Project Management Key Concepts: APM PMQ Revision Pack, Exercises of Financial Management

A concise overview of key concepts in project management, programme management, and portfolio management. It covers essential topics such as project lifecycles, business cases, organizational roles, and stakeholder management. The material is structured into key points, making it useful for revision and quick reference. It also includes methods and procedures, communication strategies, and conflict management techniques, offering a comprehensive guide for project management professionals and students. This revision pack is designed to aid in understanding and applying project management principles effectively.

Typology: Exercises

2021/2022

Uploaded on 08/30/2025

lothar-matthaus-2
lothar-matthaus-2 🇬🇧

1 document

1 / 15

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Topic: Project Management
Key Points
Four generic processes applied
at each phase of the life-cycle:
- Starting or initiation process
- Defining and planning process
- Monitoring and control process
- Learning and closing process
Projects:
Timebound and unique – use
project management techniques
Deliver outputs
Capital funded
Uses a range of specialist skills
Risk aware – mitigate only high
priority risk
BAU:
Repetitive operations – uses
process management techniques
Uses outputs to deliver outcomes
and benefits
Revenue funded
Uses (one or two) functional skills
Risk averse – tend to mitigate all
risks
Topic: Programme Management
Key Points
A group of projects with
related business benefits
Aligned to an overall strategy
Benefits integrated during the life
of the programme
May be inter-project dependencies
Delivers outcomes
Benefits of Programme Mgt:
- Focus on strategic objectives
- Focus on transition management
(making outputs into outcomes)
- Focus on benefits management
- Manage inter project dependencies,
focus resource where it is needed most
- Risk and change handled at
strategic level
Programme Manager responsibilities:
- Planning and controlling
- Managing project interfaces
- Defining governance
- Managing the budget
- Resource management
- Managing communications, risks
and issues
Topic: Portfolio Management
Key Points
Analysis of projects and
programmes
Prioritisation and/or selection
of projects and programmes
Continued monitoring of the portfolio
Adjustment of the portfolio with
regard to current circumstances
Portfolios managed at different levels
(organisational, programme or
functional level)
The Green Zone: Getting going
Topic: Methods and Procedures
Key Points
Constructed around the
life-cycle - Beginning, middle, end
Need to be adapted to each project
context - not a “one size fits all”
Guidance rather than rules
Example Contents
- Process descriptions for each phase
- Inputs and outputs of the process
- Documentation guidelines and
templates
- Procedures for:
-Business case management
- Organisation structure
APM PMQ revision pack
- Planning
- Monitoring and control
- Risk
- Quality
- Change control
- Configuration management
- Issue management
Benefits
-Consistency of approach
- Improved governance
- Creates environment for continuous
improvement
- Common understanding and language
- Increased chance of projects succeeding
PRINCE2® is a method used globally
PRINCE2® is a registered trade mark of AXELOS Limited.
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff

Partial preview of the text

Download Project Management Key Concepts: APM PMQ Revision Pack and more Exercises Financial Management in PDF only on Docsity!

Topic: Project Management

Key Points

 Four generic processes applied at each phase of the life-cycle:

_- Starting or initiation process

  • Defining and planning process
  • Monitoring and control process
  • Learning and closing process_

Projects:  Timebound and unique – use project management techniques  Deliver outputs  Capital funded  Uses a range of specialist skills  Risk aware – mitigate only high priority risk BAU:  Repetitive operations – uses process management techniques  Uses outputs to deliver outcomes and benefits  Revenue funded  Uses (one or two) functional skills  Risk averse – tend to mitigate all risks

Topic: Programme Management

Key Points

 A group of projects with related business benefits  Aligned to an overall strategy  Benefits integrated during the life of the programme  May be inter-project dependencies  Delivers outcomes  Benefits of Programme Mgt:

_- Focus on strategic objectives

  • Focus on transition management_ _(making outputs into outcomes)
  • Focus on benefits management
  • Manage inter project dependencies,_ _focus resource where it is needed most
  • Risk and change handled at_ strategic level

 Programme Manager responsibilities:

_- Planning and controlling

  • Managing project interfaces
  • Defining governance
  • Managing the budget
  • Resource management
  • Managing communications, risks_ and issues

Topic: Portfolio Management

Key Points

 Analysis of projects and programmes  Prioritisation and/or selection of projects and programmes  Continued monitoring of the portfolio  Adjustment of the portfolio with regard to current circumstances  Portfolios managed at different levels (organisational, programme or functional level)

