Steam System Schematic - Process Plant Services - Exam, Exams of Process Engineering

Main points of this exam are: Steam System Schematic, Steam Boiler, Boiler Operation, Controlled, Dryness Factor, Pressure Drop, Blended, Evaporative Condenser, Velocity Pressure, Pipe Sizing Table

Typology: Exams

2012/2013

Uploaded on 04/10/2013

davdas900
davdas900 🇮🇳

4.6

(5)

110 documents

1 / 16

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Page 1 of 16
CORK INSTITUTE OF TECHNOLOGY
INSTITIÚID TEICNEOLAÍOCHTA CHORCAÍ
Semester 2 Examinations 2010/11
Module Title: Process Plant Services
Module Code: MECH8018
School: Mechanical Engineering.
Programme Title: Bachelor of Science in Process Plant Technology
Programme Code: EPPTE_8_Y4
External Examiner(s): Mr. P. Ryan, Mr. G. Reilly
Internal Examiner(s): Ms. Maria Cullinane (Section A)
Mr. Willie Bateman (Section B)
Instructions: Answer any 3 questions.
All questions carry equal marks.
Answer Section A and Section B in seperate answer books.
Duration: 2 hours.
Sitting: Summer 2011
Requirements for this examination:
Attachments to be provided, for student reference, with this exam paper.
1
Saturated Steam - Pressure Table
Q1
(with paper)
2
Steam Pipeline Sizing Chart Pressure Drop
Q1
(with paper)
3
Pressure Enthalpy Chart R22
Q2
(with paper)
4
Pressure Enthalpy Chart R717
Q2
(with paper)
5
Vapour Pressure V’s Water Temperature.
Q3+4
(with paper)
6
Lowara Pump Data Sheet 04236D
Q3
(with paper)
7
CIBSE Velocity pressure loss factors (2 pages)
Q3+4
(with paper)
8
CIBSE Pipe Sizing Table
Medium Grade Steel Water at 80 C (2 pages)
Q3+4
(with paper)
Note to Candidates: Please check the Programme Title and the Module Title to ensure that you have received the
correct examination paper.
If in doubt please contact an Invigilator.
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff

Partial preview of the text

Download Steam System Schematic - Process Plant Services - Exam and more Exams Process Engineering in PDF only on Docsity!

CORK INSTITUTE OF TECHNOLOGY

INSTITIÚID TEICNEOLAÍOCHTA CHORCAÍ

Semester 2 Examinations 2010/

Module Title: Process Plant Services

Module Code: MECH

School: Mechanical Engineering.

Programme Title: Bachelor of Science in Process Plant Technology

Programme Code: EPPTE_8_Y

External Examiner(s): Mr. P. Ryan, Mr. G. Reilly

Internal Examiner(s): Ms. Maria Cullinane (Section A) Mr. Willie Bateman (Section B)

Instructions: Answer any 3 questions. All questions carry equal marks. Answer Section A and Section B in seperate answer books.

Duration: 2 hours.

Sitting: Summer 2011

Requirements for this examination: Attachments to be provided, for student reference, with this exam paper. 1 Saturated Steam - Pressure Table Q1 (with paper) 2 Steam Pipeline Sizing Chart – Pressure Drop Q1 (with paper) 3 Pressure Enthalpy Chart R22 Q2 (with paper) 4 Pressure Enthalpy Chart R717 Q2 (with paper) 5 Vapour Pressure V’s Water Temperature. Q3+4 (with paper) 6 Lowara Pump Data Sheet 04236D Q3 (with paper) 7 CIBSE Velocity pressure loss factors (2 pages) Q3+4 (with paper) 8 CIBSE Pipe Sizing Table

  • Medium Grade Steel Water at 80 C (2 pages)

Q3+4 (with paper)

Note to Candidates: Please check the Programme Title and the Module Title to ensure that you have received the correct examination paper. If in doubt please contact an Invigilator.

