2365-614 (Unit 304) - INSPECTION, TESTING AND INITIAL VERIFICATION
What is a statutory document? - LEGAL - H&S at Work Act, EAWR
What is a non statutory document? - Not Legal - BS7671, On-Site Guide, Guidance Note 3,
GS 38
What equipment is used for safe isolation? - 1) approved Voltage indicator
2) proving unit
3) lock and key device
4) warning notices
5) relevant PPE
Process of Safe Isolation? - 1) identify means of isolation - determine what is to be worked
on
2) obtain permission to isolate
3) switch off
4) lock off
5) secure key - keep on person
6) select approved voltage indicator
7) test voltage indicator on known source (proving unit)
8) test between all conductors (3 test for single phase, 10 tests for 3 phase)
9) re-test voltage indicator
Explain all supply systems - TN-S:
Cable sheath earth (usually 2 core SWA). Zs path is via the cable sheathing. Max Ze = 0.8
ohm
TN-C-S:
pf2

Partial preview of the text

Download 2365-614 (Unit 304) - INSPECTION, TESTING AND INITIAL VERIFICATION and more Exams Advanced Education in PDF only on Docsity!

2365-614 (Unit 304) - INSPECTION, TESTING AND INITIAL VERIFICATION What is a statutory document? - LEGAL - H&S at Work Act, EAWR What is a non statutory document? - Not Legal - BS7671, On-Site Guide, Guidance Note 3, GS 38 What equipment is used for safe isolation? - 1) approved Voltage indicator

  1. proving unit
  2. lock and key device
  3. warning notices
  4. relevant PPE Process of Safe Isolation? - 1) identify means of isolation - determine what is to be worked on
  5. obtain permission to isolate
  6. switch off
  7. lock off
  8. secure key - keep on person
  9. select approved voltage indicator
  10. test voltage indicator on known source (proving unit)
  11. test between all conductors (3 test for single phase, 10 tests for 3 phase)
  12. re-test voltage indicator Explain all supply systems - TN-S: Cable sheath earth (usually 2 core SWA). Zs path is via the cable sheathing. Max Ze = 0. ohm TN-C-S: