Project Management: Earned Value Analysis and Change Control, Study notes of Computer Engineering and Programming

An in-depth understanding of earned value analysis (eva) and change control in project management. Topics include the timeline, cost monitoring, earned value calculation, and reporting. Additionally, it covers the acquisition of software from external suppliers and the tendering process, including different types of contracts and evaluation plans.

Typology: Study notes

2013/2014

Uploaded on 11/27/2014

jiyual.mustapha
jiyual.mustapha 🇮🇳

1 document

1 / 47

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
TOPICS
MONITORING AND
CONTROL
CONTRACT MANAGEMENT
SPM
UNIT 4
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff
pf12
pf13
pf14
pf15
pf16
pf17
pf18
pf19
pf1a
pf1b
pf1c
pf1d
pf1e
pf1f
pf20
pf21
pf22
pf23
pf24
pf25
pf26
pf27
pf28
pf29
pf2a
pf2b
pf2c
pf2d
pf2e
pf2f

Partial preview of the text

Download Project Management: Earned Value Analysis and Change Control and more Study notes Computer Engineering and Programming in PDF only on Docsity!

TOPICS

MONITORING AND

CONTROL

CONTRACT MANAGEMENT

SPM UNIT 4

MONITORING AND

CONTROL

Responsibilities

Assessing progress

Checkpoints – predetermined times when

progress is checked

  • (^) Event driven: check takes place when a particular event has been achieved
  • (^) Time driven: date of the check is pre-determined Frequency of reporting The higher the management level, generally, the longer the gaps between checkpoints

Red/Amber/Green (RAG)

reporting

  • (^) Identify key tasks
  • (^) Break down into sub-tasks
  • (^) Assess subtasks as:

Green – ‘on target’

Amber – ‘not on target but recoverable’

Red – ‘not on target and recoverable only

with difficulty’

  • (^) Status of ‘critical’ tasks is particularly important

Gantt charts

Ball charts

Code and test module A Code and test module B Code and test module C 10/10/ 10/10/ 21/10/ 23/10/ 14/10/ 17/10/ 27/10/ 31/10/ 17/10/ 17/10/05 27/10/ 27/10/ Green: On time Red: Missed the target

The timeline Records the way targets have changd throughout the project

Earned value analysis

• Planned value (PV) or Budgeted cost

of work scheduled (BCWS) – original

estimate of the effort/cost to complete

a task (compare with idea of a ‘price’)

• Earned value (EV) or Budgeted cost of

work performed (BCWP) – total of PVs

for the work completed at this time

Earned value – an

example

  • (^) Tasks
    • (^) Specify module 5 days
    • (^) Code module 8 days
    • (^) Test module 6 days
  • (^) At the beginning of day 20, PV = 19 days
  • (^) If everything but testing completed, EV = 13 days
  • (^) Schedule variance = EV-PV i.e. 13-19 = -
  • (^) Schedule performance indicator (SPI) = EV/PV i.e 13/19 = 0.

Earned value chart with revised forecasts (AC) (PV) (EV)

Recipients of progress

reports

Progress report IT management Customer management Users Quality assurance Project team

Reporting in PRINCE

  • (^) Project Initiation Document (PID)
  • (^) End-stage assessment
  • (^) Mid-stage assessment
  • (^) Highlight report
  • (^) Checkpoint report
  • (^) Project closure report

Prioritizing monitoring

We might focus more on monitoring certain

types of activity e.g.

  • (^) Critical path activities
  • (^) Activities with no free float – if delayed

later dependent activities are delayed

  • (^) Activities with less than a specified float
  • (^) High risk activities
  • (^) Activities using critical resources