Docsity
Docsity

Prepara i tuoi esami
Prepara i tuoi esami

Studia grazie alle numerose risorse presenti su Docsity


Ottieni i punti per scaricare
Ottieni i punti per scaricare

Guadagna punti aiutando altri studenti oppure acquistali con un piano Premium


Guide e consigli
Guide e consigli


esercizi production processes, Esercizi di Ingegneria dei Processi di Produzione Industriale

esercizi di production processes

Tipologia: Esercizi

2019/2020

Caricato il 08/09/2020

adriana-di-carlo
adriana-di-carlo 🇮🇹

1 documento

1 / 8

Toggle sidebar

Questa pagina non è visibile nell’anteprima

Non perderti parti importanti!

bg1
Bottino Exercises
First Lesson
1) A toy shop sells fluffy bears at a very regular d=10 pcs/day (considering 310 days in a year). The
shop pays for each bear Cu=5€ pcs/day. The inventory holding cost is h=20% of the unitary
purchasing cost.
-Evaluate the lot size Q which guarantee the planning of 20 order per year in these conditions;
-If the shop orders 100 units size lot (considering EOQ), what is teh total order fixed cost due to
order plans.
-If A=10€ per order evaluate the EOQ
Exercise Done
Data:
d=10 pcs/day
working days= 310 days/year
Cu=5€ pcs/day
h%=20% Cu/year
-So
h=0,25
(pcsyear)∗( year
(310 days))= 0,0032
(pcsday)
Manual Orders=
D
Q=
(d daily 310 days
year )
Q
, daily demand per working day
2D orders /year=(10 pcs /day310 days/year )
Q
???
So we have Q=155 pcs/order
-Q'=100, which is EOQ. (Q'=Q*)
A=total order fixed cost
Q'=
2AD
h
so
A=(Q'2h)
(2D)=1002pcs20,25/(pcsyear )
(231010 pcs/year )=10000pcs 20,0032/(pcsyear)
(20 pcs/year )=1,61
So the number of annual orders is
(n ° annual)
order =D
(Q ' )=(10 pcs/day310 days/year)
(100 pcs/order)=31 orders/year
So
A annual=31 order /year1,61 /order=50 /year
-If A=10€, we have
Q'=
(2Ad
h)=
((210 10 pcs/day )
(0.0032 /pcsday))=249 pcs
So in this case we prefer a low A (1,61), so less orders (100)
pf3
pf4
pf5
pf8

Anteprima parziale del testo

Scarica esercizi production processes e più Esercizi in PDF di Ingegneria dei Processi di Produzione Industriale solo su Docsity!

Bottino Exercises First Lesson

  1. A toy shop sells fluffy bears at a very regular d=10 pcs/day (considering 310 days in a year). The shop pays for each bear Cu=5€ pcs/day. The inventory holding cost is h=20% of the unitary purchasing cost. -Evaluate the lot size Q which guarantee the planning of 20 order per year in these conditions; -If the shop orders 100 units size lot (considering EOQ), what is teh total order fixed cost due to order plans. -If A=10€ per order evaluate the EOQ Exercise Done Data: d=10 pcs/day working days= 310 days/year Cu=5€ pcs/day h%=20% Cu/year -So h =

( pcsyear )

year ( 310 days )

( pcsday ) Manual Orders=

D

Q

( d daily 310 days year

Q

, daily demand per working day 2 D orders / year = ( 10 pcs / day ∗ 310 days / year ) Q

So we have Q=155 pcs/order -Q'=100, which is EOQ. (Q'=Q*) A=total order fixed cost Q' =

AD

h so A =

( Q'

2 ∗ h ) ( 2 D )

2 ∗ pcs 2 ∗0,2∗ 5 ∗ /( pcsyear ) ( 2 ∗ 310 ∗ 10 pcs / year )

10000 ∗ pcs 2 ∗0,0032∗ /( pcsyear ) ( 20 pcs / year )

