Advanced Crane & Rigging Test, Exams of Nursing

A wide range of topics related to crane and rigging operations, including lift planning, electrical hazards, crane capacities, multiple crane lifts, sling and rigging hardware, personnel lifting, and various safety considerations. It provides detailed information and answers to specific questions on these subjects, making it a valuable resource for crane operators, riggers, and safety professionals. The document delves into the methodical process of identifying and mitigating hazards, the importance of proper rigging and load calculations, and the regulatory requirements governing crane and rigging operations. By studying this document, readers can gain a comprehensive understanding of the best practices and critical factors to consider when planning and executing complex crane and rigging tasks, ensuring the safety and efficiency of these operations.

Typology: Exams

2023/2024

Available from 07/04/2024

rosze-macharia
rosze-macharia 🇬🇧

4.4

(7)

11K documents

1 / 6

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Advanced Crane & Rigging Test
When should an approved lift plan be re-approved? - Answer D. If there is any deviation
from the original lift plan.
Electrical hazards in the lift area and swing direction and degree are factors to consider
in preparing which portion of a lift plan? - Answer D. Crane Placement
Capacities for crawler cranes that have outrigger extensions may not exceed ________.
- Answer D. 85 perfect of tipping
When planning a lift involving two cranes, calculate the lowest net capacities that both
cranes will have during the lift. The next step is to ______. - Answer A. Make sure that
the sum of the lowest rated net capacities of the cranes exceeds the load weight.
A lift plan should be discussed ______. - Answer D. At a pre-lift meeting where all
personnel in the lift are present.
What is meant by the term "two blocking?" - Answer B. The load block contacts the
boom point sheaves
Lifting 20,000 lbs with a 2-leg bridle sling at a 30° horizontal sling angle, what is the
force applied to each leg? - Answer 20,000 lbs.
In multiple crane lifts using an equalizer beam, the weight of the beam should be
considered: - Answer Part of the load weight
What is required if there is deviation from the lift plan? - Answer A new lift plan
On level ground using skids and rollers, what percent of the weigh of the load should
yield the required line pull as a general rule of thumb? - Answer 5%
All of the following are results of unbalanced reeving of the block except: - Answer Wear
on the hook
Before a spreader bar or beams can be used they MUST have been: - Answer Tested
and approved
pf3
pf4
pf5

Partial preview of the text

Download Advanced Crane & Rigging Test and more Exams Nursing in PDF only on Docsity!

Advanced Crane & Rigging Test

When should an approved lift plan be re-approved? - Answer D. If there is any deviation from the original lift plan. Electrical hazards in the lift area and swing direction and degree are factors to consider in preparing which portion of a lift plan? - Answer D. Crane Placement Capacities for crawler cranes that have outrigger extensions may not exceed ________.

  • Answer D. 85 perfect of tipping When planning a lift involving two cranes, calculate the lowest net capacities that both cranes will have during the lift. The next step is to ______. - Answer A. Make sure that the sum of the lowest rated net capacities of the cranes exceeds the load weight. A lift plan should be discussed ______. - Answer D. At a pre-lift meeting where all personnel in the lift are present. What is meant by the term "two blocking?" - Answer B. The load block contacts the boom point sheaves Lifting 20,000 lbs with a 2-leg bridle sling at a 30° horizontal sling angle, what is the force applied to each leg? - Answer 20,000 lbs. In multiple crane lifts using an equalizer beam, the weight of the beam should be considered: - Answer Part of the load weight What is required if there is deviation from the lift plan? - Answer A new lift plan On level ground using skids and rollers, what percent of the weigh of the load should yield the required line pull as a general rule of thumb? - Answer 5% All of the following are results of unbalanced reeving of the block except: - Answer Wear on the hook Before a spreader bar or beams can be used they MUST have been: - Answer Tested and approved

When materials are being hoisted to an upper level, a tag line is used to: - Answer Help control the load Two cranes are lifting 100 tons. If crane A has 40% of the load, how much weight will crane B have on its hook? - Answer 120,000 lbs To confirm the rated capacity of a specific sling, consult the manufacturer's: - Answer Sling tag OSHA regulations require hook replacement if the opening exceeds what percentage of it's original throat opening? - Answer 15% At what percentage of increase in length should a chain sling be removed from service?

