Earned Value Management Foundation Practice Exam, Exams of Technology

This practice exam focuses on Earned Value Management (EVM), a project management technique used to assess project performance. The exam covers key concepts such as project scope, schedule, cost management, and how to calculate earned value, cost variance, and schedule variance. It is suitable for professionals seeking to assess their project management and cost control skills.

Typology: Exams

2025/2026

Available from 01/03/2026

shilpi-jain-1
shilpi-jain-1 🇮🇳

4.2

(5)

29K documents

1 / 108

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Earned Value Management Foundation
Practice Exam
**1. What is Earned Value Management (EVM)?**
A) A project management technique used to measure performance
B) A type of project schedule
C) A method of cost estimation
D) A quality control process
Answer: A) A project management technique used to measure performance
Explanation: Earned Value Management is a project management technique used to
measure performance and progress by comparing the actual cost, schedule, and scope of a
project to the planned values.
**2. What is the primary objective of Earned Value Management?**
A) To reduce project costs
B) To improve project schedules
C) To measure project performance and progress
D) To increase project scope
Answer: C) To measure project performance and progress
Explanation: The primary objective of Earned Value Management is to measure project
performance and progress by comparing actual and planned values.
**3. What is the definition of Earned Value (EV)?**
A) Actual Cost (AC) x Performance Index (PI)
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a
pf1b
pf1c
pf1d
pf1e
pf1f
pf20
pf21
pf22
pf23
pf24
pf25
pf26
pf27
pf28
pf29
pf2a
pf2b
pf2c
pf2d
pf2e
pf2f
pf30
pf31
pf32
pf33
pf34
pf35
pf36
pf37
pf38
pf39
pf3a
pf3b
pf3c
pf3d
pf3e
pf3f
pf40
pf41
pf42
pf43
pf44
pf45
pf46
pf47
pf48
pf49
pf4a
pf4b
pf4c
pf4d
pf4e
pf4f
pf50
pf51
pf52
pf53
pf54
pf55
pf56
pf57
pf58
pf59
pf5a
pf5b
pf5c
pf5d
pf5e
pf5f
pf60
pf61
pf62
pf63
pf64

Partial preview of the text

Download Earned Value Management Foundation Practice Exam and more Exams Technology in PDF only on Docsity!

Practice Exam

1. What is Earned Value Management (EVM)? A) A project management technique used to measure performance B) A type of project schedule C) A method of cost estimation D) A quality control process Answer: A) A project management technique used to measure performance Explanation: Earned Value Management is a project management technique used to measure performance and progress by comparing the actual cost, schedule, and scope of a project to the planned values. 2. What is the primary objective of Earned Value Management? A) To reduce project costs B) To improve project schedules C) To measure project performance and progress D) To increase project scope Answer: C) To measure project performance and progress Explanation: The primary objective of Earned Value Management is to measure project performance and progress by comparing actual and planned values. 3. What is the definition of Earned Value (EV)? A) Actual Cost (AC) x Performance Index (PI)

Practice Exam

B) Budgeted Cost (BC) x Performance Index (PI) C) Actual Cost (AC) x Budgeted Cost (BC) D) Actual Cost (AC) - Budgeted Cost (BC) Answer: B) Budgeted Cost (BC) x Performance Index (PI) Explanation: Earned Value is defined as the budgeted cost multiplied by the performance index, which represents the amount of work completed as a percentage of the planned work. 4. What is the Performance Index (PI)? A) Actual Cost (AC) / Budgeted Cost (BC) B) Budgeted Cost (BC) / Actual Cost (AC) C) Actual Cost (AC) / Budgeted Cost (BC) D) Budgeted Cost (BC) / Budgeted Cost (BC) Answer: C) Actual Cost (AC) / Budgeted Cost (BC) Explanation: The Performance Index is the ratio of actual cost to budgeted cost, which represents the amount of work completed as a percentage of the planned work. 5. What is the Cost Variance (CV)? A) Earned Value (EV) - Actual Cost (AC) B) Budgeted Cost (BC) - Earned Value (EV) C) Earned Value (EV) - Budgeted Cost (BC) D) Actual Cost (AC) - Budgeted Cost (BC)

