Project Development Plan: Web Broadcasting System for Pyaris Fun Olympics, Study Guides, Projects, Research of Professional Communication

This document details a project plan for developing a web broadcasting system for the 2024 pyaris fun olympics. it outlines the requirements collection, project planning, prototype iteration, testing, and final presentation phases, providing a structured timeline and task breakdown. The plan demonstrates a systematic approach to software development, incorporating client meetings and feedback loops.

Typology: Study Guides, Projects, Research

2023/2024

Uploaded on 04/24/2025

ksav-yadav
ksav-yadav 🇳🇵

5 documents

1 / 15

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
CET333- Product
Development
by Keshav Kumar yadav
Submission date:
Submission ID:
File name:
Word Count:
CET333 - Product Development
Payris Fun Olympic games 2024
Keshav Kumar Yadav
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff

Partial preview of the text

Download Project Development Plan: Web Broadcasting System for Pyaris Fun Olympics and more Study Guides, Projects, Research Professional Communication in PDF only on Docsity!

CET333- Product

Development

by Keshav Kumar yadav

Submission date: Submission ID: File name: Word Count: CET333 - Product Development Payris Fun Olympic games 2024 Keshav Kumar Yadav

Registration No: 239675767 e-Portfolio Link: Github Link:

Requirement Specification Planning Documentation Schedule: ID Tasks Effor t (Hou rs) Estimated Start-Date Estimated End-Date Actual Start-Date Actual End- Date Deliverable

  1. Requirements Collection and Analysis

1.1 Visualize the similar assessment with its development history 5 17/01/2024 18/01/2024 17/01/2024 18/01/2024 Understanding the development of the broadcasting website

1.2 Look for the stakeholders 5 19/01/2024 21/01/2024 19/01/2024 21/01/2024 Make notes of stakeholder involve 1.3 Meeting with the client for requirement collection 5 18/01/2024 18/01/2024 18/01/2024 18/01/2024 List of requirement 1.4 Discover the functional and non-functional requirement of the project 5 19/01/2024 22/01/2024 19/01/2024 22/01/2024 Understand the functional and non-functional requirement of client 1.5 Perform feasibility study 3 23/01/2024 25/01/2024 23/01/2024 25/01/2024 Feasibility analysis of project 1.6 Requirements Specification Document Prepared 5 25/01/2024 26/01/2024 25/01/2024 26/01/2024 SRS document 1.7 Initial client meeting record sheet prepared 5 27/01/2024 28/01/2024 27/01/2024 28/01/2024 Record sheet 1.8 First client meeting taken 3 28/01/2024 28/01/2024 29/01/2023 29/01/2024 Wireframe and logo design 1.9 Initial client meeting record signed off

1.9 Requirements specification document signed off 1 31/01/2024 31/01/2024 31/01/2024 31/01/2024 SRS document verified by client 1.10 Second client meeting sheet prepared 2 05/02/2024 06/02/2024 05/02/2024 06/02/2024 Wireframe demonstration 1.11 Second client record signed off 1 08/02/2024 08/02/2024 08/02/2024 08/02/2024 Second client record sign

  1. Project Planning

2.1 Choose the best way to develop the project 2 03/02/2024 05/02/2024 03/02/2024 05/02/2024 Identification of suitable for the development of project ins suitable way 2.2 Draft making of the plan 5 Resources find

3.2.7 Implement Additional requirements 2 27/02/2024 29/02/2024 27/03/2024 29/02/2024 Completion of website 3.3 Test the functionality of the website

3.3.1 UI of the system is tested along with the frontend 5 30/02/2024 02/03/2024 30/02/2024 02/03/2024 UI and frontend tested 3.3.2 Performance of the website tested 5 01/03/2024 03/03/2024 01/03/2024 03/03/2024 Performance noted 3.3.3 Report analyzed of test results 5 04/03/2024 05/03/2024 04/03/2024 05/03/2024 Report 3.4 Prototype Evaluation

