PMP Sample Test Questions
(correct answers are bolded)
1. An accepted deadline for a project approaches. However, the project manager
realizes only 75% percent of the work has been completed. The project manager then
issues a change request.
What should the change request authorize?
A. Additional resources using the contingency fund
B. Escalation approval to use contingency funding
C. Team overtime to meet schedule
D. Corrective action based on causes
2. The project manager develops a process improvement plan to encourage continuous
process improvement during the life of the project. Which of the following is a valid tool
or technique to assist the project manager to assure the success of the process
improvement plan?
A. Change control system
B. Process analysis
C. Benchmarking
D. Configuration management system
3. The project manager meets with the project team to review lessons learned from
previous projects. In what activity is the team involved?
A. Performance management
B. Scope identification
C. Risk identification
D. Project team status meeting
Discount

On special offer

Partial preview of the text

Download PMP Sample Test Questions and more Exams Project Management in PDF only on Docsity!

PMP Sample Test Questions (correct answers are bolded)

  1. An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request.

What should the change request authorize?

A. Additional resources using the contingency fund B. Escalation approval to use contingency funding C. Team overtime to meet schedule D. Corrective action based on causes

  1. The project manager develops a process improvement plan to encourage continuous process improvement during the life of the project. Which of the following is a valid tool or technique to assist the project manager to assure the success of the process improvement plan?

A. Change control system B. Process analysis C. Benchmarking D. Configuration management system

  1. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

A. Performance management B. Scope identification C. Risk identification D. Project team status meeting