Spring 2004 Systems Problem 9: Building and Testing a Competition System, Exercises of Aeronautical Engineering

A group assignment for students in a systems problem course during spring 2004. The objective is to build and test an aircraft and competition system over a two-week period. Students must submit weekly reports and participate in a validation and system acceptance review. Deliverables include build reports and system acceptance presentations.

Typology: Exercises

2011/2012

Uploaded on 07/22/2012

sehgal_98
sehgal_98 🇮🇳

4.8

(4)

121 documents

1 / 3

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Spring 2004
Systems Problem 9
Build I & II
Propulsion, Payload, Operations
Validation and System Acceptance
Handed out: Thursday, 15 April 2004
Answers due: Build I Report: Thursday, 22 April 2004, 5:00 p.m.
System Acceptance Presentation: Friday, 23 April 2004
Build II Report: Thursday 29 April 2004, 5:00 p.m.
Objectives
At the end of this systems problem you should be able to:
Implement and operate a system that you have designed and conceived completing the CDIO
process
Manage, record and report against planned manufacturing and testing plans and procedures.
Discussion
Time to build! You have now completed the conceptualization and design phases of your
competition system. Now it is time to implement your designs. You will have two (2) weeks to
build and test your aircraft and competition procedures. You will report weekly on your
progress. And you will participate in a validation and system acceptance review.
Assignment
This is a group assignment. Build and test your aircraft and competition system. A record of your
building and testing process and progress is required. Two (2) weekly reports are due for this
assignment. The first is due 5 p.m. Thursday 22 April 2004 and the second is due 5 p.m.
Thursday 29 April 2004. A pro forma for the weekly report contents will be provided in
Microsoft World format. Your weekly reports must be submitted in Microsoft Word format. A
validation and system acceptance review is also required. A pro forma for the system acceptance
review will be provided in Microsoft PowerPoint format. Validation and system acceptance
presentations will take place on Friday 23 April 2004. Sign up times for the validation and
system acceptance review will be posted.
Deliverables
Build Reports: A brief outline of the build report pro forma follows below:
1 of 3
docsity.com
pf3

Partial preview of the text

Download Spring 2004 Systems Problem 9: Building and Testing a Competition System and more Exercises Aeronautical Engineering in PDF only on Docsity!

Spring 2004

Systems Problem 9

Build I & II

Propulsion, Payload, Operations

Validation and System Acceptance

Handed out: Thursday, 15 April 2004 Answers due: Build I Report: Thursday, 22 April 2004, 5:00 p.m. System Acceptance Presentation: Friday, 23 April 2004 Build II Report: Thursday 29 April 2004, 5:00 p.m.

Objectives At the end of this systems problem you should be able to:

  • Implement and operate a system that you have designed and conceived completing the CDIO process
  • Manage, record and report against planned manufacturing and testing plans and procedures.

Discussion Time to build! You have now completed the conceptualization and design phases of your competition system. Now it is time to implement your designs. You will have two (2) weeks to build and test your aircraft and competition procedures. You will report weekly on your progress. And you will participate in a validation and system acceptance review.

Assignment This is a group assignment. Build and test your aircraft and competition system. A record of your building and testing process and progress is required. Two (2) weekly reports are due for this assignment. The first is due 5 p.m. Thursday 22 April 2004 and the second is due 5 p.m. Thursday 29 April 2004. A pro forma for the weekly report contents will be provided in Microsoft World format. Your weekly reports must be submitted in Microsoft Word format. A validation and system acceptance review is also required. A pro forma for the system acceptance review will be provided in Microsoft PowerPoint format. Validation and system acceptance presentations will take place on Friday 23 April 2004. Sign up times for the validation and system acceptance review will be posted.

Deliverables

Build Reports : A brief outline of the build report pro forma follows below:

1 of 3

I. Build: goals, manufacturing procedures, schedule, time estimates and actuals, status II. Test: goals, procedures, schedule, time estimates and actuals, status III. Training: goals, procedures, schedule, time estimates and actuals, status IV. System performance against predicted goals. Appendix A. Build Log B. Test Log

Validation and System Acceptance Review : Three or four slides are required for the system acceptance review. You are expected to present the predicted performance of your system, the configuration of your system (product, people, procedures). You must present a three view of your final aircraft design. You must document and justify any production changes that differ from your initial design.

Original: CPColeman, Spring 2001 Modified: GBarter, CEJohnson, PWYoung, CPColeman, Spring 2002 CPColeman, OdeWeck, PWYoung, JPixley, Spring 2003 CPColeman, Spring 2004