



Study with the several resources on Docsity
Earn points by helping other students or get them with a premium plan
Prepare for your exams
Study with the several resources on Docsity
Earn points to download
Earn points by helping other students or get them with a premium plan
Solutions to exam #2 for a ce 167 class focusing on project management. It includes evaluating a project's earned value status, analyzing activity schedules, and understanding cardinal changes and force account. The document also covers concepts like type i and type ii differing site conditions and maslow's hierarchy of needs.
Typology: Exams
1 / 5
This page cannot be seen from the preview
Don't miss anything!




CE 167 Exam # Fall 2003 Prof. C.W. Ibbs
Directions:
Question #1 [30 points]
Using the data below, evaluate this project’s earned value status as of the beginning of day 13 and the beginning of day 22. Depict the project status graphically. How is this project trending? Do you think the project will finish on budget? Discuss your analysis. All dates represent the beginning of the day.
Activity Planned Dates Start Finish
Total Cost Budgeted Unit Cost A 1 12 $11,000 $1,000/day B 8 18 $15,000 $1,500/day C 10 25 $28,000 $2,000/day D 12 28 $32,000 $2,000/day Total 1 28 $86,
As of Beginning of Day 13:
Activity Actual or Forecasted* Dates Start Finish
Actual Cost Spent-to-Date
% Complete
A 1 9 $8,000 100% B 8 14* $21,000 90% C 12 26* $20,000 50% D 15* 28* $0 0% Total 1 28* $49,
As of Beginning of Day 22:
Activity Actual or Forecasted* Dates Start Finish
Actual Cost Spent-to-Date
% Complete
Total 1 27* $76,
Solution
As of Beginning of Day 13:
Activity BCWS ACWP BCWP SV CV A $11,000 $8,000 $11,000 $0 $3, B $7,500 $21,000 $13,500 $6,000 -$7, C $6,000 $20,000 $14,000 $8,000 -$6, D $2,000 $0 $0 -$2,000 $ Total $26,500 $49,000 $38,500 $12,000 -$10,
CPI 13 = BCWP/ACWP = $38,500/$49,000 = 0.79 < 1 (over budget)
SPI 13 = BCWP/BCWS = $38,500/$26,500 = 1.45 > 1 (ahead of schedule)
As of Beginning of Day 22:
Activity BCWS ACWP BCWP SV CV A $11,000 $8,000 $11,000 $0 $3, B $15,000 $22,000 $15,000 $0 -$7, C $24,000 $20,000 $25,200 $1,200 $5, D $20,000 $26,000 $25,600 $5,600 -$ Total $70,000 $76,000 $76,800 $16,800 $
CPI 22 = BCWP 22 /ACWP 22 = $76,800/$76,000 = 1.01 (approx. on budget)
SPI 22 = (BCWP 25 / BCWS 22 ) $76,800/$70,000 = 1.10 (slightly ahead of schedule)
Question #2 [30 points total – 15 points for each part]
a) For the following activities, find the early start, early finish, late start, late finish, total float and free float. Record your answers neatly in a table. Determine which activities are critical.
Activity Predecessor Duration A -- 2 B A 4 C A 5 D A 6 E D 2 F B, C 5 G E 6 H E 1 I F, G, H 2
b) Perform the same calculations as above, but add a finish-to-finish constraint of 10 (FF10) between Activities B and F, a start-to-start constraint of 4 (SS4) between Activities C and F, and a finish-to-start constraint of 2 (FS2) between activities E and H. Record your answers in a separate table. Do the two schedules differ, and if so, how? Be specific.
Question #3 [10 points]
What is a cardinal change? Why are cardinal changes illegal in public works projects? Can a contractor be properly forced to perform a cardinal change in private work?
According to Bartholomew (p. 208):
Question #4 [5 points]
What is force account?
According to Bartholomew (p. 210):
Force account is a particular form of retrospective pricing in which the contract spells out a specific procedure for arriving at the price adjustment when the contractor and owner fail to agree on the price by forward pricing (forward pricing is when the owner and contractor agree on the price and time requirement for a change or additional work before starting the work required by the change).
Question #5 [10 points]
Briefly define and give an example of Type I and Type II differing site conditions (DSC).
Question #6 [5 points]
List the five levels of Maslow’s Hierarch of Needs.
From lowest to highest: