Software Engineering: Multiple Choice Questions and Answers, Papers of Applications of Computer Sciences

It deals about Software project management concepts

Typology: Papers

2019/2020

Uploaded on 11/08/2020

tamil-selvi-1
tamil-selvi-1 šŸ‡®šŸ‡³

3 documents

1 / 26

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Dr.G.R.Damodaran College of Science
(Autonomous, affiliated to the Bharathiar University, recognized by the UGC)Re-accredited at the 'A' Grade Level by the NAAC and ISO
9001:2008 Certified
CRISL rated 'A' (TN) for MBA and MIB Programmes
II MCA (2018-2021 BATCH)
SEMESTER IV
CORE:SOFTWARE PROJECT MANAGEMENT-454A
Multiple Choice Questions.
1. A unique, planned, scheduled activity with one or more objectives referred as___
A. Project
B. Job
C. Process
D. Task
ANSWER: A
2. __________ formalizes acceptance and bnngs project to an orderly end.
A. planning.
B. closing process.
C. control process.
D. executing process.
ANSWER: B
3. The Stepwise Project Planning has 0-____ steps
A. 9
B. 10
C. 8
D. 11
ANSWER: B
4. Software systems are likely to be subject to a high degree of ________.
A. performance
B. change
C. time
D. strength
ANSWER: B
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a

Partial preview of the text

Download Software Engineering: Multiple Choice Questions and Answers and more Papers Applications of Computer Sciences in PDF only on Docsity!

Dr.G.R.Damodaran College of Science

(Autonomous, affiliated to the Bharathiar University, recognized by the UGC)Re-accredited at the 'A' Grade Level by the NAAC and ISO 9001:2008 Certified CRISL rated 'A' (TN) for MBA and MIB Programmes

II MCA (2018-2021 BATCH)

SEMESTER IV

CORE:SOFTWARE PROJECT MANAGEMENT-454A

Multiple Choice Questions.

