Approaches to Developing Network Schedules, Exams of Advanced Education

Approaches to Developing Network Schedules

Typology: Exams

2025/2026

Available from 05/02/2026

lectben
lectben 🇺🇸

5

(1)

7.7K documents

1 / 1

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Approaches to Developing Network
Schedules
What are the three different approaches to developing network schedules? -
CORRECT ANSWER ✔✔✔ Program Evaluation and Review Technique (PERT), Arrow
Diagramming Method (ADM), and Precedence Diagram Method (PDM).
What is a key characteristic of the Arrow Diagramming Method (ADM)? - CORRECT
ANSWER ✔✔✔ ADM uses only a single duration estimate, which is the planned
duration for the activity under normal conditions.
How do PERT and ADM represent activities in network diagrams? - CORRECT
ANSWER ✔✔✔ Both PERT and ADM are 'activity-on-arrow' (AOA) methods, where
activities are shown as lines/arrows between events.
What type of relationship do PERT and ADM treat all activities as? - CORRECT
ANSWER ✔✔✔ They treat all relationships as 'finish-to-start,' meaning activity B
cannot start until activity A is complete.
Why is the use of PERT and ADM limited? - CORRECT ANSWER ✔✔✔ The limited
use of both PERT and ADM is directly related to the increase of computer-based
scheduling tools.
What does the duration estimate in PERT approximate? - CORRECT ANSWER ✔✔✔
The duration estimate in PERT approximates the 'most likely' duration for the
activity.
Is ADM commonly used in modern scheduling? - CORRECT ANSWER ✔✔✔ Similar to
PERT, ADM is seldom used in modern scheduling.

Partial preview of the text

Download Approaches to Developing Network Schedules and more Exams Advanced Education in PDF only on Docsity!

Approaches to Developing Network

Schedules

What are the three different approaches to developing network schedules? - CORRECT ANSWER ✔✔✔ Program Evaluation and Review Technique (PERT), Arrow Diagramming Method (ADM), and Precedence Diagram Method (PDM). What is a key characteristic of the Arrow Diagramming Method (ADM)? - CORRECT ANSWER ✔✔✔ ADM uses only a single duration estimate, which is the planned duration for the activity under normal conditions. How do PERT and ADM represent activities in network diagrams? - CORRECT ANSWER ✔✔✔ Both PERT and ADM are 'activity-on-arrow' (AOA) methods, where activities are shown as lines/arrows between events. What type of relationship do PERT and ADM treat all activities as? - CORRECT ANSWER ✔✔✔ They treat all relationships as 'finish-to-start,' meaning activity B cannot start until activity A is complete. Why is the use of PERT and ADM limited? - CORRECT ANSWER ✔✔✔ The limited use of both PERT and ADM is directly related to the increase of computer-based scheduling tools. What does the duration estimate in PERT approximate? - CORRECT ANSWER ✔✔✔ The duration estimate in PERT approximates the 'most likely' duration for the activity. Is ADM commonly used in modern scheduling? - CORRECT ANSWER ✔✔✔ Similar to PERT, ADM is seldom used in modern scheduling.