Appendix B: Work Breakdown Structure (WBS). B.1. Introduction. The WBS and WBS dictionary are effective management processes for planning, ...
Typology: Study notes
1 / 9
This page cannot be seen from the preview
Don't miss anything!






Appendix B
The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with NASA directives NPR 7120.5E (“NASA Space Flight Program and Project Management Requirements”), NPR 7120.7 (“NASA Information Technology and Institutional Infrastructure Program and Project Requirements”’), and NPR 7120. (“NASA Research and Technology Program and Project Management Requirements”), the WBS and WBS Dictionary are mandatory elements of a project’s management baseline. The goal is to develop a WBS that defines the logical relationship among all program elements to a specified level. The WBS integrates technical, cost, and schedule parameters, giving the Project or Program Manager (PM) a tool to forecast cost and schedule performance, among other management objectives.
With respect to the NASA cost estimator, a project’s WBS will significantly affect two areas: the development of the Cost Breakdown Structure (CBS) and the generation of the required inputs into the Cost Analysis Data Requirement (CADRe) database. The development of a WBS with those requirements considered in the early stages will save significant “mapping” and reconciliation efforts for the cost estimator at a later stage. Accordingly, these items are the focus of this appendix. For complete WBS development guidance that includes the WBS as a basis for assigned project responsibilities, provides project schedule development, simplifies a project by dividing the total work scope into manageable units, and provides a common reference for all project communication, refer to NASA’s WBS Handbook,^1 which follows the guidelines found in NPR 7120.5E^2.
A Product-Oriented WBS, which is what is commonly meant by “WBS,” is a hierarchical organization of all of the hardware, software, services, and other deliverables necessary to successfully complete a space flight project.^3 The purpose of the WBS is to allocate the work content into manageable segments to enable the planning and control of cost, schedule, and technical content. The typical space flight system WBS is product oriented. The product-oriented WBS begins with the end product at the highest level (such as spacecraft) and subdivides the work content into lower-level elements until sufficient detail is achieved for management (or cost estimating) purposes. A WBS relates the elements of work to one another and to the end product. The WBS is the foundation that relates all project disciplines to a common framework that supports the planning, monitoring, and control of progress and status of engineering efforts, cost and schedule resources, and technical progress and performance.
(^1) NASA Work Breakdown Structure Handbook, SP-2010-3404, http://evm.nasa.gov/handbooks.html. (^2) NASA NPR 7120.5E, NASA Space Flight Program and Project Management Requirements, w/ Changes 1–10, http://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7120_005E&page_name=AppendixB&search_term=7120%2E5E_. (^3) References to WBSes of varying types may be confusing. For the purposes of this document, and due to common usage, a WBS refers to a Product-Oriented Work Breakdown Structure, an FBS refers to a Functional Work Breakdown Structure, and an OBS refers to an Organizational Work Breakdown Structure.
Appendix B
One of the first tasks that must be performed by the cost estimator when developing a new cost estimate is to either obtain or develop the WBS (step 2 in NASA’s 12 step cost estimating process). The WBS is critical because it is the primary source for development of a CBS. If composed with cost information, a WBS may serve directly as a CBS. Otherwise, it may be loaded with cost information attributed to its respective elements to create the CBS. If the project has advanced into Phase B, the Project Manager should be able to provide a WBS. If, however, the project is in the early concept study phase (including Analysis of Alternatives [AOA]), the cost estimator may need to develop a WBS.
When the project or study lead provides the WBS, the cost estimator needs to determine if the WBS addresses the total scope of work and is suitable for cost estimating. Depending on the specific cost models or estimating approaches the analyst has chosen, the project WBS may not have sufficient granularity, or misalignment may exist between the WBS and the estimating methods. Any adjustments that are made to the project WBS must be coordinated with the project or study lead to ensure that the changes will not cause issues with understanding or communicating the estimate. If adjustments to the WBS are not feasible, it is the responsibility of the analyst to make whatever
CADRe WBS
The NASA Standard WBS required by NPR 7120.5E only proceeds to level 2. This increases the degrees of freedom for the Program/Project Manager to construct a WBS that best facilitates project accomplishment. However, the cost estimator and project lead must be aware that there are managerial data demands that must map from the project’s WBS. Construction of a WBS that considers these requirements may alleviate significant PM level of effort at stages of the project beyond initial WBS formulation. For each Agency project, the WBS established by the project must use the NSM numbering scheme and also must correlate exactly through level seven to the corresponding financial accounting structure utilized for each project within the NASA Core Financial System. In addition to the NASA Core Financial System requirements, projects must submit data into the CADRe system under the CADRe WBS format, shown at right. These data are used by the Agency for reference in future cost estimates. Construction of a project WBS that mirrors or easily maps to the CADRe structure will achieve savings in future level of effort and is considered a “best practice.”