  1. A unique, planned, scheduled activity with one or more objectives referred as___ A. Project B. Job C. Process D. Task ANSWER: A
  2. __________ formalizes acceptance and bnngs project to an orderly end. A. planning. B. closing process. C. control process. D. executing process. ANSWER: B
  3. The Stepwise Project Planning has 0-____ steps A. 9 B. 10 C. 8 D. 11 ANSWER: B
  4. Software systems are likely to be subject to a high degree of ________. A. performance B. change C. time D. strength ANSWER: B
  1. In ________ type of system, system interfaces with the machine. A. embedded B. stock control C. process control D. information ANSWER: A
  2. Projects may be distinguished by whether their aim is to produce a ________ or meet certain _______. A. product, objective B. product, tasks C. tasks, objective D. tasks and null objects ANSWER: A
  3. The first stage of the software project is a ________which results in a recommended course of action. A. system driven project B. software driven project C. hardware driven project D. objectives driven project ANSWER: D
  4. The second stage of software project is _________. A. to create software product B. to meet the objective C. to make up resources D. to close the project ANSWER: C
  5. In case of product-driven projects, the objectives of the project are defined in terms of ___________. A. functional requirements only B. resource and non-functional requirements C. functional and quality requirements D. resource requirements only ANSWER: C
  6. ________ defines what the end product of the project is to do. A. product perspective. B. Non-functional requirements. C. Quality requirements. D. Functional requirements. ANSWER: D
  1. __________ standards are needed so that various systems can communicate with each other. A. Hardware. B. Hardware and software. C. Software. D. Shareware ANSWER: B
  2. The organization as part of its monitoring and control policy may have a ________ programme in place which dictates that certain statistics have to be collected at various stages of a project. A. measurement. B. system. C. software. D. testing. ANSWER: A
  3. The products handed over to the clients at the end of projects are called as __________. A. software B. application program C. deliverables D. intermediate products ANSWER: C
  4. __________ is the result of an activity. A. Software. B. System. C. Control. D. Product. ANSWER: D
  5. Product description contains___________. A. name of the product B. form of the product C. quantity of the product D. both a and b ANSWER: D
  6. The relationship between program design and program specification can be portrayed in _________. A. PFD. B. DFD. C. PDF. D. DDF. ANSWER: A
  1. Which one of the following is NOT an agile method? A. SCRUM B. Extreme Programming (XP) C. DSDM D. Waterfall ANSWER: D
  2. Same generic fragment relates to more than _________ instance of the particular type of the product. A. one. B. two. C. three D. four ANSWER: A
  3. _________ is the amount of work that needs to be done. A. Effort. B. Energy. C. Capacity. D. Strength. ANSWER: A
  4. Project planning is an _________ process. A. continuous. B. iterative. C. time consuming. D. conventional ANSWER: B
  5. In order to carry out a successful strategic assessment of a potential project there should be strategic plan clearly defining the organization's _________. A. objectives. B. rules. C. conditions. D. ideas. ANSWER: A
  6. The standard way of evaluating the economic benefits of any projects is to carry out a ________ analysis. A. price-benefit. B. cost-benefit. C. cash flow. D. fund flow. ANSWER: B
  1. Number of interrelated activities can be organized in different ways are called ______. A. activity model. B. network model. C. hierarchical model. D. process model. ANSWER: D
  2. RAD is _______. A. Resource Application Development. B. Resource Allocation Development. C. Rapid Application Development. D. Rapid Action Development. ANSWER: C
  3. JAD is _________. A. J2EE Application Development. B. J2ME Allocation Development. C. J2SE Application Development. D. Joint Action Development. ANSWER: D
  4. The alternate name for Waterfall model is _________. A. two-shot. B. phase shot. C. three-phase. D. one-shot. ANSWER: D
  5. The first phase of waterfall model is ____________. A. analysis. B. feasibility Study. C. coding. D. user requirements. ANSWER: B
  6. The spiral model is originated by __________. A. B.W.Boehm. B. B.W.Williams. C. B.W.Britto. D. B.W.Hackman. ANSWER: A
  1. An Elaboration of Waterfall which stresses the necessity for validation activities is known as __________. A. extended Waterfall. B. iterative Model. C. V-Process model. D. spiral Model. ANSWER: C
  2. ________prototypes are used and discarded when the true development of the operational system is commenced. A. Evolutionary. B. Throw away. C. Operational. D. Real. ANSWER: B
  3. ______ is as when copies of input screens are shown to the users on a workstation, but the screens cannot actually be used. A. Simulation. B. Annealing. C. Mock-ups. D. RAD system. ANSWER: C
  4. Partial working model is classified as __________. A. vertical and horizontal. B. vertical and straight. C. bended and horizontal. D. elevated and horizontal. ANSWER: A
  5. The scope of the deliverables for an increment is rigidly constrained by an agreed deadline called as ____________. A. sand boxing. B. time boxing. C. time delaying. D. local delaying. ANSWER: B
  6. ______ would mean the change can be implemented without software development. A. One cost. B. Total cost. C. Zero cost. D. No cost. ANSWER: C
  1. The statement "Putting more people on a late job makes it later" is from _________. A. Brooks Law. B. Peters Law. C. Parkinson's Law. D. Brokers Law. ANSWER: A
  2. The statement "If a system does not have to reliable, it can meet any other objective" is from __________. A. Brooks Law. B. Peters Law. C. Parkinson's first Law. D. Weinberg's Zeroth Law. ANSWER: D
  3. KLOC indicates ___________. A. hundred lines of code. B. source lines of code. C. thousand lines of code. D. million lines of code. ANSWER: C
  4. Engineering practice to derive estimates of software development is called as ______. A. algorithmic model. B. software effort estimation technique. C. software extra estimation technique. D. Markov models. ANSWER: B
  5. The top-down approach is normally associated with _______ models. A. process. B. product. C. effort. D. parametric. ANSWER: D
  6. Effort = __________. A. system size x productivity rate. B. system size x KLOC. C. person in months / SLOC. D. person in months x productivity rate. ANSWER: A