The Green Zone: Getting going

Topic: Methods and Procedures

Key Points

 Constructed around the life-cycle - Beginning, middle, end  Need to be adapted to each project context - not a “one size fits all”  Guidance rather than rules  Example Contents

_- Process descriptions for each phase

  • Inputs and outputs of the process
  • Documentation guidelines and_ templates
  • Procedures for:
    • Business case management - Organisation structure

APM PMQ revision pack

_- Planning

  • Monitoring and control
  • Risk
  • Quality
  • Change control
  • Configuration management
  • Issue management_  Benefits
  • _Consistency of approach
  • Improved governance
  • Creates environment for continuous improvement
  • Common understanding and language
  • Increased chance of projects succeeding_  PRINCE2®^ is a method used globally

PRINCE2® is a registered trade mark of AXELOS Limited.

Topic: Project Lifecycle

Key Points

 Project Lifecycle: Concept, Definition, Development, Handover & Closeout  Life cycles will differ across industries and business sectors  Structure and approach for progressively delivering the required outputs  Product life-cycle includes Operations and Termination  Extended Life-cycle includes Benefits Realisation which runs in parallel with first part of the Operations Phase  Benefits:

  • _Facilitates rolling wave planning
  • Ensures next phase of work is_ _understood
  • Better estimating (shorter durations)
  • Early identification of resource_ _and improved resource utilisation
  • Limits risk as risks in the short term_ can be accurately identified and mitigated - Funds allocated in “chunks” - Go/No Go decisions - Flexible to suit different industries/business sectors - Early phase success reinforces stakeholder commitment - Lessons learned can be applied to future phases

Topic: Business Case

Key Points

 Documents the justification  Cost vs Benefits  Provides basis upon which ongoing viability can be judged

 Typical content:

  • _Reason (the current situation)
  • Business options reviewed and the_ chosen option (to resolve the current _situation)
  • Benefits
  • Success Criteria
  • Constraints
  • Dependencies
  • Major risks
  • Issues
  • Investment Appraisal
  • Cost benefit analysis_

 Produced at the end of Concept  Updated during Definition  Reviewed for validity throughout Development  Benefits reviewed during Operations Phase

The Blue Zone: Background

APM PMQ revision pack

 Owned by Sponsor  Input/Information from PM, Users, Suppliers, Financial experts  Investment Appraisal

_- Payback Period

  • Discounted Cash Flow (DCF)
  • Net Present Value (NPV)
  • Internal Rate of Return (IRR)_

Topic: Project Environment

Key Points

 Refers to the environment within which a project is undertaken  Strategic goals  PESTLE  Pestle analysis can identify stakeholders, risks, issues, constraints, assumptions, areas of scope, key dependencies

Topic: Project Management Plan

Key Points

 What, Why, When, How, Where, Who, How much, What if, How good for a project  Written by Project Team  Read by the stakeholders. Owned by the Project Manager  Approved by the Sponsor

The Pink Zone: People and projects

APM PMQ revision pack

Topic: Organisation

Key Points

 Functional

- Advantages - Staff flexibility - Technical expertise - Peer learning - Career development - Communication _- Functional problems solving

  • Disadvantages_ - Remote from client - One project many PMs - Many points of contact - Function superiority - Inward looking - No overall responsibility - ‘Chinese Walls’ - Functional loyalty  Matrix - Advantages - Single point of contact - Global resources - Shared resources - Consistent “rules” - Tailoring to project - Rapid response to changes - Disadvantages - Resources conflict between function and projects. Double reporting (line and project management) - Conflicting loyalties - Career path: functional department or project? - Overloading of individuals - “Ring fencing” of preferred personnel  Project - Advantages - PM line authority - Strong ‘team’ identity - Goal oriented - Project skills - Disadvantages - Concurrent projects - Isolation - Development of functional skills - Continuity of employment - Group think - Expensive

Card 1 of 2

Topic: Stakeholder

Management

Key Points

 All those who have an interest or role in the project or are impacted by the project or can impact it  Identification (internal, external, direct, indirect)

 Identify area of interest (T, C, Q)  Assess Power/Interest, +/-  Plot on a grid  Decide on management actions  Prepare communications plan  Ongoing management (checking for changes to stakeholders, feedback on effectiveness)

