Construction Project Management: Key Concepts and Terminology, Exams of Construction

A concise overview of key concepts and terminology related to construction project management. It covers various stages of the facility life cycle, from project conception to facility management, and defines roles such as the principle stakeholder, ahj, design team, contractor team, and supplier team. The document also outlines different project delivery methods, construction documents, and sustainable design practices. It serves as a quick reference guide for understanding the fundamental aspects of construction projects, including procurement, bidding, and quality control. Useful for students and professionals in architecture, engineering, and construction.

Typology: Exams

2024/2025

Available from 06/22/2025

DOCSHUB
DOCSHUB 🇺🇸

5

(2)

12K documents

1 / 42

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CSI
/CDT /Exam /Questions /With /Correct /Answers
Owner /-
/correct
/answer(s) /✔✔ /Principle /stakeholder /- /initiates /project, /assumes /risk, /provides /funding
AHJ /-
/Authorities
/Having /Jurisdiction /- /correct /answer(s) /✔✔ /Protect /public /health, /safety /and /welfare
Design
/Team /-
/correct
/answer(s)
/✔✔
/Address
/planning
/issues, /determine /design /program, /identify /codes /and /regulations, /produce /procurement /and
/construction /documents, /administer /construction /contract, /*provide /QA/QC /procedures*
Contractor
/Team /-
/correct
/answer(s)
/✔✔
/Entity
/that
/constructs /
a
/facility.
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a
pf1b
pf1c
pf1d
pf1e
pf1f
pf20
pf21
pf22
pf23
pf24
pf25
pf26
pf27
pf28
pf29
pf2a

Partial preview of the text

Download Construction Project Management: Key Concepts and Terminology and more Exams Construction in PDF only on Docsity!

CSI

/CDT /Exam /Questions /With /Correct /Answers

Owner /- /correct /answer(s) / ✔✔ /Principle /stakeholder /- /initiates /project, /assumes /risk, /provides /funding AHJ /- /Authorities /Having /Jurisdiction /- /correct /answer(s) / ✔✔ /Protect /public /health, /safety /and /welfare Design /Team /- /correct /answer(s) / ✔✔ /Address /planning /issues, /determine /design /program, /identify /codes /and /regulations, /produce /procurement /and /construction /documents, /administer /construction /contract, /provide /QA/QC /procedures Contractor /Team /- /correct /answer(s) / ✔✔ /Entity /that /constructs / a /facility.

/Uses /management /abilities /to /gather /labor /forces, /subs, /and /material/product/equipment /suppliers Supplier /Team /- /correct /answer(s) / ✔✔ /Furnishes /the /materials /and /products /for /the /facility /to /be /constructed. /Fabricator, /Distributor, /Manufacturer, /Supplier. Facility /Life /Cycle /- /correct /answer(s) / ✔✔ /The /life /cycle /of /a /facility, /from /concept /through /construction /to /use /and /eventual /deconstruction. / Project /Conception Project /Delivery Design Construction /Documents Procurement /(Bidding/Negotiating/Purchasing) Construction Facility /Management

/development. /Deliverables /include /graphic /and /written /design /documents /and /estimates /of /project /cost. Schematic /Design /- /correct /answer(s) / ✔✔ /Overall /relationships /and /functions. /Site /plan /and /area, /general /size/shape/massing /of /elements, /elevations /and /exteriors /established, /conceptual /design /criteria /identified. / Deliverables /- /schematic /drawings, /probable /cost, /preliminary /schedules Design /Development /- /correct /answer(s) / ✔✔ /Technical /issues /of /constructibility /and /integration /of /systems /and /components. / Deliverables /- /Tech /information, /outline /specifications, /updated /schedule, /updated /cost /estimate. Construction /Documents /- /correct /answer(s) / ✔✔

/Defined /as /the /written /and /graphic /documents /prepared /or /assembled /by /the /A/E /for /communicating /the /project /design /for /construction /and /administering /the /construction /contract. /Construction /documents /include /two /major /types /of /documents: /Procurement /documents /and /Contract /documents. Procurement /(Bidding/Negotiating/Purchasing) /- /correct /answer(s) / ✔✔ /Acceptance /of /the /contractor's /bid /or /negotiated /sum /and /other /conditions /will /result /in /award /of /a /contract /and /commencement /of /work. Construction /- /correct /answer(s) / ✔✔ /Responsibilities: Contractor /- /perform /work, /project /coordination, /comply /with /project /documents. A/ E /- /construction /admin, /evaluation /services, /certify /application /for /payment, /final /inspection /of /work. / Owner /- /provide /information, /process /payments, /approve /contract /modifications, /accept /project /upon /completion.

/or /sequence /on /the /basis /of /systems /or /assemblies. /Particularly /useful /in /conceptual /design. /Element /Identification. MasterFormat /- /correct /answer(s) / ✔✔ /Arranges /related /construction /practices, /logical /groupings /of /work /results, /into / a /series /of /divisions. / 50 /division /format. /Used /for /Specifications, /data /organization, /and /cost /classification. MasterFormat /Groups /- /correct /answer(s) / ✔✔ / 00 /Procurement /and /Contracting /Requirement /Group Specifications /Group

  • /General /Requirements / 01
  • /Facility /Construction /Subgroup /(concrete)
  • /Facility /Services /(plumbing/HVAC)
  • /Site /and /Infrastructure /(Earthwork)
  • /Process /Equipment /(WW /equipment) SectionFormat /- /correct /answer(s) / ✔✔ /Provides / a /uniform /approach /to /organizing /specification /information /by /three /primary /parts. /General, /Products, /Execution Sustainable /Design /- /correct /answer(s) / ✔✔ /Environmental /performance /of /the /facility /over /course /of /its /life /cycle. /Takes /place /at /the /product /and /facility /level. Environmental /Design /Tools /- /correct /answer(s) / ✔✔ /National /Institute /of /Technology /(NIST) /- /Building /for /Env. /and /Economic /Sustainability /(BEES) /- /for /building /products