So the number of annual orders is ( n ° annual ) order

D

( Q ' )

( 10 pcs / day ∗ 310 days / year ) ( 100 pcs / order ) = 31 orders / year So A annual = 31 order / year ∗1,61 / order = 50 / year -If A=10€, we have Q' =

Ad h

( 2 ∗ 10 ∗ 10 pcs / day ) (0.0032 / pcsday ) )= 249 pcs So in this case we prefer a low A (1,61), so less orders (100)

2)Product A demands rate D= 416 pcs/year. The unitary purchase cost is 20 €/pcs, each order displacement cost(A) = 150€. The unitary annual storage (h) is 350 € per product per year. -Evaluate the Economic Order Quantity -If a discount of 15% is applied whenever the order exceed the 30 units, how does the EOQ change? -What is the EOQ if we consider a bounded speed of filling of P=60 pcs/month? Data: D= 416 pcs/year Cu= 20 €/pcs A=150€/order h=350 €/pcs year -So we have Q' =

AD

h

( 2 ∗ 150 / order ∗ 416 pcs / day ) ( 350 / pcsday ) )=18,9 pcs -Cu' = Cu(1-15%) if Q>30, so Cu' = Cu(1-0,15)*20=17€/pcs To evaluate discount we need to evaluate the cost, so

C 1,2 ( Q' )=√( 2 ADh )=√( 2 ∗ 150 € ∗ 416 pcs / year ∗ 350 € /( pcs ∗ year ))= 6609 € / year

[This formula for C can be used only for Q' ] But C1,2 is not the total cost, we are missing C 3. So C 3 ( Q ' )= CuD = 20 / pcs ∗ 416 pcs / year = 8320 / year and Ctot = 6609 + 8320 = 14929 €/year If Q>30 pcs, then C 1,2 ( Q = 30 )=

AD

Q

hQ 2

( 150 ∗ 416 pcs / year ) ( 30 pcs )

( 350 /( pcs year )∗ 30 pcs ) 2 = 7330 / year C 3 ( Q = 30 )= Cu ' D = 17 / pcs ∗ 416 pcs / year = 7072 / year So Ctot = 7330 + 7072 = 14402 €/year So Q=30 is preferable to Q', we have a lower cost--> EOQ= 30 Now P= 30 pcs/month = 30 pcs/month * 12 month/year = 720 pcs/year > 416 pcs/year [being P>D, has sense to continue the exercise] Q' ' =

AD

( h ( 1 −

D

P

( 2 ∗ 150 / order ∗ 416 pcs / day ) ( 350 / pcsday ∗( 1 − ( 416 pcs / year ) ( 720 pcs / year )

)=29,06 pcs with P= 720 before Q' = 18,9 pcs wish P= ∞

Second lesson

  1. An intersection press is used to produce three different products A, B and C in thermoplastic resin. A total production of 600 pcs must be produced with this mix: qA=40% qB=35% qC=25% For each typology of product the standard operation time SOT is assumed to be constant and equal to 4,5 minutes. The machines set-up time is 3 times the SOT. The AWT is 55 hours. -Verify the feasibility of a single lot production (for each product) -Evaluate the smallest sustainable lot size for each product (it's obviously assumed repetitive lot production approach ). DATA SOT= 4,5 minutes/pcs set-up time= 13,5 minutes QPtot = 600 pcs N= UST = ( setup time ) SOT = 3 pcs HVP = ( 60 mm / hours ) SOT =13,33 pcs / hours a)

SOT

∗( QPtot + NUST )⩽ AWT So

∗( 600 + 3 ∗ 3 )⩽ 55 which is^ 45,67⩽^55 OK b) being x=QPtot y =

N ∗ UST

HVP ∗ AWT

x

=40,5≃ 41 ⇒ LTPmin LAmin = qALTPmin =0,4∗40,54=16,2 pcs = 17 pcs LBmin = qBLTPmin =0,35∗40,54=14,2 pcs = 15 pcs LCmin = qCLTPmin =0,25∗40,54=10,1 pcs = 11 pcsLnmin =^17 +^15 +^11 =^43 pcs LTN = QPtotLnmin