INVOLVE/ ENGAGE

INVOLVE/ ENGAGE PARTNER

INFORM CONSULT CONSULT

INFORM INFORM CONSULT

HIGH

MEDIUM

LOW

LOW MEDIUM HIGH (^) POTENTIAL INTEREST

POTENTIAL INFLUENCE

The Pink Zone: People and projects

APM PMQ revision pack Card 2 of 2

Topic: Communication

Key Points

 Communications Media

_- Visual - Oral - Body language

  • Written - Electronic_  Screens or Barriers to Communication _- Perception
  • Level of education
  • Region of experience
  • Personality and interests
  • “Deaf ear” to unfamiliar or boring topics
  • Attitudes, emotions and prejudices
  • Receiver hearing what he wants to hear
  • Sender and receiver having different_ _perceptions
  • Receiver evaluates the source before_ _accepting the communication
  • Words meaning different things to_ different people  How To Improve Communication _- Obtain feedback
  • Establish multiple communication_ _channels
  • Use face to face if possible
  • Find out how sensitive the receiver is_ to your communication

Topic: Conflict

Management

Key Points

 Conflict over project priorities  Conflict over administrative procedures  Conflict over technical opinions and performance trade-offs  Conflict over manpower resources  Conflict over cost  Conflict over schedules  Personality conflict

Competing Collaborating

Avoiding

Compromising

Accommodating

Extent of attempts to satisfy other’s concerns

Extent of

attempts

to satisfy

own

concerns

 Conflict Management Process

_- Diagnose

  • Discuss
  • Achieve ownership
  • Agree
  • Reinforce
  • Remove (from the team)
  • Exit (from the organisation)_ - Communicate at the proper time - Use simple language - Say it in different ways  Communication Plan - Stakeholder list and contact details - Information required by each stakeholder (group) - Source of information - Format of information - Frequency of information - Method of distribution

Topic: Time Scheduling

Key Points

 Network diagrams

The Purple Zone: Planning

APM PMQ revision pack

Topic: Estimating

Key Points

 Subjective estimating  Comparative estimating  Parametric estimating  Bottom-up (analytical) estimating  3 Point Estimating

_- Lowest

  • Highest
  • Most Likely -_ PERT  Estimating Techniques _- Activity Breakdown
  • Experience
  • Phase Breakdown
  • Experts
  • Formulae
  • Statistics
  • Archives_

Topic: Scope Management

Key Points

 Product Breakdown Structure (PBS)  Work Breakdown Structure (WBS)  Basis of schedule  Advantages of Structures

_- Helps team think about the work

  • Gains agreement
  • Ensures all know what they are_ _supposed to do
  • Reduces risk of overlooking_ _something
  • Identifies deliverables
  • Makes workload allocation simpler
  • Relates costs to “cost centres”
  • Aids communication
  • Provides a numbering system
  • Provides basis for activity networks
  • Provides basis for Earned Value_ Analysis

 Critical Path – longest path through the network  Total float – the amount of slippage a task/path has before the end date is affected.  Free float the amount of time a task can slip without affecting the start of any subsequent task  Milestone Charts  Gantt Charts

Earliest start time

Latest start time

Earliest finish time

Duration

Latest finish time

Total float

Activity number/name

Topic: Resource Scheduling

Key Points

 Unlimited resources, fixed time

- Use Time-limited Scheduling - Known as Resource Smoothing  Limited resources, flexible time - Use Resource-limited Scheduling - Known as Resource levelling  Resource Histogram  Cumulative S Curve – basis of Earned Value – also known as Planned Cost

The Purple Zone: Planning

APM PMQ revision pack

Topic: Budgeting & Cost

Management

Key Points

 Prime costs  Overheads  Profit  Cost Breakdown Structure (CBS)

_- Labour

  • Materials
  • Plant and equipment
  • Subcontract
  • Management
  • Overhead and administration
  • Fees and taxation
  • Inflation
  • Other contingency
  • Allocate to a Cost Centre_  Commitment - Placement of order for work, money removed from the budget to represent the order  Accrual - Work done for which payment is due but not yet made  Actual expenditure - Monies already paid

 SPI/CPI greater than 1 - early or under budget  Efficiency = CPI x100%

Formulae CPI = EV/AC SPI = EV/PC CV = EV - AC SV = EV - PC Final Cost = BAC/CPI Final Duration = Planned Duration/SPI % complete = (EV/BAC) *

 Forecast out-turn costs _= Actual costs + Commitments

  • Accruals + Work not yet started_  Cost Commitment Profile

- Cumulative cost v cumulative revenue

Topic: Earned Value

Key Points

 Compares:

