IEM 5603 Chapter 12 Multiple Choice, Exams of Advanced Education

IEM 5603 Chapter 12 Multiple Choice

Typology: Exams

2025/2026

Available from 02/16/2026

studyclass
studyclass 🇺🇸

1

(1)

28K documents

1 / 9

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
IEM 5603 Chapter 12 Multiple Choice
Which of the following scheduling techniques is most appropriate today for
managing a project?
A. BAR charts
B. Milestone charts
C. PERT charts
D. Precedence charts - correct answer d
Which of the following scheduling techniques is most appropriate today for reporting
project status to a customer during an interchange meeting?
A. BAR charts
B. Milestone charts
C. PERT charts
D. Precedence charts - correct answer a
The major disadvantage of using a bar chart on large projects is that bar charts:
A. Cannot identify critical paths
B. Do not show dependencies between activities
C. Cannot identify milestones
D. Cannot show slack - correct answer b
Which of the following is not one of the four network diagramming techniques?
A. PERT
B. GERT
C. VERT
D. PDM - correct answer c
pf3
pf4
pf5
pf8
pf9

Partial preview of the text

Download IEM 5603 Chapter 12 Multiple Choice and more Exams Advanced Education in PDF only on Docsity!

IEM 5603 Chapter 12 Multiple Choice

Which of the following scheduling techniques is most appropriate today for managing a project? A. BAR charts B. Milestone charts C. PERT charts D. Precedence charts - correct answer d Which of the following scheduling techniques is most appropriate today for reporting project status to a customer during an interchange meeting? A. BAR charts B. Milestone charts C. PERT charts D. Precedence charts - correct answer a The major disadvantage of using a bar chart on large projects is that bar charts: A. Cannot identify critical paths B. Do not show dependencies between activities C. Cannot identify milestones D. Cannot show slack - correct answer b Which of the following is not one of the four network diagramming techniques? A. PERT B. GERT C. VERT D. PDM - correct answer c

Which of the following activity-on-arrow network diagramming methods does not require three estimates for durations? A. PERT B. GERT C. ADM D. PDM - correct answer c Which of the following network diagramming methods do not use dummy activities? A. PERT B. GERT C. ADM

  • D. PDM - correct answer d Which of the following network diagramming methods allows for branching and looping? A. PERT B. GERT C. ADM D. PDM - correct answer b Which of the following cannot be determined after performing a forward pass and a backward pass on a network diagram? A. The critical path B. The end date of the project C. The effort in each activity D. The slack in each activity - correct answer c Which of the following is an activity-on-node network diagramming method?

If the optimistic time for an activity is 6 weeks, the pessimistic time is 24 weeks and the most likely time is 12 weeks, then the expected duration is: A. 7 weeks B. 13 weeks C. 22 weeks D. 24 weeks - correct answer b Which of the following schedule compression techniques usually requires adding more resources to each work package that is being compressed? A. Overtime B. Crashing C. Outsourcing D. Descoping - correct answer b In which of the following schedule compression techniques is the cost of rework usually the greatest? A. Overtime B. Crashing C. Performing series work in parallel D. Outsourcing - correct answer c Which of the following schedule compression techniques is often the lowest risk and with the added benefit of lowering the cost? A. Crashing B. Descoping C. Outsourcing

D. Overtime - correct answer b Smoothing out project resources from period to period is called A. Resource leveling B. Resource allocation or resource limited planning C. Better effort planning D. Slack utilization planning - correct answer a Laying out a network diagram when you know before-hand the size of the available resource pool is called: A. Resource leveling B. Resource allocation or resource limited planning C. Better effort planning D. Slack utilization planning - correct answer b An activity in a network has the following characteristics: ES = 10, EF = 18 and LS =

  1. The duration of the activity is: A. 6 B. 8 C. 10 D. Cannot be determined - correct answer b If the slack in a 12 week activity is 6 weeks and ES = 4, then LF = _____. A. 4 B. 10 C. 16 D. 22 - correct answer d The measurement of lag is made within an activity whereas slack is measured between activities.
  1. Which of the following cannot be identified after performing a forward and backward pass? A. Dummy activities B. Slack time C. Critical path activities D. How much overtime is planned - correct answer d
  2. Which of the following is not a commonly used technique for schedule compression? A. Resource reduction B. Reducing scope C. Fast-tracking activities D. Use of overtime - correct answer a
  3. A network-based schedule has four paths, namely 7, 8, 9, and 10weeks. If the 10- weekpath is compressed to 8 weeks, then: A. We now have two critical paths. B. The 9-week path is now the critical path. C. Only the 7-week path has slack. D. Not enough information is provided to make a determination. - correct answer d
  4. The major disadvantage of using bar charts to manage a project is that bar charts: A. Do not show dependencies between activities B. Are ineffective for projects under one year in length C. Are ineffective for projects under $1 million in size D. Do not identify start and end dates of a schedule - correct answer a
  5. The first step in the development of a schedule is a: A. Listing of the activities

B. Determination of dependencies C. Calculation of effort D. Calculation of durations - correct answer a

  1. Reducing the peaks and valleys in manpower assignments in order to obtain a relatively smooth manpower curve is called: A. Manpower allocation B. Manpower leveling C. Resource allocation D. Resource commitment planning - correct answer b
  2. Activities with no time duration are called: A. Reserve activities B. Dummy activities C.Zero slack activities D. Supervision activities - correct answer b
  3. Optimistic, pessimistic, and most likely activity times are associated with: A. PERT B. GERT C. PDM D. ADM - correct answer a 10.The most common constraint or relationship in a precedence network is: A. Start-to-start B. Start-to-finish C. Finish-to-start D. Finish-to-finish - correct answer c
  4. A network-based technique that allows for branching and looping is: