Download Understanding S-Curves in Technology Management: Project Progress Analysis and more Exercises Project Management in PDF only on Docsity!
Technology Management Students Notes
TM Tools - S Curve
Prof. Dr. Muhammad Anwar-ur-Rehman Pasha Rector IT-hub, Sargodha
Definition
• a display of cumulative costs, labour hours or
other quantities plotted against time. The
name derives from the S-like shape of the
curve, flatter at the beginning and end and
steeper in the middle, which is typical of most
projects.
• The beginning represents a slow, deliberate
but accelerating start, while the end
represents a deceleration as the work runs out
S-Curve Quantities
• Man Hours
• Costs
S Curve Quantity Units
• Absolute Values for man hours and / or costs
• Percentage Values for man hours and / or costs
The Baseline S Curve
Prior to project commencement, a schedule is prepared outlining the proposed allocation of resources and the timing of tasks necessary to complete the project within a set time frame and budget. This schedule is referred to as the Baseline Schedule.
What Is The Cut Off Date?
• The Cut Off Date is the date on which the
tasks were physically inspected to determine
their percentage complete values.
Example of Actual S Curves Using
Different Cut Off Dates
Percentage Man Hours versus Time
(Baseline = 100%) S Curves
Percentage Man Hours versus Time
(Target = 100%) S Curves
Calculating Project Progress
- Analysis of the above S Curves reveals the project as of
the 3rd^ of May 2012:
- Has grown in man hours by 5.56% (105.56 – 100.00)
- Has grown in duration by 1 day (6 days – 5 days)
Slippage
• Slippage is defined as " the amount of time a
task has been delayed from its original
baseline schedule. The slippage is the
difference between the scheduled start or
finish date for a task and the baseline start or
finish date. Slippage can occur when a
baseline plan is set and the actual dates
subsequently entered for tasks are later than
the baseline dates or the actual durations are
longer than the baseline schedule durations ".
S Curve Analysis
- The progress of the project is behind target. The Actual S Curve sits below the Target S Curve at the Cut Off Date.
- The project has grown in man hours. The Target S Curve finishes above the Baseline S Curve.
- The project has grown in duration. The Target S Curve duration is longer than the Baseline S Curve duration.
- The project has experienced start slippage, and thus started later than planned. The Target S Curve starts to the right of the Baseline S Curve.
- The project has experienced finish slippage, and thus will finish later than planned. The Target S Curve finishes to the right of the Baseline S Curve
Project Progress
Actual % Complete =
Actual YTD Man Hours @ Cut Off Date / Target Man
Hours x 100%
= 38.0 / 95.0 x 100%
Target % Complete =
Target YTD Man Hours @ Cut Off Date / Target Man
Hours x 100%
= 48.5 / 95.0 x 100%
Project Growth (Duration)
Analysis of the Baseline and Target S Curve data reveals the project has experience a growth in duration of 1 day, or 20.00% as compared to the Baseline Schedule.
Project Growth (Duration) = Target Duration - Baseline Duration = 6 days – 5 days = 1 day
Project % Growth (Duration) = ((Target Duration / Baseline Duration) - 1) x 100% = ((6 days / 5 days) - 1) x 100% = 20.00%
Project Start Slippage
Analysis of the Baseline and Target S Curve data reveals the project has a start slippage of 1 day, or 20.00% as compared to the Baseline Schedule.
Start Slippage = Target Start Date – Baseline
=Start Date1st^ May 2012 – 30 th^ April 2012 =1 day
Start Slippage % = Start Slippage / Baseline Duration x 100%
=1 day / 5 days x 100% = 20.00%