_- Planned Costs(PC) - What I planned to do

  • Actual Costs (AC)- What I paid
  • Earned Value (EV) - What I achieved_  Benefits of Earned Value _- How well are we doing?
  • How well will we do assuming that_ _factors continue?
  • How well could we do?
  • Identify areas of under achievement
  • Provides data for future estimates of_ _similar work
  • Development of standard curves to assist_ with target setting for future projects  Cost Variance (CV)  Schedule Variance (SV)  Cost Performance Index (CPI)  Schedule Performance Index (SPI)  SPI/CPI less than 1 - late or over budget

The Red Zone: Stop and think

APM PMQ revision pack

Topic: Project Success and

Benefits Management

Key Points

 Success Criteria - Specific

_- Time - Cost - Quality

  • Met customer’s requirements -_ _Acceptance Criteria
  • Business Case_  View from different perspectives - Customer - Supplier - Team - Others?  Success Factors _- Personal drive, motivation and leadership
  • Team motivation
  • Management support
  • Functional support
  • Client support and commitment
  • Project objectives
  • Financial resource
  • Communication and control
  • Technical expertise_  Key Performance Indicators - Measurable indicator for each success _criterion
  • Used to report progress
  • Chosen to reflect the success criteria
  • Clear and unambiguous_

 Benefits

- Identify benefits _- Stated by the users and/or the sponsor

  • Encapsulated in the Business Case_ - Can be positive or negative _- Can be tangible or intangible
  • Maintain and manage_ - Through the life-cycle - When things change - Realise - Usually after the project finishes - Business as usual activity

Topic: Negotiation

Key Points

 Preparation

_- Understand the issue/problem

  • Study relevant material
  • Learn about opponents’ objectives
  • Anticipate opponents’ strategies
  • Define own objectives and priorities
  • Define own negotiating strategy
  • Allocate roles and responsibilities_  Discussing  Listening  Proposing  Signalling  Conceding  Agreeing

Topic: Project Quality

Management

Key Points

 4 elements:

  • Quality Planning
  • Quality Assurance
  • Quality Control
  • Continuous Improvement  Acceptance Criteria  Techniques used in Control/Improvement

Minimum Cost

Cost

Low High

High Low

Number of Mistakes Standards

Cost of Control

Cost of Failure

_- Audits

  • Ishikawa diagrams (Cause & Effect_ _Analysis)
  • Pareto Analysis
  • Sampling
  • 100% testing
  • Inspection
  • Control Charts_  Cost of Quality

Card 1 of 2

The Red Zone: Stop and think

APM PMQ revision pack Card 2 of 2

Topic: Health & Safety

Key Points

 The main purposes of the Health & Safety At Work Etc. Act (1974)

- Secure the health, safety and welfare of _people at work

  • Protect others from risks arising from_ _activities of people at work
  • Control use and storage of dangerous_ _substances
  • Control atmospheric emission of noxious_ or offensive substances  The Employer’s General Duty of Care _- A safe place of work
  • Safe means of access and egress
  • Safe system of work
  • Safe appliances, equipment and plant
  • Competent and safety-conscious fellow_ _employees
  • Protection from unnecessary risk of injury_  Duties of Employers _- Publish a safety policy
  • Provide adequate instruction and training
  • Establish a safety committee if_ union-appointed health and safety representatives so request  Duties of Employees - While at work, all employees have a duty to: - take reasonable care - co-operate with employer

 HASAW Legislation Relevant to Projects Construction (Design & Management) Regulations These regulations and the Approved Code of Practice apply specifically to the construction industry. They apply if the work is greater than 30 days duration or require more that 500 person days and these projects must be reported to the HSE. The regulations also detail specific responsibilities for:

  • Client, Designer, CDM Coordinator, Principal Contractor, Contractors  The regulations require that a Health and Safety Plan is in place and a Health and Safety File should be kept which is handed to the client when the work is complete so that it can be referenced during the operational life of the products, for example, when maintenance work is being undertaken.  Risk assessment process _- Step 1: Identify the hazards
  • Step 2: Decide who might be harmed_ _and how
  • Step 3: Evaluate the risks and decide on_ precaution - Step 4: Record your findings and implement them - Step 5: Review your assessment and update if necessary A typical H&S plan should cover the following topics:  Introduction  Overview of the project and its health and safety context  Health, safety and environmental management - Details of how these matters will be addressed including any industry specific matters  Organisation - Who will take the specific roles such as CDM coordinator  Health and safety risk assessment - Details of the Risk assessment  Training - Details of how all staff and visitors will be trained  Auditing and Reporting - Details of how audits will be undertaken, their frequency and details of reporting arrangements (make specific reference to relevant industry standards)

