Download Project Management: Earned Value Analysis and Change Control and more Study notes Computer Engineering and Programming in PDF only on Docsity!
TOPICS
MONITORING AND
CONTROL
CONTRACT MANAGEMENT
SPM UNIT 4
MONITORING AND
CONTROL
Responsibilities
Assessing progress
Checkpoints – predetermined times when
progress is checked
- (^) Event driven: check takes place when a particular event has been achieved
- (^) Time driven: date of the check is pre-determined Frequency of reporting The higher the management level, generally, the longer the gaps between checkpoints
Red/Amber/Green (RAG)
reporting
- (^) Identify key tasks
- (^) Break down into sub-tasks
- (^) Assess subtasks as:
Green – ‘on target’
Amber – ‘not on target but recoverable’
Red – ‘not on target and recoverable only
with difficulty’
- (^) Status of ‘critical’ tasks is particularly important
Gantt charts
Ball charts
Code and test module A Code and test module B Code and test module C 10/10/ 10/10/ 21/10/ 23/10/ 14/10/ 17/10/ 27/10/ 31/10/ 17/10/ 17/10/05 27/10/ 27/10/ Green: On time Red: Missed the target
The timeline Records the way targets have changd throughout the project
Earned value analysis
• Planned value (PV) or Budgeted cost
of work scheduled (BCWS) – original
estimate of the effort/cost to complete
a task (compare with idea of a ‘price’)
• Earned value (EV) or Budgeted cost of
work performed (BCWP) – total of PVs
for the work completed at this time
Earned value – an
example
- (^) Tasks
- (^) Specify module 5 days
- (^) Code module 8 days
- (^) Test module 6 days
- (^) At the beginning of day 20, PV = 19 days
- (^) If everything but testing completed, EV = 13 days
- (^) Schedule variance = EV-PV i.e. 13-19 = -
- (^) Schedule performance indicator (SPI) = EV/PV i.e 13/19 = 0.
Earned value chart with revised forecasts (AC) (PV) (EV)
Recipients of progress
reports
Progress report IT management Customer management Users Quality assurance Project team
Reporting in PRINCE
- (^) Project Initiation Document (PID)
- (^) End-stage assessment
- (^) Mid-stage assessment
- (^) Highlight report
- (^) Checkpoint report
- (^) Project closure report
Prioritizing monitoring
We might focus more on monitoring certain
types of activity e.g.
- (^) Critical path activities
- (^) Activities with no free float – if delayed
later dependent activities are delayed
- (^) Activities with less than a specified float
- (^) High risk activities
- (^) Activities using critical resources