3.4.1 Demonstration of the functional prototype in the third meeting 3 07/03/2024 07/03/2024 07/03/2024 07/03/2024 Work on adding some more feature 3.4.2 Working on the comments of the 2 nd^ client meeting 5 06/03/2024 09/03/2024 06/03/2024 09/03/2024 Made change with system 3.4.3 Signed off 3 rd client meeting 2 08/03/2024 08/03/2024 10/03/2024 10/03/2024 Record sheet ready 4 Iteration prototype design in second phase

4.1 Design updated 10 11/03/2024 14/03/2024 11/03/2024 14/03/2024 Change the UI of the website 4.2 Prototype updated 10 14/03/2024 15/03/2024 14/03/2024 15/03/2024 Make effective prototype 4.3 Tested the updated features in the system 15 16/03/2024 17/03/2024 16/03/2024 17/03/2024 Testing 4.4 Review through meeting with the client 5 18/03/2024 19/03/2024 18/03/2024 19/03/2024 Get feedback for the system 5 Presentation and assessment of the prototype

5.1 Gather and evaluate all 5 20/03/2024 22/03/2024 20/03/2024 22/03/2024 Solution design, test , report,

supporting documentation feedback note etc. 5.2 Show the client a working prototype of the system 2 23/03/2024 24/03/2024 23/03/2024 24/03/2024 Presentation 5.3 Write the evaluation of the prototype 5 25/03/2024 27/03/2024 25/03/2024 27/03/2024 Evaluate 5.4 Write critical reflection draft 5 28/03/2024 29/03/2024 28/03/2024 29/03/2024 Critical reflection writing 5.5 Write the final draft for evaluation document 5 29/03/2024 30/03/2024 29/03/2024 30/03/2024 Evaluation writing 5.5 Write the final draft of critical reflection document 2 30/03/2024 01/04/2024 30/03/2024 01/04/2024 Critical reflection writing 5.6 Update the final drafts of section in e-Portfolio 2 02/04/2024 02/04/2024 02/04/2024 02/04/2024 Update e-Portfolio 5.7 Final Submission 1 03/02/2024 03/02/2024 03/02/2024 03/02/2024 Submission, final submission date is on 05 April Gantt chart ID Tasks title Effort (Hour s)

W1 W2 W3 W4 W5 W6 W7 W8 W9 W

  1. Requirements Collection and Analysis

1.1 Visualize the similar assessment with its development history

3.1.1 Prepare wireframe 3.1.2 Make use case diagram and flowchart of the website 3.1.3 Prepare solution design document 3.2 Develop the broadcasting website

3.2.1 Review Design documentation 3.2.2 Set up development environment 3.2.3 Work on the project’s UI/UX 3.2.4 Website backend development 3.2.5 Set up a third client meeting 3.2.6 Collect additional requirement 3.2.7 Implement Additional requirements 3.3 Test the functionality of the website

3.3.1 UI of the system is tested along with the frontend 3.3.2 Performance of the website tested 3.3.3 Report analyzed of test results 3.4 Prototype Evaluation 3.4.1 Demonstration of the functional prototype in the third meeting 3.4.2 Working on the comments of the 2 nd client meeting 3.4.3 Signed off 3 rd^ client meeting 4 Iteration prototype design in second phase 4.1 Design updated 4.2 Prototype updated

4.3 Tested the updated features in the system 4.4 Review through meeting with the client 5 Presentation and assessment of the prototype

5.1 Gather and evaluate all supporting documentation 5.2 Show the client a working prototype of the system 5.3 Write the evaluation of the prototype 5.4 Write critical reflection draft 5.5 Write the final draft for evaluation document 5.5 Write the final draft of critical reflection document 5.6 Update the final drafts of section in e-Portfolio 5.7 Final Submission

Second Client Meeting

Third Client Meeting