holds lump sum contracts with all the subcontractors. The contractor was selected through a competitive process based upon qualification, fee, and a general conditions proposal. Turner Construction uses a Contractor Controlled Insurance Program (CCIP) which includes workers compensation and general liability. The Owner separately purchased Builders Risk Insurance. There is no Performance Bond on this project. See the following page for the project delivery system organizational chart.
Lump Sum Development Manager Mark G. Anderson Consultants Landscape Architect Oculus Civil Engineer PHR+A Structural Engineer Rathgeber/Goss Associates Architect Architecture Inc. MEP Engineer RG Vanderweil Engineers Life Safety Consultant Rolf Jensen and Associates Design Architect Winberly Allison Tong and Goo Interior Designer Forrest Perkins Food Service Consultants CINI, Little Spa Consultant Blue Spas General Contractor Turner Construction Owner Salamander Hospitality Cost plus Fee and GMP Electrical Contractor HVAC Contractor Concrete Contractor Other Contractors Excavating Contractor
Turner Construction has eight people working on site, one project manager, three superintendents, and four engineers. There are more people on this site than usual because of the complexity of the systems and installation. The Project Engineer and Assistant Engineer are responsible for RFI’s and submittals on a daily basis. The Superintendents are responsible for work flow, schedule changes, and subcontractors. Below is the Turner Construction on‐site staff. Project Manager Mark Miller Project Superintendent Roger Shepard Asst. Superintendent 2 Asst. Superintendent 1 Chris Kayton Project Engineer There Swanson Asst. Engineer Tamika McCory MEP Engineer Andy Yohe Asst. Engineer Pragnya Kappagantula
2009
2009