Practice Exam

8. What is the Schedule Performance Index (SPI)? A) Earned Value (EV) / Budgeted Cost (BC) B) Budgeted Cost (BC) / Earned Value (EV) C) Earned Value (EV) / Actual Cost (AC) D) Actual Cost (AC) / Earned Value (EV) Answer: A) Earned Value (EV) / Budgeted Cost (BC) Explanation: The Schedule Performance Index is the ratio of earned value to budgeted cost, which represents the ability to complete work within schedule. 9. What is the definition of At Completion (AC)? A) The total budget for the project B) The total cost of the project C) The total earned value of the project D) The total actual cost of the project Answer: B) The total cost of the project Explanation: At Completion is the total cost of the project, which includes all actual costs and any changes to the budget. 10. What is the definition of Planned Value (PV)?

Practice Exam

A) The budgeted cost for the project B) The earned value of the project C) The actual cost of the project D) The cost of completing the project Answer: A) The budgeted cost for the project Explanation: Planned Value is the budgeted cost for the project, which represents the planned value of work completed. 11. What is the definition of Actual Cost (AC)? A) The total budget for the project B) The total earned value of the project C) The total cost of the project D) The actual cost incurred for the project Answer: D) The actual cost incurred for the project Explanation: Actual Cost is the actual cost incurred for the project, which includes all actual expenditures. 12. What is the definition of Budget at Completion (BAC)? A) The total budget for the project B) The total cost of the project C) The total earned value of the project

Practice Exam

Explanation: Earned Value is the earned value of the project, which represents the value of work completed. 15. What is the definition of Budgeted Cost of Work Scheduled (BCWS)? A) The total budget for the project B) The total cost of the project C) The budgeted cost of the project D) The budgeted cost of work scheduled Answer: D) The budgeted cost of work scheduled Explanation: Budgeted Cost of Work Scheduled is the budgeted cost of work scheduled, which represents the budgeted cost of work to be done. 16. What is the definition of Budgeted Cost of Work Performed (BCWP)? A) The total budget for the project B) The total cost of the project C) The budgeted cost of the project D) The budgeted cost of work performed Answer: D) The budgeted cost of work performed Explanation: Budgeted Cost of Work Performed is the budgeted cost of work performed, which represents the budgeted cost of work completed.

Practice Exam

17. What is the definition of Variance at Completion (VAC)? A) The actual cost of the project B) The budgeted cost for the project C) The total cost of the project D) The variance at completion Answer: D) The variance at completion Explanation: Variance at Completion is the variance at completion, which represents the difference between planned and actual costs at completion. 18. What is the definition of Earned Value Index (EVI)? A) The ratio of earned value to actual cost B) The ratio of budgeted cost to actual cost C) The ratio of earned value to budgeted cost D) The ratio of actual cost to earned value Answer: C) The ratio of earned value to budgeted cost Explanation: Earned Value Index is the ratio of earned value to budgeted cost, which represents the ability to complete work within budget. 19. What is the definition of Schedule Performance Index (SPI)? A) The ratio of earned value to actual cost B) The ratio of budgeted cost to actual cost

Practice Exam

Answer: A) A set of metrics used to measure project performance Explanation: EVM metrics are a set of metrics used to measure project performance and progress. 22. What is the purpose of Earned Value Management (EVM) metrics? A) To measure project costs B) To measure project schedules C) To measure project performance and progress D) To measure project scope Answer: C) To measure project performance and progress Explanation: The purpose of EVM metrics is to measure project performance and progress by comparing actual and planned values. 23. What is the definition of Baseline Cost? A) The total budget for the project B) The total cost of the project C) The budgeted cost of the project D) The baseline cost Answer: C) The budgeted cost of the project Explanation: Baseline Cost is the budgeted cost of the project, which represents the planned cost of the project.