  1. The estimator seeks out projects that have been completed and that have similar characteristics to the new project is called ____________. A. code based reasoning. B. case based reasoning. C. case based analysis. D. code based analysis. ANSWER: B
  2. UFP indicates ________. A. unused function points. B. unstructured function points. C. uniform function points. D. unadjusted function points. ANSWER: D
  3. Effort = c x sizek refers to. A. parametric Design. B. COCOMO model. C. organic mode. D. embedded Mode. ANSWER: B
  4. ________ is refined by Barry Boehm and his co-workers. A. COCOMO III B. COCOMO IV. C. COCOMO II. D. COCOMO I. ANSWER: C
  5. ________ the degree to which there is a large dispersed team as opposed to there being a small tightly knit team. A. Small cohesion. B. Team cohesion. C. Process maturity. D. Team maturity. ANSWER: B
  6. ______ is one of the objectives of activity planning. A. Designing. B. Detailed costing. C. Cooperation. D. Team work. ANSWER: B
  1. The time by which an activity may be delayed without affecting any subsequent activity is called _________. A. action float. B. terminal float. C. free float D. null float ANSWER: C
  2. The objective of ________ is to avoid or minimize the adverse effects of unforeseen events is called A. risk management. B. risk maintenance. C. risk taking. D. risky job. ANSWER: A
  3. A _________ is an event that might occur and if it occurs, create a problem for the successful completion of the project. A. planning. B. hazard. C. safety. D. start. ANSWER: B
  4. ________ = risk likelihood x risk impact. A. Risk estimate. B. Risk expenditure. C. Risk identification D. Risk exposure. ANSWER: D
  5. RRL is ________. A. risk reduction leverage. B. risk relax leverage. C. risk reading letter. D. risk resource letter. ANSWER: A
  6. WBS is known as A. Wealth Breaking Scheme B. Wealth Brokerage Scheme C. Work Breakdown Structure D. Work Breakup Structure ANSWER: C
  1. The impact of some risks can be transferred away from the project by _______. A. risk analysis. B. risk control. C. risk transfer. D. risk evaluation. ANSWER: C
  2. The shortest time in which we could expect to complete the activity, barring outright miracles called ________. A. Optimistic Time B. Pessimistic Time C. Most Likely Time D. Shortest Time ANSWER: A
  3. PERT combines three estimates of time and obtains a single expected duration is ____________. A. te B. tp C. tm D. ts ANSWER: A
  4. _________ is proportional to the difference between the optimistic and pessimistic estimates. A. Activity Regression B. Activity mean C. Activity Standard Deviation D. Activity Variance ANSWER: C
  5. The________ value in PERT is calculated for each node that has a target date. A. x value. B. y value. C. t value. D. z value. ANSWER: D
  6. _________ simulation is an alternate to PERT. A. Morris mano. B. Monte Carlo. C. Markov. D. Hidden Markov. ANSWER: B
  1. ______ is the selection of individuals in which the final shape of the project team is taken into account A. Independent building. B. Construction building. C. Team building. D. Recruitment. ANSWER: B
  2. To know whether a particular individual is available when required is known as _____. A. reliability. B. consistency. C. availability. D. portability. ANSWER: C
  3. Activity plans can be illustrated using _______. A. activity bar charts B. activity pie charts. C. activity ball charts D. activity flow charts ANSWER: A
  4. _________ represents expenditure that an organization incurs, which cannot be directly related. A. Under head B. Over head. C. Top head. D. Miscellaneous expenses ANSWER: B
  5. Cost schedule of an activity plan is represented by _________. A. ascending steps. B. descending steps. C. sequence of steps. D. reverse steps ANSWER: C
  6. ________ is the group to ensure the satisfactory progress of a project. A. Product board. B. Purpose board. C. Project board. D. Perfect board. ANSWER: C
  1. Check points of a project plan must be _____. A. regular. B. irregular. C. random D. fixed. ANSWER: A
  2. _______ is an activity bar chart indicating scheduled activity dates and durations frequently augmented with activity floats.. A. Bar chart. B. Ball chart. C. Slip Chart. D. Gantt chart ANSWER: D
  3. Gantt charts, Slip chars and Ball charts are under ___________ process. A. monitoring. B. verification. C. control. D. visualization. ANSWER: D
  4. _______ is the method of recording and displaying the way in which targets have changed throughout the duration of the project. A. Gantt chart. B. Bar chart. C. Timeline. D. Schedule. ANSWER: C
  5. The total value credited to a project at any point is known as _______. A. earned value. B. moral value. C. money value. D. recurred value ANSWER: A
  6. The priorities we might apply in deciding levels in monitoring is called as ______. A. deciding monitoring. B. monitoring. C. tracking. D. prioritized monitoring. ANSWER: D
  1. Generalization/Specialization is implemented in Object Oriented Programming as ______. A. polymorphism. B. inheritance. C. overloading. D. abstract. ANSWER: B
  2. ___________ are building a software product. A. Acquirere. B. Developers. C. Independent evaluators. D. All the above. ANSWER: B
  3. An ______ is a named property of a class that describes the object being modeled. A. method. B. constant. C. message. D. attribute. ANSWER: B
  4. A Class symbol in UML has ___ chambers. A. 4. B. 2. C. 5. D. 3. ANSWER: D
  5. _______ is a description of a set of objects that share the same attributes,operations, relationships, and semantics. A. Object. B. Class. C. Process. D. Instance ANSWER: B
  6. _______ will divide the domain of the task hierarchy in activity diagrams. A. Swim lane. B. Activity. C. Interface. D. Split. ANSWER: A
  1. _______ is the task/process which describes the way in which the actor interact the system. A. Class. B. Flow. C. Object. D. Use case. ANSWER: D
  2. Informing to the developer which bug to be fix first is called as A. Severity B. Priority C. Fix ability D. Traceability ANSWER: B
  3. A metric used to measure the characteristic of documentation and code called as A. Process metric B. Product Metric C. Test metrics D. None of the above ANSWER: B
  4. What are the Types of Integration Testing? A. Big Bang Testing B. Bottom Up Testing C. Top Down Testing D. All the above ANSWER: D
  5. Component Level is implemented using ________ software tools. A. client. B. server. C. middleware. D. peer. ANSWER: C
  6. Software testing which is done without planning and Documentation is known as A. adHoc Testing B. Unit Testing C. Regression testing D. Functional testing. ANSWER: A