Understanding Work Breakdown Structures and Schedules in Project Management, Lecture notes of History

The concept of Work Breakdown Structures (WBS) and schedules in project management. WBS identifies tasks and deliverables associated with a project, facilitates budgeting, and helps determine the critical path and create the project schedule. Schedules are created from the WBS to ensure the project's objective is accomplished within the given time frame. Tools like Microsoft Project and methods such as Critical Path Method and PERT are used in conjunction with WBS and schedules.

Typology: Lecture notes

2021/2022

Uploaded on 09/27/2022

lakshmirnarman
lakshmirnarman 🇺🇸

5

(5)

221 documents

1 / 6

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Work Breakdown Structure & Schedules
WBS & Schedules.doc Page 1 of 6 V 0.0
A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a
project. Resources are identified for each item within the WBS that facilitates budgeting
as well as assignment of responsibilities. T he WBS can be used to determine the critical
path of the project and create the project schedule.
Project activities in which WBS and schedules are useful:
Drafts are created during the project definition phase of the project then details
are flushed out during the planning phase. The WBS and schedules are
continuously revisited and updated through the duration of the project.
Other tools that are useful in conjunction with WBS and schedules:
CMT (Critical Path Method)
PERT (Program Evaluation and Review Technique)
Risk Management
Aids
Microsoft Project™
Introduction
The WBS is the tool that is used to record and communicate the project deliverables
(something produced or an outcome) and sub-deliverables as well as the
accomplishments (something achieved) and sub-accomplishments. The identification of
these elements relies on the experience of the team members as well as consultation with
outside experts. Once the deliverables and accomplishments are listed, resources are
determined for each element and sub-element.
A schedule is created from the WBS to ensure the project’s objective is accomplished in
the time allotted. The first step in creating a schedule is an assessment of the critical path
or the shortest period in which the project can be completed. Once the critical path has
been established, start and end dates are assigned based on their relationship to the
critical path.
Application of WBS and Schedules
Work Breakdown Structure
The first step in creating a WBS is identifying the
project deliverables and sub-deliverables, and the
achievements and sub-achievements. Each
deliverable or achievement must equal the sum of its
sub-elements. The WBS can be represented either
1. Table Designed
1.1 Dimensions determined
1.2 Drawings completed
2. Materials Obtained
2.1 Material calculated
2.2 Materials purchased
3. Table Constructed
3.1 Parts prepared
3.1.1 Top cut to size
3.1.2 Legs turned
3.1.3 Parts assembled
4. Table Finished
4.1 Table sanded
4.2 Table stained
5. Table installed
pf3
pf4
pf5

Partial preview of the text

Download Understanding Work Breakdown Structures and Schedules in Project Management and more Lecture notes History in PDF only on Docsity!

A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a

project. Resources are identified for each item within the WBS that facilitates budgeting

as well as assignment of responsibilities. T he WBS can be used to determine the critical

path of the project and create the project schedule.

Project activities in which WBS and schedules are useful:

☛ Drafts are created during the project definition phase of the project then details

are flushed out during the planning phase. The WBS and schedules are

continuously revisited and updated through the duration of the project.

Other tools that are useful in conjunction with WBS and schedules:

☛ CMT (Critical Path Method)

☛ PERT (Program Evaluation and Review Technique)

☛ Risk Management

Aids

☛ Microsoft Project™

Introduction

The WBS is the tool that is used to record and communicate the project deliverables

(something produced or an outcome) and sub-deliverables as well as the

accomplishments (something achieved) and sub-accomplishments. The identification of

these elements relies on the experience of the team members as well as consultation with

outside experts. Once the deliverables and accomplishments are listed, resources are

determined for each element and sub-element.

A schedule is created from the WBS to ensure the project’s objective is accomplished in

the time allotted. The first step in creating a schedule is an assessment of the critical path

or the shortest period in which the project can be completed. Once the critical path has

been established, start and end dates are assigned based on their relationship to the

critical path.

Application of WBS and Schedules

Work Breakdown Structure

The first step in creating a WBS is identifying the

project deliverables and sub-deliverables, and the

achievements and sub-achievements. Each

deliverable or achievement must equal the sum of its

sub-elements. The WBS can be represented either

1. Table Designed 1.1 Dimensions determined 1.2 Drawings completed 2. Materials Obtained 2.1 Material calculated 2.2 Materials purchased 3. Table Constructed 3.1 Parts prepared 3.1.1 Top cut to size 3.1.2 Legs turned 3.1.3 Parts assembled 4. Table Finished 4.1 Table sanded 4.2 Table stained 5. Table installed

as a list or graphically. Figures 1 and 2 provide examples of a WBS for the building of a

table.

Once the elements of the WBS have been defined, resource requirements are determined

for each element. The resources to be identified include:

  • Human resources identified as the type of knowledge or skills required
  • Equipment resources
  • Materials and supplies
  • Space and facility requirements
  • Special requirements (e.g., not typical energy sources)

For each resource, the type, amount or effort (e.g., number of person hours), and

associated costs are determined and recorded in the WBS.

Table Designed

Table Built

Dimensions Determined

Drawings Completed

Materials Obtained

Table Constructed

Table Finished

Table Installed

Parts Prepared

Parts Assembled

Materials Calculated

Materials Purchased

Top Cut to Size

Legs Turned

Table Sanded

Table Stained

Figure 1: WBS List Format

Figure 2: WBS Chart Format

If desired, create a Gantt chart to graphically represent the schedule. A Gantt chart uses

horizontal bars in a linear-type calendar. Figure 4 provides an example of a schedule.

Work Breakdown Structure & Schedules

WBS & Schedules.doc

Page 5 of 6

V 0.

Task

Start

Finish

Effort(days)

Responsibility

Precedence

Dimensions determined

Nov 1

Nov 2

John S.

Drawings completed

1

Nov 3

Nov 9

Alana B.

Materials determined

Nov 10

Nov 10

John S.

Materials purchased

2,

Nov 12

Dec 12

John S.

3.1.1 Top cut to size

Dec 13

Dec 14

Andrew F.

3.1.2 Legs turned

Dec 13

Dec 16

Karen P.

Parts assembled

4

Dec 17

Dec 21

Andrew F.

Table sanded

5

Dec 21

Jan 2

Andrew F.

Table stained

4

Jan 3

Jan 5

Andrew F.

Table installed

Jan 6

Jan 6

Stewart B.

Figure 4: Example Schedule & Gantt Chart Notes:1.

Turn around time within the drafting department has been included although the effort is only 1 day.

A one month lead-time allotted for materials.

Remembrance Day (November 11) not included in schedule as it is a holiday.

Time allowed for glue and stain to dry.

Time allotted for shop closure due to Christmas holiday.

Nov

Dec

Jan

|^

|^

|^

|^

|^

|^

|^

|^

|^