2 nd^ verification LTNSOT 60 ∗(∑ Lnmin + NUST )⩽ AWT So

∗( 43 + 3 ∗ 3 )⩽ 55 which is 54,6⩽ 55 Total units are LTN ∗∑ Lnmin =^14 ∗^43 =^602 pcs

  1. Once produced, circuits are packed by a special machine. The time needed for packing operation is 8mm. Following quantities, m 2008, are required to be packed: -100 type A -40 type B -180 type C -80 type D Every time the production changes the machine needs a set-up time equal to 16mm, AWT is between 65 and 70 hours. The packing has to be done in order to have repetitive lots of the smallest sustainable lot size. -Find the lot size -Evaluate the average time needed to pack the single integrated circuit considering the time loss due to the set-up. Calculate also the number of set-ups realized. -Repeat the previous point doubling the repetitive lot size. DATA N= UST = ( setup time ) SOT

= 2 pcs SOT 60 ∗( QPtot + NUST )⩽ AWT so^

∗( 400 + 4 ∗ 2 )⩽ 65 / 70 which is^ 54,4⩽^65 /^70 We have then qA =

qB =

qC =

qD =

AWT= 65/70 hours, we consider 65 because the 5 extra hours costs, so LTPmin =

N ∗ UST

HVP ∗ AWT

QPtot

LAmin = qALTPmin =0,25∗36,6=9,1 pcs = 10 pcs LBmin = qBLTPmin =0,1∗36,6=3,6 pcs = 4 pcs LCmin = qCLTPmin =0,45∗36,6=16,46 pcs = 17 pcs LDmin = qDLTPmin =0,2∗36,6=7,3 pcs = 8 pcsLnmin =^10 +^4 +^17 +^8 =^39 pcs LTN = QPtotLnmin

2 nd^ verification LTNSOT 60 ∗(∑ Lnmin + NUST )⩽ AWT

Third Lesson

  1. A company produces bookshelves. The production of each bookshelf requires the following production stages: -Shelves machining: the average time needed is 2 weeks per lot, we need two shelves for bookshelf. -Bookshelf frame production, which average lead time is 1 week, 1 frame needed for each bookshelf. -Assembly and packing LT=1 week. Build a proper MRP from these data t 1 2 3 4 5 6 7 8 MPS - - 40 20 - 70 10 60 Item master file \ OH 0 LT SR Lot sizing rule A 10 1 / L4L B 0 1 10(1), 20(7) FOP= 2 time buckets C 100 2 10(2) FOQ= 60*n Exercise Done Notes: -If I can postpone a SR, then I have to note it with a * and sign it on the last table -FOP the time I must consider for the OR order, (here 2, so 1 “time” is empty) -FOQ says the multiples of “items” I can put in OR -LT is the time I need to receive my “items”, so I have to anticipate A 1 2 3 4 5 6 7 8 GR 40 20 70 10 60 SR OH with OH 0 =

NR 30 20 70 10 60

OP 30 20 70 10 60

OR 30 20 70 10 60

B 1 2 3 4 5 6 7 8

GR 30 20 70 10 60

SR 10* 20

OHwith OH 0 =

NR 20 20 70 10 40

OP 40 80 40

OR 40 80 40

C 1 2 3 4 5 6 7 8

GR 60 40 140 20 120

SR 20*

OHwith OH 0 =

NR 120 60 120

OP 120 60 120

OR 120 60 120

Code Quantity (Qty) Period Remarks A 30 2 OR 20 3 OR 70 5 OR 10 6 OR 60 7 OR B 40 1 OR 80 4 OR 40 6 OR 10 1-->3 SR defer 20 7 SR OK C 120 3 OR 60 4 OR 120 5 OR 20 2-->5 SR defer