Section A – Steam & Refrigeration

Q1 a) Sketch and label a basic steam system schematic [3 Marks]

b) Why does TDS build up inside a steam boiler? What negative effects can high TDS have on boiler operation? How are TDS levels controlled within a steam boiler? [5 marks]

c) Calculate the size (tonnes/hour) of boiler required to heat a 25m^3 tank of water from 10oC to 70 oC in 1 hour. The boiler will be located 165m from the water tank and will run at 8 bar gauge. Assume that the steam is 90% dry. The specific heat capacity of water is 4.18kJ/kgK. The maximum permissible pressure drop for the steam line is 0.3bar/100m. Size the pipe-work needed to supply the required steam. [12 Marks]

Additional information:

Q E  mCp  T

Actual hfg = (dryness factor) x hfg Add 10% additional length to pipe lengths over 100m to allow losses due to pressure drop. Allow 3.5% steam losses per 100m of pipe length due to heat losses and condensation.

L = 165m

Section B – Pipe work systems.

Q3 a) The following diagram shows an open tank positioned below the suction of the pump. Determine if the pump shown will cavitate under the operating conditions shown. Show all calculations. [14 marks]

All valves are globe valves

0.4 m

Q = 9000 Lit/hr

4.2 m 1.8 m

Water 80 Deg

PG

Pump Details Lowara HTF4 32- Data Sheet 04236D

3.0 m

1.0 m

Pressure Gauge Reading 0.5 Bar g vacuum

vessel to pump

Steel Pipe connecting

Welded mild steel elbows

b) As the designer of an unspecified pumping system, your calculations have shown that cavitation is likely to occur at the suction of the pump. List and explain four possible actions you could suggest to reduce the likelihood of cavitation. [6 marks]

Reference - Vapour Pressure V’s Water Temperature. Q3+4 (with paper) Lowara Pump Data Sheet 04236D Q3 (with paper) CIBSE Velocity pressure loss factors (2 pages) Q3+4 (with paper) CIBSE Pipe Sizing Table

  • Medium Grade Steel Water at 80 C (2 pages)

Q3+4 (with paper)

Q4 A pump and pipe work is required to transfer 90000 l/h of water to one of three points on T1003, T2002 or T3007. Only one route is enabled at any one time. The pipe work is stainless steel. However no CIBSE pipe sizing tables exist for stainless steel. Then use CIBSE pipe sizing tables for medium grade steel pipes and fittings. Use all welded joints. (a) Which of the three possible routes will be the index run. Justify your selection by comparing the relevant factors that contribute to the total pressure drop along each run. [4 marks] (b) Estimate the pipe diameter for each section of pipe. [2 marks] (c) Specify overall flow and pressure requirements for the pump. [14 marks]

CIP SYSTEM PIPE SIZING EXERCISE

4,2 m

3,2 m

NOTES

of 3m/s for CIP systems.

To facilitate agressive washing of pipes + PHE use a target water flow

at inlet to spay ball

CIP spray ball T residual pressure of 1 bar

Use CIBSE Charts for Mild Steel

No CIBSE Charts for SS.

on all pipe runs.

Stainless Steel Pipe work

at any one time A. T1003 CIP nozzle. B. T2002 CIP nozzle. C. T3007 Spray Ball.

Only one route in use

Pumped Volume Q=90,000 l/h Water at 80 Deg C

i.e from pump to one of

on all pipe runs

All valves are actuated globe valves

also welded mild steel elbows

i.e. assume mild steel pipe work

at inlet to nozzle.

residual pressure of 3 bar

CIP nozzles T1003, T

at inlet to nozzle.

residual press of 1 bar

Tank 3007 CIP spray ball

at inlet to nozzle.

residual press of 3 bar

Tank 2002 CIP nozzle

at inlet to nozzle.

residual pressure of 3 bar

Tank 1003 CIP nozzle

0,4 m

(^) 2,2 m

0,4 m

0,4 m

3rd Floor^ Tank 3007

2nd Floor Tank 2002

1st Floor Tank 1003

Ground Floor

Tank G

3 m

3 m

2,7 m

P.H.E

1 m 1 m

Floor Drain

dP 1.1 Bar

Outlet

Cond Steam Inlet

1 m

Water

Reference - Vapour Pressure V’s Water Temperature. Q3+4 (with paper) CIBSE Velocity pressure loss factors (2 pages) Q3+4 (with paper) CIBSE Pipe Sizing Table – Medium Grade Steel Water at 80 C Q3+4 (with paper)