The tasks, efforts, and timeline for a software development project, from reviewing the project proposal and gathering meta data, to designing the architecture, developing the system, testing, and deployment. The plan includes client interviews, requirement documentation, and user manual preparation.
Typology: Study Guides, Projects, Research
1 / 5
This page cannot be seen from the preview
Don't miss anything!




S. No Title Effort (Hours) Plan Start Date Plan End Date Actual Start Date Actual End Date Deliverables 1 Requirement Specification 28 1.1 Reviewing Project Proposal 2 11/14/2021 11/14/2021 Reviewing Proposal 1.2 Gathering Meta data from proposal and other resources 4 11/14/2021 11/14/2021 Data Collection 1.3 Reviewing similar products 10 11/15/2021 11/17/2021 Reviewing products 1.4 Preparing for Client interview 2 11/17/2021 11/17/2021 Preparing for interview 1.5 Client Interview-01 1 11/18/2021 11/18/2021 11/18/2021 11/18/2021 Functional and Nonfunctional requirement finalized 1.6 Adding client needs and suggestion 2 11/19/2021 11/19/2021 Adding client needs to the notes from interview 1.7 Preparing Requirement Document 5 11/20/2021 11/20/2021 Documenting 1.8 Client discussion and approval of the requirements 2 11/21/2021 11/21/2021 11/20/2021 11/20/2021 Verifying the requirement specification 2 Designing Architecture 19 2.1 Analyzing and defining the relation between data to develop the entities 3 11/22/2021 11/22/2021 Defining relation between entities 2.2 Designing the Data Flow of the system 4 11/22/2021 11/22/2021 Developing Data Flow 2.3 Designing the wireframe of the product
2.4 Preparing the interview slide 2 11/23/2021 11/23/2021 Interview slide 2.5 Presenting and approving the design specification Client interview - 02 1 11/24/2021 11/24/2021 11/24/2021 11/24/2021 Recording points 2.6 Documentation of the architecture and specification 4 11/25/2021 11/27/2021 Documentation 3 Developing the system 35 3.1 Developing the database 3 11/29/2021 11/29/2021 Working database 3.2 Building the backend 20 11/30/2021 12/6/2021 Working logic of system 3.3 Developing the frontend 12 12/7/2021 12/10/2021 Beautiful UI/UX 4 Testing 18 4.1 Checking and fixing bugs 6 12/11/2021 12/13/2021 Fixed bug from
system 4.2 Verifying functional and non-functional requirement 3 12/14/2021 12/15/2021 Analyzing the system 4.3 Testing the requirement functionality 4 12/16/2021 12/17/2021 Testing 4.4 Preparing the testing documentation 5 12/18/2021 12/18/2021 Documentation 5 Maintenance and Deployment
5.1 Reviewing from Client Client meeting 1 12/19/2021 12/19/2021 12/19/2021 12/19/2021 Approved system 5.2 Preparing and documenting the User manual 15 12/20/2021 12/25/2021 User guide 5.3 Setting up the servers and deployment 2 12/26/2021 12/26/2021 Working System 5.4 Agreement and Maintenance Contact 1 12/28/2021 12/28/2021 Agreement