


Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
COST ANALYSIS OF DEWAN TERBUKA UNTUK SEKOLAH MENENGAH KEBANGSAAN
Typology: Assignments
1 / 4
This page cannot be seen from the preview
Don't miss anything!



ELEMENTAL COST ANALYSIS - Form 1 3 - Administrative Buildings A - 3 - 8586. JOB TITLE: Kerja-Kerja Membina Dan Menyiapkan Bangunan Sebuah Dewan Terbuka CLIENT: Public Berbumbung Di Sekolah Kebangsaan Desa Cempaka, Daerah Seremban, Negeri Sembilan Darul Khusus. LOCATION: Daerah Seremban, Negeri Sembilan Darul Khusus. TENDER DATE: 18-Apr- INFORMATION TOTAL PROJECT Project and Contract Information Project Details and Site Condition: Contract: (^) JPNS(KK): 29/ An open hall is mainly for the students of Sekolah Menengah Kebangsaan Desa Cempaka. The land is generally flat in nature and surrounded by the existing building of the school. Market Conditions: Market condition are competitive and price of labour and materials are stable. Contract Particulars: Competitive Tender List Type of Contract: Bespoke Contract Cost Fluctuation: Yes RM Int (jv)/L No Basis of Tender Open/Selected Bills of Quantities Competition Government Bills of Appr. Quant. Negotiated Private Sched. Of Rates/ Provisional Sum RM 58,780. Spec. & Drawings Serials Prime Cost Sum RM N/A Contract Period Stip. By Client: Preliminaries RM 12,000. Contract Period Offered by Builders: Contingencies RM N/A Number of Tenders Issued: Contract Sum RM 580,175. Number of Tenders Received: ANALYSIS OF SINGLE BUILDING Design/Shape Information Accommodation and Design Features: An open hall is a reinforced concrete structure in square shape for standard units. Areas: Functional Unit: Design/Shapes Percentage of Gross Floor Area Lower Ground Floor N/A m Ground Floor 358.66 m2 External Wall Area (a) Below Grd. Flr. % Upper Floor N/A m2 Gross Floor Area GROSS FLOOR AREA 358.66 m2 (b) Single Storey Construction % Usable Area m2 = Circulation Area m2 (c) Two-Storey Ancillary Area m2 Storey Heights: Construction % Internal Division m GROSS FLOOR AREA m2 Av. Below Grd. Floor m (d) 3-Storey Construction % Floor Space NOT Enclosed m2 At Ground Floor m (e) - Storey Roof Area m2 Above Ground Floor m Construction % (Structural & Plant Rooms) Brief Cost Information Contract Sums RM Functional Unit Costs Provisional Sums RM excluding external works: Prime Cost Sums RM Preliminaries RM being % of remainder Contingencies RM being % Contract Sum Contract Sums less Contingencies RM
ELEMENTAL COST ANALYSIS - Form 2 ELEMENT COST ANALYSIS - Form 2 SUMMARY OF ELEMENT COSTS GROSS FLOOR AREA: TENDER DATE: Preliminaries Shown Separately Total Cost Cost per m2 Element Element Unit Element Reinforced Reinforcement Formwork of Element GFA Unit Rate Ratio Concrete kg m RM RM Quantity RM per m2 GFA m 1 Substructure 1A Piling 1B Work Below Lowest Floor Finish Group Element Total 2 Superstructure 2A Frame 2B Upper Floors 2C Roof 2D Stairs 2E External Walls 2F Windows & External Doors 2G Internal Walls & Partitions 2H Internal Doors Group Element Total 3 Finishes 3A Internal Wall Finishes 3B Internal Floor Finishes 3C Internal Ceiling Finishes 3D External Finishes Group Element Total 4 Fittings and Furnishings P.C. Sum Allowed Tendered Sum 5 Services 5A Sanitary Appliances 5B Plumbing Installation 5C Refuse Disposal 5D Air-conditioning & Ventilation System 5E Electrical Installation 5F Fire Protection Installation 5G Lift & Conveyor Installation 5H Communication Installation 5J Special Installation 5K Builder's Profit & Attendance on Services 5L Builder's Work in Connection with Services Group Element Total Sub-total exc. External Works, Preliminaries and Contingencies 6 External Works 6A Site Work 6B Drainage 6C External Services 6D Ancillary Buildings 6E Recreational Facilities Group Element Total Preliminaries TOTAL (less Contingencies)