Green /Buildings /- /correct /answer(s) / ✔✔ /Reduce /overall /impact /of /the /built /environment /by /protecting /occupant /health /and /improving /employee /productivity. National /CAD /standard /- /correct /answer(s) / ✔✔ /CSI /Uniform /Drawing /System Autonomy /to /Contract /- /correct /answer(s) / ✔✔ /Two /parties /are /mutually /free /to /determine /the /terms /of /an /agreement /for /a /specific /purpose. Trade /Customs /- /correct /answer(s) / ✔✔ /If /contract /document /don't /adequately /establish /intent, /court /may /rely /on /customs /of /an /industry. Preliminary /Project /Description /- /correct /answer(s)

/Method /of /describing /aspects /of /the /schematic /design /in /written /form. /Describe /physical /requirements /the /logical /grouping /of /systems /assemblies /and /components. Dual /Nature /of /Design /- /correct /answer(s) / ✔✔ /Aesthetic /and /Technical /Design Quality /Control /- /correct /answer(s) / ✔✔ /Procedures /for /evaluating /completed /activities /and /elements /of /design /for /conformance. Quality /Assurance /- /correct /answer(s) / ✔✔ /Procedures /for /guarding /against /defects /and /deficiencies /before /and /during /execution /of /work. Allowance /- /correct /answer(s) / ✔✔

Construction /Budget /- /correct /answer(s) / ✔✔ /Prepared /by /several /methods. /Systems /(CSI /UniFormat), /cost /per /measured /units, /component /costs. Project /Schedule /- /correct /answer(s) / ✔✔ /Succession /of /steps, /script /of /interactions, /milestone /dates. Six /Project /Delivery /Methods /- /correct /answer(s) / ✔✔ /Design-Bid-Build Design-Negotiate-Build CMA Design-Build Owner-Build Integrated /Project /Delivery Total /Project /Commissioning /- /correct /answer(s) / ✔✔ /Quality /process /utilizing /an /independent /company /providing

/services. /Commissioning /continues /through /the /construction /stage /of /the /project /to /provide /QA/QC. Life /Cycle /Costs /- /correct /answer(s) / ✔✔ /Total /cost /of /ownership. /Initial /construction /costs /as /well /as /renovation, /remodeling, /and /improvements. Alternate /- /correct /answer(s) / ✔✔ /Portion /of /the /work /that /is /priced /separately /and /thus /provides /and /option /for /owner /in /determining /final /scope. /Additive /or /deductive /work /item. Unit /Price /- /correct /answer(s) / ✔✔ /Type /of /work /is /defined, /but /extent /is /unknown /of /likely /to /change.

/Various /types /of /information /should /be /made /available /to /bidders/proposers/contractors, /however, /they /are /not /contract /documents. /Reference /documents /that /do /not /belong /in /contract /documents. Bid /Form /- /correct /answer(s) / ✔✔ /Project /Identification Name /and /address /of /addressed /party Entity /submitting /bid Acknowledgements Amount /of /time /bid /is /open Identification /of /addenda Prices Combined /bids Alternates Allowances Unit /Prices Completion /Time Liquidated /damages Supplements

Closing Conditions /of /the /Contract /- /correct /answer(s) / ✔✔ /Define /basic /rights, /responsibilities, /and /relationships /of /parties /involved. /Inherent /part /of /owner- contractor /agreement. /General /and /Supplementary General /Conditions /- /correct /answer(s) / ✔✔ /Standard /documents /that /establish / a /baseline /of /which /exceptions, /modification, /and /additions /of /the /supplementary /conditions /are /identified. Supplementary /Conditions /- /correct /answer(s) / ✔✔ /Requirements /of

Certificates Drawing /- /correct /answer(s) / ✔✔ /Graphic /and /textual /information /in /2D /format. /Conveys /design /intent. Construction /Drawings /- /correct /answer(s) / ✔✔ /Consist /of /contract /drawings /and /resource /drawings. Contract /Drawings /- /correct /answer(s) / ✔✔ /Legally /enforceable /drawings. /Could /show /deconstruction, /alteration, /new /construction. Record /Drawings /- /correct /answer(s) / ✔✔ /Marked- up /or /corrected /contract /drawings /that /identify /changes /incorporated /into /the /work /during /construction. Scaled /Views /- /correct /answer(s) / ✔✔ /Plans /- /Horizontal /Planes Elevations /- /Vertical /Planes Sections /- /Vertical /Cut Detail /- /may /be /a /plan, /elevation, /or /section /view Nonscaled /Views /- /correct /answer(s) / ✔✔ /Diagrams, /Key /Plans, /Schedules, /Perspectives, /Isometric, /Title /Sheet

Two /methods /for /preparing /written /changes /- /correct /answer(s) / ✔✔ /Narrative /Method /and /Revised /Page /Method Addenda /- /correct /answer(s) / ✔✔ /Written /or /graphic /instruction /to /clarify, /revise, /add /to, /or /delete /information /in /the /procurement /documents. /Clarifies /questions /raised /by /bidders, /issue /new /requirements, /and /correct /errors/omissions. /Usually /prior /to /receiving /bids. Contract /Document /Modifications /- /correct /answer(s) / ✔✔ /Change /Orders Construction /Change /Directive