Topic: Procurement

Key Points

 The Basic Steps

_- Establish user's need

  • Survey market place
  • Specify realistic requirement
  • Seek tenders for supply
  • Assess tenders and choose supplier
  • Accept goods into service
  • Support equipment during use
  • Decommission and dispose_  Acquisition Strategies _- Off the Shelf Buys
  • ‘Key’ Point Specifications
  • Partnering Arrangements
  • PPP, PFI_  Contract Types _- One comprehensive contract
  • Sequential contracts
  • Parallel contracts
  • Sub contracts
  • PPP, PFI_  Payment Arrangements _- Firm price/Fixed price
  • Target cost
  • Maximum price
  • Cost reimbursement
  • Unit rates
  • Mixed terms
  • Milestone payments/activity schedules_

The Orange Zone: Sunset

APM PMQ revision pack

Topic: Project Reviews

Key Points

 Stage Review (regularly throughout the project)

_- Evaluate the processes being used

  • Establish any lessons learned and_ _actions arising
  • Identify concerns and agree_ _corrective action
  • Establish likely technical success_ _of the project
  • Validate progress against time, cost,_ _quality, scope and resources
  • Consider stakeholder relationships_ and perceptions  Gate Reviews - Undertaken at the end of phase or _stage
  • Determines whether project should_ _proceed or not
  • Major decision point for senior_ management  Audits - Undertaken by group outside the team - Project Office - Internal auditors _- External auditors
  • Used to provide objective evaluation and assessment of the management of the project_  Post Project Review _- Part of handover, before closeout
  • Used to assess “did we do it right?”
  • Evaluate against success criteria
  • Determine what went well, what went badly, what could be done differently, separating cause from effect
  • Recognise individual and team performances
  • Evaluate the project processes and any tools or techniques used_  Benefits Realisation Review _- Undertaken some time after the products are in use
  • Perhaps more than one?
  • Have the benefits been realised?
  • Have any unexpected benefits been realised?
  • Any problems caused by the new products?
  • Responsibility of the sponsor_  Circulate reports of all reviews to key stakeholders

Topic: Information Management

Key Points

 Collection, Storage (analysis), Dissemination, Archive, Destruction  Written formal or informal  Oral formal or informal  Vertical/Horizontal  Manual filing systems  Project management and design software  Project meetings  Shared access to networked databases  Hard-copy document distribution  Fax and E-Mail  Video conferencing  Exception reports  Weekly reports  Monthly reports  Project closure reports  Project Report Structure

_- Schedule status - Cost status

  • Quality status - Risk status
  • Issue status_  Project Archiving _- A repository for historic records
  • Audit Trail
  • Important part of an organisation’s_ _forecasting and estimating capability
  • Project manager’s store of experience
  • Capture experience in a form usable by_ others

Topic: Handover and Closeout

Key Points

 Prepare a handover and closeout plan as part of the PMP  Final testing against acceptance criteria  Pass the deliverables to the sponsor and the user and obtain acceptance  Handover to operational maintenance and support and obtain acceptance  Prepare for benefits realisation and review  PM Responsibilities

- Dispose of surplus materials, _infrastructure and facilities

  • Finalise contracts and purchase orders
  • Finalise project accounts
  • Complete and archive all documentation
  • Undertake a post-project review
  • Operational review on the way the_ _project was managed
  • Create and distribute lessons learned_ _report
  • Complete performance appraisals of_ _project team staff as appropriate
  • Recognise individual and team_ performance

The Orange Zone: Sunset

APM PMQ revision pack

Topic: Handover and Closeout

Inform stakeholders of stage entry

Brief project team

Finalise release preparations

Prepare for project closure

Release decision

Release

Complete project work scope

Handover & closure of project

PROJECT CLOSED

END

Post Project Review

Guidance for learners

Use this study card in conjunction with the ILX APM PMQ podcasts. Study its contents and try to recall the key points under each section.

About this document...

This document is part of an ILX study pack. It has been designed to assist your study for the APM’s project management qualification examination. It forms part of comprehensive portfolio of materials designed by ILX Group to assist learners in their exam preparation.