Appendix B
Spacecraft Level and then double-costing when applying mission wraps to the spacecraft results. The cost analysis must take care to avoid these pitfalls.
The CBS should be consistent with other functions and data sources, such as the budget, the Master Equipment List (MEL), and the Project Management Plan (PMP). The CBS should also be consistent with the appropriate NASA Standard Level 2 WBS template. The analyst must be aware that Pre–Phase A studies may not address all elements in a NASA Standard WBS or provide a cost categorization consistent with the standard WBS terminology.
Per the requirements in NPR 7120.5E, a project should have a preliminary WBS and WBS dictionary by Phase A. The WBS dictionary defines all of the elements in the WBS and is a highly useful document for aligning the project’s structure for tracking resources to the content of the cost models. Identifying and resolving differences between these elements is necessary to produce an estimate that accurately reflects the project content.
Once the estimate is complete, the analyst will need to coordinate with the project or study lead to identify the proper WBS level for reporting. Generally speaking, reporting is done at a higher level than the estimate (e.g., reporting the spacecraft estimate at the total level when the estimate is performed at the subsystem level). The costs at the more detailed WBS levels need to be available as backup material to address questions and provide substantiation.
When performing a full Life Cycle Cost (LCC) estimate, the analyst must consider the temporal aspects of the WBS. Ideally, all elements of the WBS will be defined at the beginning of the project life cycle. However, if the project is in the formulation phase, the focus may be on near-term activities such as system development, with less attention being paid to other aspects of the project life cycle. It is incumbent upon the analyst to ensure that all content of a project’s life cycle is adequately addressed.
The NASA Space Flight Project Standard WBS, as defined in the NASA Work Breakdown Structure Handbook,^6 is an acceptable approach to ensuring that all LCCs are captured. Since all projects are required to use the NASA Standard WBS, the project’s WBS and WBS dictionary must be compatible. The NASA Standard WBS is shown below in Figure B-2.
(^6) http://ntrs.nasa.gov/archive/nasa/casi.ntrs.nasa.gov/20110012671_2011013098.pdf
PCEC replacing NAFCOM At the time of this report’s publication, NAFCOM is still heavily used by the NASA cost estimating community. However, NAFCOM users are in the process of transitioning to the Project Cost Estimating Capability (PCEC), which contains additional information and tools. PCEC incorporates NAFCOM models, as well as models developed by various NASA Centers and directorates. Since most users at this time are more familiar with NAFCOM, this handbook will continue to reference it. The expectation is that the functionality provided to users by NAFCOM and referred to here will continue with PCEC.
Appendix B
Figure B-2. NASA Standard Space Flight Project WBS
Note that Figure B-2 only proceeds to level II in its depiction. The standard does not intend that this is the lowest level required. Rather, the standard grants significant freedom to the Project or Program Manager to select which branches require lower levels. In addition to the Flight Projects Standard WBS, there are lower-level standard WBSes defined in NPR 7120.8, Appendix K.^7 The standard CADRe WBS is also consistent with the NASA Standard WBS but goes to more detailed levels. MIL-STD-881C^8 is another resource. PCEC has multiple standard WBS templates that may be helpful to the analyst.^9
In addition to the product- or cost-oriented WBS, there are alternative ways of organizing the work and presenting the cost. This section discusses three of these approaches: the Organizational Work Breakdown Structure (OBS), the Functional Work Breakdown Structure (FBS), and Elements of Cost (EOC). The relationship between these different breakdown structures is shown in Figure B-3.