  • Answer 5% The methodical process that attempts to identify hazards and devise plans to overcome or eliminate hazards which may interfere with crane or rigging is called: - Answer Lift plan What provides additional control of a load being lifted? - Answer Tag lines When travelling on a rubber tire mobile crane, how should the boom be positioned? - Answer In line with the direction of travel. Before performing pick and carry operations with any mobile crane, it is important to: - Answer Refer to the manufacturer's capacity chart. According to ASME B30.5, a two crane lift is signaled by: - Answer One designated person What is the primary concern when working with a high boom angle? - Answer Backward stability ON multiple crane lifts, the load on each crane should NOT exceed what percentage of capacity? - Answer 75% What are lifting lugs? - Answer Eyelets welded to steel plate for lifting. The formula for determining stress on a snatch block performing a vertical lift is: line pull x block factor = block load. What must be done to calculate the formula? - Answer Multiply the load weight by the coefficient of friction to determine line pull, and then use the standard formula. If both fists are placed in front of your body with your thumbs pointed outward, the crane operator should: - Answer Extend the boom sections.

When is the most important reason rigging hardware should not be modified? - Answer It could negatively affect its capacity In the term D/d ratio, the d is an abbreviation for? - Answer Diameter A document that outlines weights, crane configuration and rigging requirements for a lift is? - Answer Lift plan When using a 1-inch wire rope sling in a vertical basket hitch lifting a 24 ft, 36 inch diameter pipe - Answer 36- What is an LMI - Answer Load moment indicator Location of electrical hazards on the job site should be documented on a: - Answer Lift plan When forming a lift plan, a primary concern for the person doing the rigging is: - Answer Capacity of rigging When using a wedge socket, the dead end of the rope is secured in the socket by the: - Answer Wedge When erecting or stowing a swing-away lattice extension, what should be used to control the movement of the extension? - Answer Tag line Planning for rigging is required: - Answer Only when lifting any load A lift plan must be completed by a: - Answer Supervisor Anchorage point for fall arrest for a single person must be able to hold? - Answer 5000 lbs. When of the following items are used for heavy rigging? - Answer Slings, shackles and spreader beam If the jacket of a synthetic round sling is damaged, that sling should be: - Answer removed from service immediately Which of the following is not a factor when making submerged lifts? - Answer water temperature When a tugger is mounted where the operator can NOT see the load, the signal person must use: - Answer Signals used for cranes Who can design a personnel platform? - Answer Qualified personnel

A one inch, 3 leg bridle wire rope sling rigged at 45° angle is good for 18 tons. The addition of a fourth leg will increase your capacity by: - Answer 0 lbs After any structural repair or modification, a personnel lifting platform shall be tested to what percentage of the platform rating? - Answer 150% All of the following statements about crane contact to power lines are true EXCEPT: - Answer The operator should leave the cab as quickly as possible Loads introduced into the machine or its components due to accelerating or decelerating force is called: - Answer Dynamic loading When lifting 100,000 lb, the main load block must be reeved with how many parts of line? - Answer 4 In a multiple-crane lift using an equalizer, the weight of the equalizer is considered part of the - Answer load weight To read a lattice boom crawler crane load/capacity chart, the operator must first know the - Answer boom length and load radius Equipment condition is categorized under which part of a lift plan? - Answer Weight The person in charge of planning a critical lift is the: - Answer Rigging superintedant During a critical lift, the only person(s) who may give signals to the crane operator is/are the: - Answer designated, qualified signalers Sling lengths need to be long enough to ensure that the horizontal angle is greater than:

  • Answer The device used as an alternative to a freestanding tower crane where lower erection height allows its use is a - Answer On multiple-crane lifts, the load on each crane should be no more than: - Answer The net capacity of crane one is 130,000 lbs. The net capacity of crane two is 90, lbs. The weight of the load is 145,000 lbs. The weight of the equalizer beam is 3000 lbs. The distance between the hook blocks is 25 ft. The loads pickup point on the equalizer beam is: - Answer If the gross capacity of a crane is 75,000 lbs. and the total weight of the deductions is 4500 lbs. The net capacity of the crane in this configuration is: - Answer If the net capacity of a crane in a particular configuration is 85,000 lbs and the total weight of deductions is 6,400 lbs, the gross capacity is: - Answer