Practice Exam

24. What is the definition of Budget? A) The total budget for the project B) The total cost of the project C) The budgeted cost of the project D) The budget Answer: C) The budgeted cost of the project Explanation: Budget is the budgeted cost of the project, which represents the planned cost of the project. 25. What is the definition of Cost Variance (CV)? A) The difference between earned value and actual cost B) The difference between budgeted cost and earned value C) The difference between actual cost and earned value D) The difference between earned value and budgeted cost Answer: A) The difference between earned value and actual cost Explanation: Cost Variance is the difference between earned value and actual cost, which represents the difference between planned and actual costs. 26. What is the definition of Schedule Variance (SV)? A) The difference between earned value and budgeted cost

Practice Exam

Answer: A) The ratio of earned value to budgeted cost Explanation: Schedule Performance Index is the ratio of earned value to budgeted cost, which represents the ability to complete work within schedule. 29. What is the definition of Earned Value (EV)? A) The actual cost of the project B) The budgeted cost for the project C) The earned value of the project D) The budgeted cost of the project Answer: C) The earned value of the project Explanation: Earned Value is the earned value of the project, which represents the value of work completed. 30. What is the definition of Budget at Completion (BAC)? A) The total budget for the project B) The total cost of the project C) The total earned value of the project D) The budget at completion Answer: D) The budget at completion Explanation: Budget at Completion is the budget at completion, which represents the planned budget for the project at completion.

Practice Exam

31. What is the definition of At Completion (AC)? A) The total budget for the project B) The total cost of the project C) The total earned value of the project D) The actual cost at completion Answer: B) The total cost of the project Explanation: At Completion is the total cost of the project, which includes all actual costs and any changes to the budget. 32. What is the definition of Earned Value Index (EVI)? A) The ratio of earned value to actual cost B) The ratio of budgeted cost to actual cost C) The ratio of earned value to budgeted cost D) The ratio of actual cost to earned value Answer: C) The ratio of earned value to budgeted cost Explanation: Earned Value Index is the ratio of earned value to budgeted cost, which represents the ability to complete work within budget. 33. What is the definition of Schedule Performance Index (SPI)?

Practice Exam

D) A quality control process Answer: A) A set of metrics used to measure project performance Explanation: EVM metrics are a set of metrics used to measure project performance and progress. 36. What is the purpose of Earned Value Management (EVM) metrics? A) To measure project costs B) To measure project schedules C) To measure project performance and progress D) To measure project scope Answer: C) To measure project performance and progress Explanation: The purpose of EVM metrics is to measure project performance and progress by comparing actual and planned values. 37. What is the definition of Baseline Cost? A) The total budget for the project B) The total cost of the project C) The budgeted cost of the project D) The baseline cost Answer: C) The budgeted cost of the project

Practice Exam

Explanation: Baseline Cost is the budgeted cost of the project, which represents the planned cost of the project. 38. What is the definition of Budget? A) The total budget for the project B) The total cost of the project C) The budgeted cost of the project D) The budget Answer: C) The budgeted cost of the project Explanation: Budget is the budgeted cost of the project, which represents the planned cost of the project. 39. What is the definition of Cost Variance (CV)? A) The difference between earned value and actual cost B) The difference between budgeted cost and earned value C) The difference between actual cost and earned value D) The difference between earned value and budgeted cost Answer: A) The difference between earned value and actual cost Explanation: Cost Variance is the difference between earned value and actual cost, which represents the difference between planned and actual costs.

Practice Exam

C) The ratio of earned value to actual cost D) The ratio of actual cost to earned value Answer: A) The ratio of earned value to budgeted cost Explanation: Schedule Performance Index is the ratio of earned value to budgeted cost, which represents the ability to complete work within schedule. 43. What is the definition of Earned Value (EV)? A) The actual cost of the project B) The budgeted cost for the project C) The earned value of the project D) The budgeted cost of the project Answer: C) The earned value of the project Explanation: Earned Value is the earned value of the project, which represents the value of work completed. 44. What is the definition of Budget at Completion (BAC)? A) The total budget for the project B) The total cost of the project C) The total earned value of the project D) The budget at completion

Practice Exam

Answer: D) The budget at completion Explanation: Budget at Completion is the budget at completion, which represents the planned budget for the project at completion. 45. What is the definition of At Completion (AC)? A) The total budget for the project B) The total cost of the project C) The total earned value of the project D) The actual cost at completion Answer: B) The total cost of the project Explanation: At Completion is the total cost of the project, which includes all actual costs and any changes to the budget. 46. What is the definition of Earned Value Index (EVI)? A) The ratio of earned value to actual cost B) The ratio of budgeted cost to actual cost C) The ratio of earned value to budgeted cost D) The ratio of actual cost to earned value Answer: C) The ratio of earned value to budgeted cost Explanation: Earned Value Index is the ratio of earned value to budgeted cost, which represents the ability to complete work within budget.