(^7) http://nodis3.gsfc.nasa.gov/displayDir.cfm?Internal_ID=N_PR_7120_0008&page_name=AppendixK_ (^8) MIL-STD 881C Work Breakdown Structure for Defense Materiel Items, 3 October 2011, https://acc.dau.mil/CommunityBrowser.aspx?id= (^9) PCEC will contain the following WBS templates: NASA NPR 7120.5, NASA CADRe, NC12 Earth Orbiting Spacecraft, NC Planetary Spacecraft, NC12 Uncrewed Spacecraft, NC12 Crewed Spacecraft, NC12 Launch Vehicle Stage
Appendix B
FBSes are typically seen in recurring activities. Both mission operations and ground processing lend themselves to an FBS, where the work required to either prepare flight hardware for launch or operate the hardware post launch is best described using action (or functional) terms (vehicle processing, for example).
An FBS is sometimes referred to as an activity-oriented structure. An activity-oriented structure contains all the activities needed to develop a mission. It is also usable for any subset of the mission. It focuses on work that must be done, rather than on end products. The activity-based structure is not tied to any particular architecture because it is a list of the needed functions, not the elements, of the architecture.^11
The following is an example of an activity-based structure:
It should be noted that these activities are performed in support of a number of the aforementioned WBS elements (e.g., payload, spacecraft, and ground systems). Each of the above activities is a part of each of the WBS elements and can even be assigned to individual subsystems or components. The activities are typically performed by different organizations, with engineering performed by the engineering organization and manufacturing by the manufacturing organization. Contractor or civil service labor may be recorded in systems that are first organized by function and then by end item. Data may be available for both. Every contractor manages its projects differently. Some manage by products, some by functional activities, and others by both.
The estimating community has traditionally focused on the cost by WBS, but the activity-based or FBS may be utilized to either develop a grassroots estimate or to normalize data for inclusion in a parametric cost model. With the introduction of JCL (see Appendix J), obtaining actual costs by both WBS and activities will become more critical. So as more data are collected, the Agency will have better historical data to improve future JCL estimates. During project execution, use of activity- or function-based data displays may also provide very useful insight into both plans and actuals and offer analysts the ability to quickly identify problems or disconnects between planned expenditures or staffing and project schedules.
(^11) The Functional Breakdown Structure and its Relationship to Life Cycle Costs,” DeHoff, Levack, and Rhodes, 45th
AIAA/ASME/SAE/ASEE Joint Propulsion Conference, August 2009.
Appendix B
An EOC structure is unique in that it can be used as a standalone approach to organizing cost data, or it can be used to provide more detail for other WBS forms. Because it is relatively standard, elements of cost are often aligned with the accounting system and focus on capturing cost and other resource data at the lowest possible level. A typical EOC breakdown will look similar to the NAFCOM EOC shown in Figure B-4.
Example: EOC in NAFCOM: In addition to estimating by WBS, cost models such as NAFCOM, PCEC, PRICE, and SEER can produce cost estimates by EOC. NAFCOM assumes a standardized cost element breakdown, including cost for labor, material, overhead, subcontracts, Other Direct Charges (ODCs), and General and Administrative (G&A) expenses for each element in the WBS. The cost element breakdown is computed using default labor, overhead, and G&A rates, as well as average percent-of-total factors derived from an analysis of historical missions. The analyst is able to further refine the cost estimate with user-defined labor, G&A, and overhead rates. In addition to cost, labor is also reported in hours separated into engineering, manufacturing, and other (quality control, tooling, facilities labor) categories.
Figure B-4. Standard Elements of Cost Used in NAFCOM
The data and research performed result in the default labor rates; percent-of-total factors for engineering labor, manufacturing labor, other labor, material, and Other Direct Charges; default make percentage; G&A percentage; and overhead percentage. Data are obtained representing different spacecraft types, agencies, and reporting methods. The standard cost elements identified above provide consistency for allocating various reporting types into similar groupings. Definitions for these elements of cost are provided in the next subsection.
Engineering Labor —Engineering labor is generally defined as the direct labor expended by engineering employees while performing all scientific investigations, technical processes, research, development and design, system engineering, testing, logistics, and support for the manufacturing process of a specific product.
Standard Elements of Cost in NAFCOM
Labor Hours o Engineering Labor Hours o Manufacturing Labor Hours o Other Labor Hours Labor $ o Engineering Labor $ o Manufacturing Labor $ o Other Labor $ Overhead $ Material $ Subcontracts $ ODCs $ G&A $