S1 BOLTING QUESTIONS AND ANSWERS
According to the IBC, which of the following cases are exceptions to where special
inspections are required? - Answers- • Building components where a design
professional is not required
• Group U occupancies that are accessory to residential occupancy
• Work of a minor Nature
According to the IBC which is the first party the special inspector is to notify regarding a
discrepancy found during special inspection? - Answers- Contractor
Which of the following reference documents has report forms? - Answers- Model
program for special inspection
At completion of fabrication ________ shall submit a certificate of compliance to the
building official. - Answers- The approved fabricator
According to the code of Standard Practice for Buildings and Bridges, which party
performance material test of the structural steel for verification of material properties? -
Answers- Steel supplier
According to the Specification for Structural Steel Buildings, _____ would not apply to a
sample for a hot-rolled steel shapes - Answers- ASTM A53
Identification markings for structural steel shall conform to ____ standard specified and
they approve construction documents - Answers- ASTM
Identification markings for high-strength bolts, nuts, and washers shall conform
to_______ standards specified in the approved construction documents - Answers-
ASTM
Compressible-washer-type direct tension indicators shall meet the requirements of: -
Answers- ASTM
According to the Specification for Structural Joints, which of the following g is the
definition of a "faying surface" ? - Answers- The plane of contact between two piles of a
joint
According to the Specification for Structural Joints the _____ is an allowed method for
installing Pretensioned bolted joints - Answers- • Calibrated wrench method
• Turn of the nut method
• Twist off type tension control bolt pretensioning method
According to the Specification for Structural Joints, what method of installation is used
for high-strength bolted connections when Pretensioned joints are not needed? -
Answers- Snug tightened method
pf3
pf4
pf5

Partial preview of the text

Download S1 BOLTING QUESTIONS AND ANSWERS and more Exams Nursing in PDF only on Docsity!

S1 BOLTING QUESTIONS AND ANSWERS

According to the IBC, which of the following cases are exceptions to where special inspections are required? - Answers- • Building components where a design professional is not required

  • Group U occupancies that are accessory to residential occupancy
  • Work of a minor Nature According to the IBC which is the first party the special inspector is to notify regarding a discrepancy found during special inspection? - Answers- Contractor Which of the following reference documents has report forms? - Answers- Model program for special inspection At completion of fabrication ________ shall submit a certificate of compliance to the building official. - Answers- The approved fabricator According to the code of Standard Practice for Buildings and Bridges, which party performance material test of the structural steel for verification of material properties? - Answers- Steel supplier According to the Specification for Structural Steel Buildings, _____ would not apply to a sample for a hot-rolled steel shapes - Answers- ASTM A Identification markings for structural steel shall conform to ____ standard specified and they approve construction documents - Answers- ASTM Identification markings for high-strength bolts, nuts, and washers shall conform to_______ standards specified in the approved construction documents - Answers- ASTM Compressible-washer-type direct tension indicators shall meet the requirements of: - Answers- ASTM According to the Specification for Structural Joints, which of the following g is the definition of a "faying surface"? - Answers- The plane of contact between two piles of a joint According to the Specification for Structural Joints the _____ is an allowed method for installing Pretensioned bolted joints - Answers- • Calibrated wrench method
  • Turn of the nut method
  • Twist off type tension control bolt pretensioning method According to the Specification for Structural Joints, what method of installation is used for high-strength bolted connections when Pretensioned joints are not needed? - Answers- Snug tightened method

Given: a bolt length less than 4 times the bolt diameter where both faces of the joint are normal to the bolt axis. According to the Specification for Structural Joints, what is the required nut rotation beyond snug tight for the turn of the nut method of installation? - Answers- 1/3 turn According to the Specification for Structural Joints, the faying surfaces of ______ joints are important in the performance of the joint when stressed - Answers- Slip critical The special inspector shall perform an inspection of ______ to verify compliance with the details shown on the approved construction documents such as bracing, stiffening, member locations, and proper application of joint details at each location - Answers- The steel frame The special inspector need not to be continuously present the welding of: - Answers- Single-pass fillet welds not exceeding 5/16 inch in size According to the Specification for Structural Steel Buildings, the ________ identifies each primary structure was still a member, so it is placed in the correct location in the building. - Answers- Fabricator According to the Specification for Structural Joints, the nominal diameter of an oversized bolt hole for a 1- inch diameter bolt is _____ inches - Answers- 1 - 1/ According to the Specification for Structural Joints, what is the purpose of tension calibrator testing of the method of bolt installation used on the job site? - Answers- To verify the method of bolt installation has achieved the required bolt tension The Specifications for Structural Joints stars "the tightness that is attained with a few impacts of an impact wrench or the full effort of an iron worker using an ordinary spud wrench to bring the plies into firms contact" this is the description of which method of high-strength bolt installation? - Answers- Snug tight According to the Specification for Structural Joints _______ is the minimum bolt pretension required for an A325 bolt 1 1/4 inch in diameter - Answers- 71 kips According to the Specification for Structural joints, where the turn of the nut method of bolt installation is used, how often is a special inspector to observe the work as it progresses? - Answers- Periodically Thermally cut surfaces shall be ground smooth for: - Answers- Cyclically loaded joints Fasteners components that accumulate rust or dirt shall not be incorporated into the work unless they are: - Answers- Prequalified

According to the Specification for Structural Steel Buildings, what fabrication process is to be used on column ends for a compression joint that depends on contact bearing for transfer of load? - Answers- Milled ends According to the Specification for Structural Steel Buildings the document which includes the required dimensional tolerances for structural steel is the: - Answers- Code of Standard Practice for Steel Buildings and Bridges According to the Specification for Structural Steel Buildings, the special inspector can check an individual structural steel member to see that it is the proper one for a certain location in the building by viewing the: - Answers- The fabricators marking on the member which matches the location of that member on the shop drawings According to the AISC Steel Construction Manuel, which of the following is not an allowed manner for setting column base plates? - Answers- Treated hardwood shims According to the AISC Steel Construction Manual, the grout used between the column base plate and the foundation must be: - Answers- High-strength non-shrink What is the maximum steel temperature allowed to correct camber in an A514 structural steel beam - Answers- 1,100 F According to the Code of Standard Practice for Steel Buildings and Bridges, what party is to review the fabricator's ship and erection drawings? - Answers- Owner's representatives for design and construction According to the code of standard practice for steel building and bridges, the ________ must be approved before the fabrication of the structural steel begins. - Answers- Shop and erection drawings According to the code of standard practice for steel buildings and bridges ______ is the tolerance on the length of a floor beam that is less than 30 feet long - Answers- 1/ inch According to the code of standard practice _____ of the steel surface is required prior to shop painting - Answers- Wire brushing According to the code of standard practice for steel buildings and bridges the permitted method of applying shop paint is: - Answers- • Brushing

  • Rolling
  • Spraying According to the code of standard practice for steel buildings and bridges, the ______ is responsible for the temporary vertical and lateral supports necessary for the erection of the building framework - Answers- Steel erection contractor

Which section of the code of standard practice for steel buildings and bridges includes the permitted tolerances for detailed erection? - Answers- Section 7. According to the code of standard practice for steel buildings and bridges ______ are(is) allowed in moderate amounts for correction of errors during steel framing erection. - Answers- • Drifts Pins

  • Grinding
  • Reaming According to the code of standard practice for steel buildings and bridges, what types of openings for other trades are allowed to be cut in the structural steel - Answers- Only those openings shown on the contract document drawings and specifications. According to the AISC Steel Construction Manual, what should be done if grouting is delayed on a base plate supported by leveling nuts until after steel erection? - Answers- Use Steel shims to support base plate